Professional Documents
Culture Documents
Unit 2 - Rate Analysis
Unit 2 - Rate Analysis
2
QUANTITY FOR RATE ANALYSIS
Generally quantities taken for the rate analysis are as
follows:
• For mass works: 10cu.m (example: cement concrete
work, stone and brick masonry work, etc).
• For surface works: 100sq.m (example: pointing,
plastering, flooring, etc).
• For running meter works: 100RM (example: pipeline
works, etc).
• For unit quantity works: 1 number (example: fixing of
plumbing items such as wash basin, w.c. urinals, etc).
3
Factors affecting the rate analysis
The rate of an item of work mainly depends on the following factors.
• Specification of the item which indicates the qualities and
proportion of materials, the methods of construction.
• The present rate of materials.
• Daily wages of different categories of labor and their respective
outputs.
• The range of lead and lift requires (ground floor or fist floor, etc).
• Profits and miscellaneous and overhead expenses of contractor.
• Site condition, site organization and cost control during
execution, etc.
The rate analysis of some common items is worked out by adopting
the rates of materials and labor prevailing in T/phu, P/ling, S/khar,
city in 2009. Students may use their local prevailing rates for rate
analysis.
4
Purpose of Rate Analysis
5
Schedule of Rates
• A schedule or list of rates of various items is prepared after the analysis of rates of these
items − Schedule of Rates (BSR 2021).
• It is prepared by large concerns or public bodies.
• It becomes very useful in deciding the rate of an extra item carried out by the
contractor.
• Normally, a clause in the conditions of contract is inserted, stating that: “Any extra item
that might occur during the execution of the work shall be paid as per rate in the
schedule of rates”.
• Comprises groups of items such as demolishing items, excavation items, concrete
items, brickwork items, etc. and also information regarding the present wages of labour
and process of different items is given in it.
• S.O.R vary and are periodically revised after every three years.
• The rates of the finished items are worked out by the analysis of rates with the
standard requirements of material, labour, and necessary sundries like water charges,
contractor’s profit, etc.
6
Task work per day:
• Represents the quantity of an item which an ordinary labourer of a particular
trade can do in a working day of eight hours.
• Thus, it depends on various variable factors such as type of labour, nature of
work, climatic conditions, situation of work, skill of labourer, site
organisation and many other factors often outside the control of the
contractor.
• The task work per day is also known as the labour constant and it is the most
uncertain part of rate analysis.
• The task work per day is calculated either by maintaining a record of labour
employed and the work done or by experience.
• The task work per day becomes useful in framing the rate of an item.
• It is, however, found that if the work is given on piece-work basis, the
efficiency of the labourer increases considerably and in some cases, the turn out
may be doubled than the task work per day under normal conditions for such
category of labourer.
7
Standardize unit quantity of materials
• 1 cu.m of Portland Cement = 1440 kgs
• 1cu.m of Portland cement =30 bags (normally taken)
• 1 bag of cement of 50 kg = 0.034 cu.m
