Professional Documents
Culture Documents
Generation Scheduling With Integration of Wind Power and Compressed Air Energy Storage
Generation Scheduling With Integration of Wind Power and Compressed Air Energy Storage
I. NOMENCLATURE FLmax
l Maximum line flow
T Number of hours for the scheduling period Vbbs ,t Voltage magnitude at bus bs
I Set of thermal units Vbbsmax , Vbbsmin Maximum/minimum voltage magnitude at bus bs
Nb Number of buses Ak ,t +1 Inventory level at time t+1
L Number of lines Ak ,t Inventory level at time t
i Denote a thermal unit
k Denote a CAES unit Amax (h) Maximum capacity of the carven in MWh
w Denote a wind unit Amin (h) Minimum capacity of the carven in MWh
t Time index ν kinj,t Amount of injected air in MW at hour t
l Line index
bs Bus index
ν kw,t Amount of released air in MW at hour t
w
u i ,t Unit status indicator (1 is ON and 0 is OFF) v k ,min Minimum amount of released air in MW
y i ,t Startup indicator vkw,max Maximum amount of released air in MW
z i ,t Shutdown indicator v inj
Minimum amount of injected air in MW
k ,min
Fi ,t Production cost function of unit i
vkinj,max Maximum amount of injected air in MW
Pi ,t Generation of a unit
α w
k Efficiency factor for producing power
Pi ,min , Pi ,max Minimum/maximum generating capacity
α inj
k Efficiency factor for injecting air
MU i , MDi Minimum up/down time of a unit
II. INTRODUCTION
Hossein Daneshi is with the Electric Power and Power Electronic Center
at Illinois Institute of Technology, Chicago, IL, 60616, USA (e-mail:
danehos@iit.edu)
Anurag K Srivastava is with the Department of Electrical and Computer
M arket operators in various Independent System
Operators (ISO) apply the standard market design
(SMD) for scheduling a secure and economically
Engineering at Mississippi State University, USA (e-mail: viable power generation for the day-ahead electricity market.
srivastava@ece.msstate.edu) One of the key components of SMD is security-constrained
number of cycles without degradation. They are relatively • High thermal efficiency in the production mode
expensive compare to other energy storage technologies. • A CAES is able to ramp up 2 to 3 times faster than other
Superconducting magnetic energy storage (SMES): stores gas-fired plants because it is not restrained by
energy in a magnetic field by direct current flowing in a compression requirements.
superconducting coil, that has been cryogenically cooled. The
advantage of SMES is its fast response, and short charge and IV. SCUC FORMULATION WITH CAES
discharge time. Power is available almost instantaneously and As mentioned, the objective of SCUC is to determine an
very high power output can be provided for a brief period of optimum schedule of generating units for minimizing the cost
time. The energy content of SMES systems is quite small and of supplying energy and ancillary services constrained by
the cryogenics (cold temperature technology) can be a security requirement. Spinning and non-spinning reserves are
challenge. modeled in this paper while other types of ancillary services
Batteries: Batteries are made of stacked cells where-in such as regulation up/down and placement services could be
chemical energy is converted to electrical energy and vice modeled similarly [6]. The objective function is formulated as
versa. The desired battery voltage and current requirements is
follow:
obtained by electrically connecting the cells in series and T
⎧ I K
⎫
parallel. The batteries are rated in terms of their energy, Min ∑ ⎨∑ [C ( Pi ,t ) + STi ,t + SDi ,t ] + ∑ C ( Pk ,t )⎬ (1)
capacity, efficiency, life span (stated in terms of number of t =1 ⎩ i =1 k =1 ⎭
cycles), operating temperature, charge, and discharge rate. Where the first term represents thermal operating cost
Reference [9] discusses the present status of battery energy including fuel, startup and shutdown costs; the second term
storage technology and methods of assessing their economic represents the operating cost of CAES units over the given
viability and impact on power system operation.
period. The list of symbols is presented in the Nomenclature
Compressed air energy storage (CAES): has been in use as
section I.
a peak shaving option since 1970s. It is a low cost technology
The constraints listed next include the system energy
for storing large quantities of electrical energy in the form of
high-pressure air. CAES operates like a gas turbine except balance (2), required system spinning (3) and operating
that compression and expansion cycles occur at different reserve (4), ramping limits (5-a), (5-b), minimum On/Off time
times. In a regular gas turbine two thirds of the output power limits (6-a), (6-b), and real and reactive power generation
from the expansion is used to run the compressor. limits (7), (8), transmission line flow limit (9), bus voltage
The first CAES plant, a 290 MW facility, was started in limit (10). Additional system and unit constraints can be
Huntorf, Germany in 1978. It was designed and built to modeled easily, which is not the scope of this paper.
