Professional Documents
Culture Documents
Psoc Unit IV Fat II
Psoc Unit IV Fat II
EE18601-PSOC VENKATESAN C
1
ASP/EEE/SVCE
Formulation of economic dispatch problem
EE18601-PSOC VENKATESAN C
3
ASP/EEE/SVCE
Formulation of Economic Dispatch Problem
EE18601-PSOC VENKATESAN C
4
ASP/EEE/SVCE
I/O Cost Characterization
• The total generator operating cost includes fuel cost, cost of
transmission loss, labour and maintenance costs
• For simplicity, Fuel Cost is the only one considered to be
variable
• The fuel cost is meaningful in case of thermal and nuclear
stations, but for hydro stations, where the energy storage is
apparently free, it is not meaningful
• Cost of generation depends on the following Operating or
System Constraints
i. Equality constraint (Generation = Demand + Losses)
ii. Inequality constraints
EE18601-PSOC VENKATESAN C
5
ASP/EEE/SVCE
I/O Cost Characterization
• The Inequality constraints are further subdivided into
a) Generator constraints
b) Voltage constraints
c) Running space capacity constraints
d) Transformer tap settings
e) Transmission line constraints
f) Network security, etc.
EE18601-PSOC VENKATESAN C
6
ASP/EEE/SVCE
Incremental Cost Curve
• The Input-output curve of a generating unit specifies the input
energy rate, Fi(PGi) (kcal/hr) or cost of fuel used per hour Ci (PGi)
(Rs/hr) as a function of generator power output PGi (MW).
EE18601-PSOC VENKATESAN C
7
ASP/EEE/SVCE
Incremental Cost Curve
• The input-output curve can be determined
experimentally.
• It is convenient to express the input-output curves
interms of input energy rate (kcal/hr) rather than fuel
cost per hour (Rs/hr) because fuel cost can change
monthly or daily.
• In Fig. MWmin is the minimum loading limit below which
it is uneconomical (or may be technically infeasible) to
operate the unit and MWmax is the maximum output limit
• [NOTE: Power or Energy Units can be in Mega (M) or Kilo
(k) units]
EE18601-PSOC VENKATESAN C
8
ASP/EEE/SVCE
Heat rate Curve
→ (1)
EE18601-PSOC VENKATESAN C
11
ASP/EEE/SVCE
Incremental Cost Curve
• The slope of the fuel-cost curve, i.e. dCi(PGi)/dPGi is called the
Incremental Fuel Cost (IC), and is expressed in Rs/MWh
• A typical plot of the IC vs Power output is shown in Fig.
EE18601-PSOC VENKATESAN C
12
ASP/EEE/SVCE
Incremental Cost Curve
The assumptions of incremental cost theory are:
➢ Input-output curves are continuous
➢ First derivative of input-output curves are also continuous
➢ The incremental rate increases with increase in input
• From eqn. (1) Ci(PGi) = ai PGi2 + bi PGi + ci Rs/hr
• Slope of the fuel-cost curve, = dCi(PGi)/dPGi
= 2aiPGi + bi (Rs/MWh)
• This is a linear relationship (shown as dotted line in Fig.)
• The economic optimum load distribution is obtained when all
the generator units operate at the “equal incremental rate”
EE18601-PSOC VENKATESAN C
13
ASP/EEE/SVCE
Incremental Cost Curve
• The incremental cost curve for a thermal power plant is
EE18601-PSOC VENKATESAN C
14
ASP/EEE/SVCE
Incremental Cost Curve
• The input-output curve and incremental cost curve for hydro
power plant is
EE18601-PSOC VENKATESAN C
15
ASP/EEE/SVCE
Incremental Cost Curve
EE18601-PSOC VENKATESAN C
16
ASP/EEE/SVCE
Incremental Cost Curve
• The fuel-cost curve and the incremental cost curve may have
a number of discontinuities, as shown in Fig.
• The discontinuities occur when the output power has to be
extended by using additional boilers, steam condensers or
other equipments.
