WORK INSTRUCTION Control Number REV History Established Date

Lathe Machine COP-IPODS-W-PR-01-01 Rev.00 September 5,2023


Step 1 Step 2 Step 3 WORKING PROCEDURE

Note : Always perform 5s before and after work

1. Set-up the machine.


2. Review drawing and prcoess requirements.
3. Check the machine parts and tool holder.
4. Set-up the workpiece to be cut.
5. Check and set-up cutting tools to be use.
6. Switch "ON" the power.
Step 6 Step 5 Step 4 7. Push start button for process operation.
8. Remove workpiece.
9. Check and measure workpiece for the required
10. Fill up Traveller Card.

SAFETY REMINDER

● Environmental / Work place Cleaning.


Step 7 Step 8 Step 9 ● Check Switch / Emergency switches.
● Concentrate while setting.
● Keep thing at designated place after use.

Machine Checklist

Daily Production Report


Step 10

Equipment Preventive Maintenance Schedule