• Nominal size of bricks = 20 cm x 10 cm x 10 cm
• No. of bricks per m³=500 nos
• Dry mortar volume =25%-30% wet mortar volume but
used 33%
8
Standardize unit quantity of materials cont…
Cement Concrete
Normally adopted values
Dry volume is taken 52.7% above wet volume
Dry volume = 1.527 x wet volume
Densities
Cement=1440 kg/ 𝑚3
Fine aggregate = 1450-1600 kg/ 𝑚3
Coarse aggregate= 1450-1500 kg/𝑚3
For example
Take M15 Concrete (1:2:4)
i)Cement=1
ii)Sand=2
iii)Aggregate=4
Total =1+2+4=7
9
Standardize unit quantity of materials cont…
CEMENT
• 𝐦𝟑 : Cement = 1 𝑥 1.527/7=0.22 𝑚3
• kg: Cement = 1 𝑥 1.527/7 x 1440 =312.7 kg
• Cft: Cement=1 𝑥 1.527/7 x 35.3147=7.66 cft
10
Standardize unit quantity of materials cont…
SAND
• 𝐦𝟑 : Sand = 2𝑥1.527/7=0.43 𝑚3
• kg: Sand= 2 𝑥 1.527/7 x 1500 =651.43 kg
• Cft: Sand =2 𝑥 1.527/7 x 35.3147=15.34 cft
AGGREGATE
• 𝐦𝟑 : Aggregate = 4 𝑥 1.527/7=0.87 𝑚3
• kg: Aggregate= 4 𝑥 1.527/7 x 1500=1302.86 kg
• Cft: Aggregate =4 𝑥 1.527/7 x 35.3147=30.67 cft
11
Quantity of materials for 10 cu.m of concrete for different proportions (variation 5% allowed)
12
Standardize unit quantity of materials cont…
Cement Plaster
• Normally adopted values
• 12 mm thick inside and 20 mm thick outside with ratio 1:6 for wall
• 12 mm thick in ceiling with ratio 1:4
Densities
• Cement=1440 kg/ 𝑚3
• Fine aggregate = 1450-1600 kg/ 𝑚3
• For example
• Take volume of mortar in plaster as 1 m x 1 m x 12 mm thick plaster with ratio 1:6 of
wall
• i)Cement=1
• ii)Sand=6
Total =1+6=7 13
Standardize unit quantity of materials cont…
Cement Plaster
• Total volume of mortar in plaster = 1 x 1 x 0.012=0.012 𝑚3
• Total dry volume=0.012 x 1.33=0.015967 𝑚3
For example
• Take volume of mortar for plaster as 1 m x 1 m x 0.012 m thick plaster with ratio 1:6 for wall
• i)Cement=1
• ii)Sand=6
Total =1+6=7
CEMENT
• 𝐦𝟑 : Cement = 1/7𝑥0.015967=0.00228 𝑚3
• kg: Cement = 1/7 𝑥 0.015967 x 1440 =3.28 kg =0.0656 bags
• Cft: Cement=1/7 𝑥 0.015967 x 35.3147=0.081 cft
SAND
• 𝐦𝟑 : Cement = 6/7 𝑥 0.015967=0.01368 𝑚3
• kg: Cement = 6/7 𝑥 0.015967 x 1500 =20.52 kg
• Cft: Cement=6/7 𝑥 0.015967 x 35.3147=0.483 cft
14
Standardize unit quantity of materials cont…
Brickwork
Normally adopted values
• Modular brick size=190 mm x 90 mm x 90 mm with ratio 1:6
• Mortar thickness = 10 mm
Densities
• Cement=1440 kg/ 𝑚3
• Fine aggregate = 1450-1600 kg/ 𝑚3
For example
• Take volume of brickwork=1 𝑚3
• Volume of 1 brick with mortar =0.200 x 0.100 x 0.100 = 0.002 𝑚3
• Cement=1
• Sand=6
Total = 1+6=7
No. of bricks in 1 𝑚3
=1/0.002=500𝑛𝑜𝑠
15
Standardize unit quantity of materials cont…
Brickwork
• Volume of 1 brick without mortar = 0.19 x 0.09 x 0.09=0.001539 𝑚3
• Volume covered by 500 nos of bricks =500 x 0.001539=0.7695 𝑚3
• Volume of mortar in wet condition = 1-0.7695=0.2305 𝑚3
• Dry volume of mortar = 0.2305 x 1.33=0.306565 𝑚3
• Dry mortar volume =1.33 x wet mortar volume
CEMENT
• 𝐦𝟑 : Cement = 1/7 𝑥 0.3065657=0.043795 𝑚3
• kg: Cement = 1/7 𝑥 0.3065657 x 1440 =63.065 kg =1.26 bags
• Cft: Cement=1/7 𝑥 0.365657 x 35.3147=1.5466 cft
SAND
• 𝐦𝟑 : Sand = 6/7 𝑥 0.3065657=0.26277 𝑚3
• kg: Sand = 6/7 𝑥 0.3065657 x 1440 =378.389 kg
• Cft: Sand=6/7 𝑥 0.3065657 x 35.3147=9.2796 cft
16
Standardize unit quantity of materials cont…
CEMENT CONCRETE
Calculation of materials
To determine the quantity of materials for 10 cu.m concrete is to divide
15.27 by the sum of the numerical of the proportion of the materials
which gives the quantity of cement in cu m.