• Discontinuities also appear if the cost represents the
operation of an entire power station, so that the cost has
discontinuities on paralleling of generators
• Within the continuity range, the IC may be expressed by a
number of short line segments (piecewise linearization)
• Alternatively, we can fit a polynomial of suitable degree to
represent the IC curve in the inverse form as,
EE18601-PSOC VENKATESAN C
17
ASP/EEE/SVCE
Co-ordination Equations without Loss
Optimal division of load between Two machines:
• Let PT be the total output of the two machines
• The problem is to find the optimal division of load between
the two machines
• Let P1 = Power output of machine 1 (MW)
P2 = Power output of machine 2 (MW)
C1 = Fuel cost of machine 1 (Rs/hr)
C2 = Fuel cost of machine 2 (Rs/hr)
CT = Total Fuel cost (Rs/hr)
EE18601-PSOC VENKATESAN C
18
ASP/EEE/SVCE
Co-ordination Equations without Loss
• If the losses in the transmission network are neglected
Total output, PT = P1 + P2
Total cost, C T = C1 + C2
• The total power output PT is equal to active power demand
and is constant
• It is desired to find the values of P1 and P2 such that CT is
minimum for a given value of PT
→ (1)
EE18601-PSOC VENKATESAN C
19
ASP/EEE/SVCE
Co-ordination Equations without Loss
• As P1 = PT – P2
dP1 = -dP2 (since dPT = 0) → (2)
EE18601-PSOC VENKATESAN C
20
ASP/EEE/SVCE
Co-ordination Equations without Loss
Large no. of Units:
• Here the loads should be so allocated among the different
units that every unit operates at the same incremental cost
• For a plant with ‘k’ units
EE18601-PSOC VENKATESAN C
21
ASP/EEE/SVCE
Co-ordination Equations without Loss
• Our aim is to find P1, P2 ….. Pk such that CT is minimum
• The input or cost of a unit is dependent only on the output of
that unit
EE18601-PSOC VENKATESAN C
22
ASP/EEE/SVCE
Co-ordination Equations without Loss
• This equation is satisfied only if each term is zero
• For n = 2, 3, ….., k
EE18601-PSOC VENKATESAN C
23
ASP/EEE/SVCE
Co-ordination Equations without Loss
1. The incremental cost in Rs./MWhr of two 250 MW units are
as under:
EE18601-PSOC VENKATESAN C
24
ASP/EEE/SVCE
Co-ordination Equations without Loss
EE18601-PSOC VENKATESAN C
25
ASP/EEE/SVCE
Co-ordination Equations without Loss
2 4
EE18601-PSOC VENKATESAN C
26
ASP/EEE/SVCE
Co-ordination Equations without Loss
EE18601-PSOC VENKATESAN C
27
ASP/EEE/SVCE
Solution by Direct Method
1. Analytical Method
• Cost function, Ci = aiPGi2 + biPGi + ci
• Using equal incremental cost, find = dCi/dPGi
= 2aiPGi + bi (Rs/MWhr)
EE18601-PSOC VENKATESAN C
28
ASP/EEE/SVCE
Solution by Direct Method
EE18601-PSOC VENKATESAN C
29
ASP/EEE/SVCE
Solution by Direct Method
2. Graphical Method
• In this method, the incremental cost of each generator is
plotted on the same graph as shown in fig.
