Professional Documents
Culture Documents
CL-NG-6460-002-019 Checklist For Oil-Immersed Shunt Reactor Rev02
CL-NG-6460-002-019 Checklist For Oil-Immersed Shunt Reactor Rev02
APPROVED
1. Equipment General Data and Information 13 APRIL 2022
Substation
Bay/Panel
Equipment Serial No
2. Visual Inspection
11. Perform Surge Arrestors Tests as per the latest revision of WI-
NG-6460-002-020.
12. Measure zero-sequence impedance.
13. Measure the Insulation resistance of control wires (the test
voltage should be a minimum of 500 V dc one minute).
Check online gas analyzer device (If specified in the data
Schedule) :
14. a. Check readings of each fault gas as per data schedule.
b. Check alarms of fault Gases and their settings.
c. Check the online DGA monitor is integrated with SAS.
15. Check that the tank pressure is positive. (if applicable)
16. Oil Dielectric Strength (Break Down Voltage)
Perform the Oil Leakage Test:
The Reactor tank and accessories shall withstand operating
pressure due to the oil preservation system, i.e. oil in the tank
17. and conservator, plus an additional pressure of 30 kPa for 24
hours. Oil leakage shall not be observed during this period.
Operating pressure (kPa) due to the oil preservation system
shall be stated in the test report.
Oil Test:
a. Before proceeding to the end of commissioning as per PR-
NG-6460-002 Project Commissioning procedure, ensure that
the CONTRACTOR followed the manufacturer's instructions
for taking oil samples from (Oil sampling valves of main tank
(Top & Bottom) – OLTC – cable boxes if applicable &
Conservator). Ensure that the samples were not collected
before 48 h after the transformer is filled.
b. Ensure that the submitted report from the CONTRACTOR is
for insulation samples tested in an approved independent lab
according to the latest revision of the approved labs list.
18. c. Ensure that the lab report states clearly the following:-
i. Criteria of each test result.
ii. Actual result of each test.
iii. Clearly state whether the values are within the criteria
limits.
iv. Assessments of each test.
v. Assessment of the oil sample (Accepted – Not Accepted).
vi. Recommendations.
d. Ensure that the lab report contains at least the results of the
following tests:-
i. Appearance
ii. Color
iii. Dielectric Strength (Break Down Voltage)
NATIONAL GRID SA
diagram.
Check all wiring and ensure that each end of every wiring
leaving a terminal block is identified indicating local termination
7.
point and distant termination point as per the approved
drawings.
Ensure that all trip circuits are provided with a red ferrule at the
8.
terminal block.
Ensure that all AC circuit terminals and DC power terminals are
fitted with non-inflammable, transparent plastic covers to prevent
accidental contact with live parts. Each incoming and outgoing
9.
conductor is connected to an individual terminal through size 1
hooked crimps or ring-type terminals. Ensure that no termination
of more than one conductor at one terminal point.
Check that the DC supervision is not disturbed in both
mechanical protection selector In/Out positions and check all
10.
related alarms and all SAS indications, alarms and
measurements.
Check AC supervision and check all related alarms and all SAS
indications, alarms and measurements.
11.
Ensure that Humidity/thermometers for the heater of the local
panel are at correct settings.
Ensure that Additional 20% spare terminals of each
12. category/type are provided on the terminal blocks adjacent to
used terminals to accommodate future requirements.
Check MCBs in the marshaling kiosk by current injection (as per
13.
manufacturer manual).
Check the current and voltage ratings of all motors for tap
changer, oil filtering unit, and fans are matched with SEC
14.
standard supply. And all MCBs are at proper overload settings
(As per the manufacturer manual).
Measure fan motor current (starting, running, one phase removal
and locked rotor) and check against rating. Check if wiring size
15.
is suitable to carry the current. Check vibration, sound and
proper position of fan blade shield (cover).
Check the operation of fans automatic, manual, local and remote
16. positions and check all related alarms and all SAS indications,
alarms and measurements.
Check fan running direction to get airflow towards radiator and
17. phase sequence of the supply voltage to fan motors circuits is
correct.
Check the supply changeover for fan motor circuit during AC
MCB trip and Main source failure (under-voltage condition) and
18.
check all related alarms and all SAS indications, alarms and
measurements.
19. Perform the functional check for the following and check all
NATIONAL GRID SA