For 1:2:4 proportion
• Summation of proportion=1+2+4=7
• Therefore, cement= 15.27/7=2.2 cu m
• Sand=2.2 x 2=4.4 cu m
• Coarse aggregate=2.2 x 4=8.8 cu.m
Note: 1 bag cement (50 kg) =0.0347 cu.m
• 2.2 cu.m=2.2/0.0347=63.4 bags.
17
Brick Work
First class brickwork in cement mortar 1:4 in superstructure, ground floor
Take 10 cu.m
Calculation of materials per 10 cu.m of brick work
• Number of bricks (with mortar 10 cm x 10 cm x 20 cm)=5000 nos
• Wet mortar=10 - (5000 x 0.09 x 0.09 x 0.19) = 2.30 cu.m.
Adding extra 15% for frog filling, brick bonding courses and
wastages, etc.
Volume of wet mortar=2.3+0.15*2.3=2.64 cu.m
• For dry mix mortar, adding 1/3rd extra
Therefore, volume of dry mortar=1.33 * 2.64 = 3.50 cu.m.
Cement and sand for 1:4 mortar
• Cement= (1/5) * 3.5=0.7 cu.m=21 bags
• Sand=0.7 * 4=2.8 cu.m
18
Flooring
C.C (1:4:8) flooring 75 mm thick
Take 100 sq.m
Calculation of materials:
• Volume of concrete=0.075 x 100=7.5 cu.m
• Adding 10% extra for unevenness of base concrete=7.5 + 0.10*7.5 =8.25 cu.m
• Adding 50% (1.527-1.54) extra for dry volume =8.25+0.5*8.25=12.375 cu.m
• Cement =(1/13)*12.375 =0.95 cu.m=27.40 bags
• Sand=0.95 x 4 =3.8 cu.m
• Course aggregate = 0.95 x 8=7.6 cu.m
19
Plastering
Analyze rate for 12 mm thick cement plastering 1:6 on new brick
work.
Take 100 sq.m
Calculation of materials:
• Volume of wet mortar= 0.012 x 100= 1.20 cu.m
• Adding extra 20% for filling the depressions, joints, wastage, etc.
• Volume of wet mortar=1.2 + 0.2 x 1.2=1.2=1.44 cu.m
• Volume of dry mortar, add 1/3 extra=1.44+ (1/3) *1.44=1.92 cu.m
• Cement=(1/7)*1.92 = 0.274 cu.m=8.2 bags
• Sand=0.274 x 6=1.64 cu.m
20
Materials required for cement plastering with different proportions
12mm thick plastering
20 mm thick plastering
53.85
Reinforcing Bars & Mesh -Thermo Mechanically
MT0208 1.05 kg 51.29
Treated Bars (TMT bars)
Total 66.33
6.63
Profit and overhead@ 10% of the total
Total Rate per kg 73.63
27
Coefficient for per
S.No BSR ref. Description Unit Rate(Nu.) Total(Nu.)
cu.m
31.40
Profit and overhead@ 10% of the total
Total Rate per sq.m 348.52
28
Coefficient for per
S.No BSR ref. Description Unit Rate(Nu.) Total(Nu.)
cu.m
P&L Second-Class Brick work in Foundation & Plinth
8 BW0001
-in cement mortar 1:3
Total 4810.05
481.00
Profit and overhead@ 10% of the total
Total Rate per cu.m
5,339.15
29
Coefficient for per
S.No BSR ref. Description Unit Rate(Nu.) Total(Nu.)
cu.m
Total 4234.05
423.41
Profit and overhead@ 10% of the total
Total Rate per cu.m 4699.80
30
31