EE18601-PSOC VENKATESAN C
30
ASP/EEE/SVCE
Solution by Direct Method
• Various values of (increase or decrease line) are tried till
PGi = total load to be supplied (PD)
EE18601-PSOC VENKATESAN C
31
ASP/EEE/SVCE
Solution by Direct Method
3. Iterative technique using the Gradient method
• Let f() = PD, expand using Taylor’s series,
EE18601-PSOC VENKATESAN C
32
ASP/EEE/SVCE
Significance of Equality and Inequality
Constraints
Equality constraints:
EE18601-PSOC VENKATESAN C
33
ASP/EEE/SVCE
Solution by -Iteration Method
without Loss
Case (i): Operating limits for power generation are not specified
• Step 1: Calculate using
• Step 3: Compute
EE18601-PSOC VENKATESAN C
34
ASP/EEE/SVCE
Solution by -Iteration Method
without Loss
• Step 4: Check the power balance equation,
EE18601-PSOC VENKATESAN C
35
ASP/EEE/SVCE
Solution by -Iteration Method
without Loss
• Case (ii) Operating limits for power generation and the
production cost function are given
• Step 1: Calculate using
EE18601-PSOC VENKATESAN C
36
ASP/EEE/SVCE
Solution by -Iteration Method
without Loss
• Step 3: If the computed PGi satisfy the operating limits,
PGi,min PGi PGi, max for i = 1, 2,……………, N
then the optimum solution is obtained, otherwise go to the
next step
• Step 4: If PGi violates the operating limits, then fix the
generation at the respective limit
EE18601-PSOC VENKATESAN C
37
ASP/EEE/SVCE
Solution by -Iteration Method
without Loss
• Step 6: Compute new using PD new and compute the remaining
generations using
EE18601-PSOC VENKATESAN C
38
ASP/EEE/SVCE
Solution by -Iteration Method
without Loss
• If the condition is satisfied, then stop. Otherwise release the
generation schedule fixed at PGi,min or PGi, max of those units
not satisfying the optimality condition
• Include these units in the remaining units and modify the new
power demand (PD new)
EE18601-PSOC VENKATESAN C
39
ASP/EEE/SVCE
PGi,min & PGi, max
EE18601-PSOC VENKATESAN C
40
ASP/EEE/SVCE
EE18601-PSOC VENKATESAN C
41
ASP/EEE/SVCE
1. The fuel cost of two units are given by,
F1 = 0.1 PG12 + 25PG1 + 1.6 Rs/hr
F2 = 0.1 PG22 + 32PG2 + 2.1 Rs/hr
If the total demand on the generators is 250 MW, find the
economic load scheduling of the two units
EE18601-PSOC VENKATESAN C
42
ASP/EEE/SVCE
→ (1)
→ (2)
EE18601-PSOC VENKATESAN C
43
ASP/EEE/SVCE
EE18601-PSOC VENKATESAN C
44
ASP/EEE/SVCE
2. Determine the economic generation schedules of three
generating units in a power system to meet the system load
of 925 MW. The operating limit and cost function are given
below:
Operating limits 250 MW PG1 450 MW
200 MW PG2 350 MW
125 MW PG3 225 MW
Cost function is F1 = 0.0045 PG12 + 5.2 PG1 + 580
F2 = 0.0056 PG22 + 4.5 PG2 + 640
F3 = 0.0079 PG32 + 5.8 PG3 + 820
EE18601-PSOC VENKATESAN C
45
ASP/EEE/SVCE
EE18601-PSOC VENKATESAN C
46
ASP/EEE/SVCE
→ (1)
→ (2)
EE18601-PSOC VENKATESAN C
47
ASP/EEE/SVCE
→ (3)
EE18601-PSOC VENKATESAN C
48
ASP/EEE/SVCE
3. Resolve the previous problem (2) and determine the
economic dispatch by changing the limit for the third unit is
180 MW PG3 225 MW
EE18601-PSOC VENKATESAN C
49
ASP/EEE/SVCE
EE18601-PSOC VENKATESAN C
50
ASP/EEE/SVCE
→ (1)
→ (2)
EE18601-PSOC VENKATESAN C
51
ASP/EEE/SVCE
4. The fuel inputs per hour of plants 1 and 2 are given as
F1 = 0.2 P12 + 40 P1 + 120 Rs/hr
F2 = 0.25 P22 + 30 P2 + 150 Rs/hr
Determine the economic operating schedule and the
corresponding cost of generation. The maximum and
minimum loading on each unit is 100 MW and 25 MW.
Assume the transmission losses are ignored and the total
demand is 180 MW. Also determine the saving obtained if the
load is equally shared by both the units.
