Ensure the Testing and Commissioning shall be done with 4 Approved MS & MAS. 5 Proper Tagging & Labelling All live parts screened with an insulating plate or earthed 6 metal.
7 Phase identification provided on the distribution board.
VISUAL INSPECTION 8 All exposed metal parts effectively earthed. All metal conduits, trunking, switch boxes and exposed 9 metal parts effectively earthed. All non-armored cables susceptible to damage protected 10 with steel conduit/ trunking. Bushing and rubber grommet, where necessary, provided. Conductor sized to suit the rating of the FUSE / MCB 11 protecting the circuit. All joints of metal conduits or trunking to be mechanically 12 sound, electrically continuous and protected against corrosion.
13 All exposed conductive parts effectively earthed.
14 Panel Door Earthing Shall be done.
15 DB Incoming Cable Tagging shall be done.
16 Insulation resistance of not less than 0.5 M ohm
measured between phases/neutral/ earth. 17 Checking of Voltage on O/G Power Circuit T&C 18 Checking of Phase Sequence. 19 Checking of (MCCB's) ON/OFF and Manual Trip Test