EEBA-PCF Cost Estimates
EEBA-PCF Cost Estimates
DIRECT COST
% of Total Cost Cost
Material 55% of (A, B) Php 25,289,385
Labor 45% of (A, B) Php 26,691,315
Total Cost Php 51,980,700
ENGINEERING COST ANALYSIS
Percentage (%) Estimated Cost
Project Building Cost N/A Php 26,560,700
Site Development Cost N/A Php 19, 420,000
Legal Expense 2.5% of PDC Php 664,017.50
Bond Expense 1.5% of PDC Php 398,410.50
Architects Fee 10% of PDC Php 2,656,070
Contingency Cost 10% of PDC Php 2,656,070
Interest During Construction 5% of PDC Php 1,328,035
Total Project Construction Cost Php 53,683,303