EE18601-PSOC VENKATESAN C
52
ASP/EEE/SVCE
= 88.8889 MW
EE18601-PSOC VENKATESAN C
53
ASP/EEE/SVCE
EE18601-PSOC VENKATESAN C
54
ASP/EEE/SVCE
Effect of Transmission Loss
• The optimum scheduling for different power stations situated
close to each other can be done without considering the
losses in the transmission network
• However the power stations are far from each other, the
economic scheduling must take transmission losses into
account
EE18601-PSOC VENKATESAN C
55
ASP/EEE/SVCE
Effect of Transmission Loss
• Neglecting the losses means that each unit should
supply half the load.
• However it is evident that if unit 2 supplies more
load, the transmission line would have to carry less
current resulting in lower transmission loss
• Thus the economic scheduling obtained by neglecting
the transmission loss may not be the most economic
arrangement in actual practice.
EE18601-PSOC VENKATESAN C
56
ASP/EEE/SVCE
Coordination Equation with Loss
d
d
d
d
EE18601-PSOC VENKATESAN C
58
ASP/EEE/SVCE
Coordination Equation with Loss
d
IC – Incremental Fuel Cost
d
→ (2)
Where,
• PL = Transmission Losses in p.u.
• PG = Plant loading in p.u.
• B = Loss coefficients in p.u
• indicate independent summation to include all sources
EE18601-PSOC VENKATESAN C
61
ASP/EEE/SVCE
Optimum Allocation of Generator
• For a two generator source system (N = 2)
EE18601-PSOC VENKATESAN C
62
ASP/EEE/SVCE
Optimum Allocation of Generator
• In matrix form
EE18601-PSOC VENKATESAN C
63
ASP/EEE/SVCE
Optimum Allocation of Generator
EE18601-PSOC VENKATESAN C
64
ASP/EEE/SVCE
Optimum Allocation of Generator
• For optimum operating condition, coordination equation is
→ (1)
EE18601-PSOC VENKATESAN C
65
ASP/EEE/SVCE
Optimum Allocation of Generator
→ (2)
• Equality constraint is
EE18601-PSOC VENKATESAN C
67
ASP/EEE/SVCE
Computational Approach for Optimum
Allocation of Generator
EE18601-PSOC VENKATESAN C
68
ASP/EEE/SVCE
Computational Approach for Optimum
Allocation of Generator
EE18601-PSOC VENKATESAN C
69
ASP/EEE/SVCE
Solution by -Iteration Method with Loss
• Step 1: Choose Lagrange multiplier as or (IC) (OR)
EE18601-PSOC VENKATESAN C
70
ASP/EEE/SVCE
Solution by -Iteration Method with Loss
EE18601-PSOC VENKATESAN C
71
ASP/EEE/SVCE
Solution by -Iteration Method with Loss
• or decrease by , if
EE18601-PSOC VENKATESAN C
72
ASP/EEE/SVCE
, N
EE18601-PSOC VENKATESAN C
73
ASP/EEE/SVCE
EE18601-PSOC VENKATESAN C
74
ASP/EEE/SVCE
EE18601-PSOC VENKATESAN C
75
ASP/EEE/SVCE
1. A two bus system is shown in Fig. If 50 MW is transmitted
from plant 1 to the load, a transmission loss of 10 MW is
incurred. Find the required generation for each plant and
the power received by load when the system is
Rs.22/MWhr. The cost function is given by,
EE18601-PSOC VENKATESAN C
76
ASP/EEE/SVCE
• Since the load is at bus 2 alone, PG2 will not have any effect on
power loss, B22 = 0, B12 = B21 = 0
• Transmission loss will depend on PG1 only,
EE18601-PSOC VENKATESAN C
77
ASP/EEE/SVCE
EE18601-PSOC VENKATESAN C
78
ASP/EEE/SVCE
Aliter:
• Power generation is given by,
EE18601-PSOC VENKATESAN C
79
ASP/EEE/SVCE
2. A system consists of two plants connected by a line as shown
in Fig. A load is at plant 1 and 180 MW is transmitted from
plant 2 to the load, a transmission loss of 18 MW is incurred.