provide black-start services to nuclear units near the North I K
Sea and provide peak power. It has the storage capacity to ∑P +∑P
i =1
i ,t
k =1
k ,t + W (t ) = PD (t ) + PL (t ) ∀t (2)
generate for 2-3 hours per cycle [10]. I K
A 110 MW plant commenced operation in McIntosh,
Alabama in 1991. The McIntosh plant made improvements to
∑ rs
i =1
i ,t + ∑ rs
k =1
k ,t ≥ RS (t ) ∀t (3)
v w
k ,min .u k ,t ≤ v w
k ,t ≤v w
k ,max .u k ,t (14) TABLE II: PARAMETERS OF THERMAL UNITS
Unit G1 G2 G3 G4
v inj
.u c
≤v inj
≤v inj
.u c
(15) Bus 2 3 6 7
k ,min k ,t k ,t k ,max k ,t
A 0.012 0.0014 0.0085 0.0046
In compressing mode, the amount of compressed air is B 8.66 9.66 19 12.69
limited to the maximum capacity of the cavern minus the C 190 230 270 250
current inventory level. Pmin 50 50 10 20
Pmax 200 150 50 100
Ak ,t +1 = Ak ,t + vkinj,t − vkw,t , ∀k , ∀t (16) ST 1600 1500 500 500
Ramp up 0.83 0.83 1.66 2.92
Amin (k ) ≤ Ak ,t ≤ Amax (k ) , ∀k , ∀t (17) Min On 8 8 1 1
Min Off 8 8 1 1
Mathematically SCUC is a decision problem with an IniT 8 8 -1 -1
objective to be minimized with respect to a series of TABLE III: TRANSMISSION LINE PARAMETERS
prevailing equality and inequality constraints. The problem is Line From To Line Limit
a mixed-integer problem and includes a large number of X (pu)
No Bus Bus (MW)
integer and continuous variables. A common way of solving 1 1 2 0.03 200
MIP problem is to relax some coupling constraint and 2 1 4 0.03 200
decompose it into several sub problems. Many commercial 3 1 7 0.0065 200
4 2 3 0.011 200
packages such as CPLEX, LINDO, OSL and XPRESS-MP
5 5 1 0.03 200
exist in the market place have been successfully applied to UC 6 4 5 0.03 200
problems. In this paper, we use CPLEX to solve the problem. 7 5 6 0.02 200
8 6 7 0.025 200
9 7 8 0.015 200
10 8 3 0.022 200
5
TABLE IV: FORECASTED LOAD DEMAND AND WIND POWER TABLE VI: GENERATION DISPATCH WITHOUT CAES
Wind Load Wind Load Without CAES
Hour Hour
(MW) (MW) (MW) (MW) Unit G1 G2 G3 G4
1 58.27 377.80 13 10.80 416.86 1 200 120.9 0 0
2 82.12 365.92 14 12.50 408.60 2 200 84.4 0 0
3 89.22 362.86 15 15.00 402.84 3 200 74.0 0 0
4 84.73 363.11 16 21.62 401.67 4 200 78.8 0 0
5 77.25 370.56 17 15.00 406.20 5 200 94.2 0 0
6 65.13 386.83 18 10.88 431.55 6 200 123.8 0 0
7 75.91 411.61 19 14.50 468.17 7 200 115.7 0 20
8 200 129.6 0 20
8 71.55 421.20 20 12.54 477.40
9 200 135.5 0 20
9 73.40 428.95 21 16.00 480.00
10 200 138.5 0 47.5
10 49.11 435.17 22 28.41 465.26 200 138.8 0 62.6
11
11 30.71 432.06 23 30.34 439.86 12 200 139.3 0 67.5
12 18.09 424.82 24 37.10 409.72 13 200 139.8 0 66.2
14 200 140.4 0 55.7
1) Case 1: SCUC result without CAES 15 200 140.8 0 47.0
16 200 140.9 0 39.2
In this case, we assume there is no CAES. The 24-hour 17 200 140.6 0 50.6
system load and wind profile are listed in Table IV in which 18 200 146.8 10 63.9
the peak load is 480 MW at hour 21. We solve the SCUC and 19 200 144.2 28.4 81
determine the commitment and dispatch of units given in 20 200 143.6 40.3 81
Table V and VI, respectively. It is assumed that the fuel price 21 200 143.4 39.6 81
is 1 $/MBtu and spinning reserve is 7% of the load, we also 22 200 144.4 11.4 81
exclude transmission line limit. 23 200 146.2 10 53.3
The cheaper units G1 and G2 are always committed. The 24 200 140.3 0 32.3
more expensive unit G3 is committed between hours 11 and
23 to supply the generating capacity requirement. Total TABLE VII: SCUC RESULT WITH CAES
Total Cost = $100,881.2
operating cost is $105,551.2.
