Consultant :Al Rouya AL motakamela Eng. Con. Owner: Lulua saif al qallaf
PLOT:3768 AJMAN - yasmen CONTR: AL TASAMOH BUILDING CONTRACTING
PAMENT NO: 2 Total
NO DESCRIPTION OF WORK Unit Qty. Unit Cost Work Amount Done 1.0 Mobilization 1.1 Mobilization l.s 1 8000 50% 4000 Sub - Total of MobilizationWorks 4000 2.0 Earth Works 2.1 Excavation m3 559 100% 0 2.2 Road Base m3 73 100% 0 2.3 Back Filling Subgrade 50 cm m3 468 7 50% 1638 Sub - Total of Earth Works 1638 3.0 SUB-STRUCTURE WORKS PCC under Footing, Tie Beams, 3.1 m3 18 100% 0 Solid Blocks 3.2 RCC For footing+Raft m3 89 100% 0 3.3 Under Ground water tank l.s 1 14000 50% 7000 3.4 Bakary water tank l.s 1 8000 50% 4000 3.5 Neck column m3 4 100% 0 3.6 RCC Tie Beams m3 19 950 100% 18050 3.7 Strip beam m3 4 100% 0 3.8 Septin tank l.s 1 0 50% 0 Sub - Total of substructure Works 29050 4.0 Insulation works for concrete infrastructure 4.1 Anti MiteProtection l.s 1 2000 50% 1000 4.2 Insulation by Polythen Sheets l.s 1 1000 50% 500 Sub - Total of Superstructure Works 1500 5.0 SUPER STRUCTURE WORKS 5.1 RCC Columns m3 32 950 33% 10,032 5.2 RCC Slabs m3 129 950 33% 40,441 5.3 RCC Beams works m3 25 950 33% 7,837 5.4 RCC Parapet Wall and design m3 5 950 5.5 Middle Beam Concrete m3 0 0 0 5.6 Floor Concrete Workers 10cm FloorPCC19 500 100% 9500 Sub - Total of Superstructure Works 67810 6.0 BLOCK WORKS 6.1 Solid BLOCK work m2 186 100% 0 6.2 External Blocks Works m2 648 70 6.3 Internal 200mm Hollow Blocks Works m2 691 70 6.4 100mm Hollow Blocks Works m2 129 65 Sub - Total of Block Works 0 7.0 Isolation works Roof Insulation Works The roof 7.1 m2 188 90 combo system 7.2 Waterproofing works for bathrooms m2on the38first floor 60 and the roof Sub - Total of Isolation works 0 8.0 finishing works 8.1 Internal plaster workers m2 2288 18 8.2 External plaster work m2 810 23 8.3 Ceiling Plaster Works m2 115 20 8.4 skirting For Ceramics RM 250 0 Ceramic works Flate+ studio 8.5 m2 209 0 25aed 8.6 Threshold RM 40 0 8.7 Marble work Step 100aed RM 58 0 8.8 Marble Landing 100aed m2 15 0 8.90 Entrance Granet 100aed RM 7 0 8.10 Entrance Granet wall 100aed m2 32 0 8.11 lobby Landing 30aed m2 24 0 8.12 Wall lobby 25 aed m2 118 0 ceramic works for 8.13 Bath,Wash&Kitchen Floor 25 m2 48 0 aed Ceramic Work Kitchen & Bath 8.14 m2 358 0 Wall 25aed Ceramic works for Service 8.15 m2 60 0 20aed Ceramic works for25aed 8.16 m2 109 0 Bakery+shop+show room Ceramic wall works for Bakery 8.16 m2 102 0 25 aed Sub - Total of finishing works 0 9.0 Painting Works 9.1 External Paint National m2 810 33 9.2 Internal Paint-walls National m2 2288 18 9.3 Internal Paint CEILING m2 115 20 9.4 False ceiling works m2 59 60 9.5 lobby&coredor for false ceiling m2 27 60 Sub - Total of Painting Works 0.00 10.0 FLOOR Carpentry Works 10.1 Main Door PIC 1 3000 0 D2 room + w . Man + kitchen 10.2 PIC 10 1500 0 Door 10.3 Bath Door PIC 8 1200 0 10.4 pump doom PIC 1 2000 0 10.5 Bakery doom PIC 1 2000 0 10.6 Store PIC 2 1500 0 10.7 Carpeg door outsaide PIC 1 2000 0 10.8 Stair case door FRD 90 PIC 4 2000 0 10.9 Glass Door D6+D7 m2 31.3 500 0 10.1 Garbage Door PIC 2 1200 0 10.1 Telephone Room Door PIC 3 1500 0 10.1 Electrical Room door PIC 3 1500 0 10.1 Water meter Door PIC 3 1200 0 Sub - Total of Carpentry Works 0 11.0 Clading WORKS 0 11.1 Cladding Dicourtion for elevtion m2 29 100 Sub - Total of stone Works 0 12.0 ALUMINUM - METAL WORKS Aluminum and Glazing Works ( 12.1 M2 44.8 650 Double Glazed)) 12.6 Handrail works Rm 19.5 600 12.8 Kitchen Cabinet aluminum l.s 1 30877 Sub - Total of Aluminum and glass works 0 13.0 MANWHOLE WORKS 13.1 Total Monhole PCS 10 450 13.2 Interlock m2 208 0 0 13.3 Kerbstone RM 99 0 0 Total Works 0 14.0 Electricity WORKS 14.1 Electricity Works l.s 1 40000 5% 2000 14.2 C.C.T SYSTEM + T.V L.S 0 0 0 14.3 Etesalate ls 1 10000 Sub - Total of electricity works 2000 15.0 Air conditioning works 15.1 Air-conditioning repare l.s 1 0 0 Sub - Total of Air conditioning works 0 16.0 Sanitary WORKS 16.1 Sanitary WORKS ls 1 20000 5% 1000 16.2 accesaries no 7 1000 Sub - Total of Sewer and water works 1000 17.0 FIRE FIGHTING work 17.1 FIRE FIGHTING l.s 1 45000 5% 2250 Sub - Total of Additional work 2250 18.0 LIFT WORKS 18.1 LIFT l.s 0 0 0 Sub - Total of LIFT work 0 Total Amount of the Works 109,248 Total Amount of Done Work Discount 05% Retaintion 5% 5,462 Discount 15% Advanced Payment 15% 16,387 Discount Previous Payments Total Amount of Deduction Amount of The Net Payment 87,399 Vat @ 5% 4,370 Amount of The Payment 91,769