Find the optimum schedule considering transmission losses
to supply a load of 200 MW. Also evaluate the amount of loss
that may be incurred, if at the time of scheduling, losses are
not coordinated. Fuel costs are given by,
EE18601-PSOC VENKATESAN C
80
ASP/EEE/SVCE
• Since the load is connected at bus 1, the transmission loss will
depend on PG2, Let = 1
EE18601-PSOC VENKATESAN C
81
ASP/EEE/SVCE
• Iteration 1: Power generations are given by,
EE18601-PSOC VENKATESAN C
82
ASP/EEE/SVCE
• Iteration 2:
EE18601-PSOC VENKATESAN C
83
ASP/EEE/SVCE
• Iteration 3:
EE18601-PSOC VENKATESAN C
84
ASP/EEE/SVCE
ii. Transmission losses are considered and NOT coordinated:
• Iteration 1:
EE18601-PSOC VENKATESAN C
85
ASP/EEE/SVCE
• Iteration 2:
EE18601-PSOC VENKATESAN C
86
ASP/EEE/SVCE
• Iteration 3:
EE18601-PSOC VENKATESAN C
87
ASP/EEE/SVCE
3. For a two unit system, the loss coefficients are
Find the optimal generations PG1 and PG2 for = 20. Also
compute the transmission loss and received power.
EE18601-PSOC VENKATESAN C
88
ASP/EEE/SVCE
Power generations are given by,
→ (1)
→ (2)
EE18601-PSOC VENKATESAN C
89
ASP/EEE/SVCE
Assume initial generations, (since power transmitted to load is not given)
EE18601-PSOC VENKATESAN C
90
ASP/EEE/SVCE
Iteration 2: Substitute PG2 = 51.136 in eqn.(1)
Iteration 3:
Iteration 4:
EE18601-PSOC VENKATESAN C
91
ASP/EEE/SVCE
From the results of iteration 3 and 4, we got the same values of PG1
and PG2
Since load demand is not given, need not to find P and check < 1
EE18601-PSOC VENKATESAN C
92
ASP/EEE/SVCE
4. The incremental costs of two units are:
EE18601-PSOC VENKATESAN C
93
ASP/EEE/SVCE
• Step 1: Determine using,
EE18601-PSOC VENKATESAN C
94
ASP/EEE/SVCE
• From the equation of PL,
• Iteration 1:
EE18601-PSOC VENKATESAN C
95
ASP/EEE/SVCE
• Repeating this until the previous and current (PGk = PGk-1)
generations are same
>1
EE18601-PSOC VENKATESAN C
96
ASP/EEE/SVCE
• Iteration 2:
• Determine and
EE18601-PSOC VENKATESAN C
97
ASP/EEE/SVCE
EE18601-PSOC VENKATESAN C
98
ASP/EEE/SVCE
Base Point and Participation Factors
• The economic dispatch problem has to be solved repeatedly
by moving the generators from one economically optimum
schedule to another as the load changes.
• We start from a schedule obtained from equal incremental
cost as base point.
• Next, the scheduler assumes a load change and investigates
how much each generating unit needs to be moved (i.e.,
participate in the load change) in order that the new load be
served at the most economic operating point.
• Assume that both the first and second derivatives in the cost
versus power output function are available (i.e., both Fi' and
Fi" exist)
EE18601-PSOC VENKATESAN C
99
ASP/EEE/SVCE
Base Point and Participation Factors
• The incremental cost curve of the ith unit is given in Fig.
EE18601-PSOC VENKATESAN C
100
ASP/EEE/SVCE
Base Point and Participation Factors
• As the unit load is changed by an amount Pi, the system
incremental cost moves from to +
• For a small change in power output on the single unit,
→ (1)
EE18601-PSOC VENKATESAN C
101
ASP/EEE/SVCE
Base Point and Participation Factors
EE18601-PSOC VENKATESAN C
102
ASP/EEE/SVCE
Base Point and Participation Factors
• Change in demand,
→ (2)
EE18601-PSOC VENKATESAN C
103
ASP/EEE/SVCE
Base Point and Participation Factors
• Suppose PD increases to PD+PD, the new value of generation is
calculated using,
EE18601-PSOC VENKATESAN C
104
ASP/EEE/SVCE