Unit Hours (0-24)
2) Case 2: SCUC result with CAES G1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
G2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
To observe the impact of CAES, we add a CAES unit at bus G3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 in which wind is located. The characteristic of CAES is G4 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
presented in Table I. The maximum power output from CAES
TABLE VIII: GENERATION DISPATCH WITH CAES
is 50 MW. The efficiency factors ( α kw , α kinj ) for compress
With CAES
and discharge are 1. The load and wind profile are same as Unit G1 G2 G3 G4 S
Case 1. Table VII presents the unit commitment with CAES 1 200 121.0 0 0 0
for 24 hours. 2 200 125.0 0 0 -40.6
First, we take a look at the scheduling results of the CAES 3 200 124.0 0 0 -50.0
unit in Table VIII. In this table, positive numbers correspond 4 200 125.0 0 0 -46.2
to periods for compressing air, while negative numbers are 5 200 125.0 0 0 -30.8
discharging or generating periods. According to the daily load 6 200 123.8 0 0 0.0
profile with two peak loads, wind power and power from grid 7 200 125.0 0 0 14.5
will help in compressing the air during the off-peak, when 8 200 125.0 0 0 29.1
hourly loads are relatively low. Then during the peak load, 9 200 125.0 0 0 35.6
CAES will supply the load. 10 200 138.5 0 20.0 27.5
In this case, the expensive unit G3 is not dispatched. Lower 11 200 138.8 0 62.6 0.0
operating cost of $100,881.2 is obtained in Case 2 when 12 200 139.3 0 73.3 -5.9
CAES unit is added compared to higher cost in Case 1 before 13 200 139.8 0 73.3 -7.1
14 200 140.4 0 50.7 5.0
adding CAES. These results show the lower cost of using
15 200 140.8 0 52.0 -5.0
CAES for supplying the load in the system. In our analysis,
16 200 140.9 0 72.5 -33.3
we are not considering the comparative capital investment for 17 200 140.6 0 73.3 -22.7
the installation of CAES. 18 200 138.8 0 73.3 8.6
TABLE V: SCUC RESULT WITHOUT CAES 19 200 136.2 0 73.3 44.1
Total Cost = $105,551.2 20 200 135.6 0 79.3 50.0
Unit Hours (0-24) 21 200 135.4 0 78.6 50.0
G1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 200 136.4 0 73.3 27.1
22
G2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
23 200 138.2 0 71.3 0.0
G3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 0
24 200 140.3 0 32.3 0.0
G4 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6
VI. CONCLUSION
A MIP based SCUC problem including wind and CAES
unit is described in this paper. The case studies based on an 8-
bus test system indicate that the application of CAES can
impact the peak load reduction, system operating cost,
commitment and dispatch of the units. Much of the benefits
listed here will depend on the MW size of the CAES. The
example on 8-bus system showed the effectiveness of the
proposed model.
VII. REFERENCES
[1] J. Wood, F. Wollenberg, “Power Generation Operation and Control”,
John Wiley and Sons, 1996.
[2] M.Shahidehpour, H.Yamin, Z.Li, “Market Operations in Electric Power
Systems”, John Wiley and Sons, 2002.
[3] J. J. Shaw,“A direct method for security-constrained unit commitment”,
IEEE transactions on power systems, Vol.10, No.3, Aug 1995.
[4] Y. Fu, M. Shahidehpour, “Security-constrained unit commitment with
AC constraints”, IEEE transactions on power systems, Vol.20, No.2,
May 2005.
[5] H. Ma, M. Shahidehpour, “Unit commitment with transmission security
and voltage constraints”, IEEE transactions on power systems, Vol.14,
No.2, May 1999.
[6] Z. Li, M. Shahidehpour, “Security-constrained unit commitment for
simultaneous clearing of energy and ancillary services markets”, IEEE
transactions on power systems, Vol.20, No.2, May 2005.
[7] T. Li, M. Shahidehpour, “Price-based unit commitment: a case of
Lagrangian relaxation versus mixed integer programming”, IEEE
transactions on power systems, Vol.20, No.4, November 2005.
[8] US Department of Energy: http://www.eere.energy.gov
[9] K.C. Divya, Jacob Ostergaard, “Battery energy storage technology for
power systems – An overview”, Electric Power Systems Research, Dec
2008.
[10] O. Weber, "Air-Storage gas turbine power station at Huntorf," Brown
Boveri Review, vol. 62, 1975.
[11] V. De Biasi, "110 MW McIntosh CAES plant over 90% availability and
95% reliability," Gas Turbine World, vol. 28, 1998.
[12] Iowa Stored Energy Park. 2007. http://www.isepa.com
[13] D. J. Swinder, “Compressed air energy storage in an electricity system
with significant wind power generation”, IEEE transactions on energy
conversion, Vol.22, No.1, March 2007.
[14] L. A. Schienbein, “Energy storage and wind energy conversion
systems”, International Journal Global Energy Issues, Vol.9, No.3,
1997.