HW Section 4-Daily Plan-Consolidated 08-5-2024

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

MPWT LEA Associates South Asia Pvt. Ltd.

, India Joint Venture of Road Number8


Department of Road NR13S - Improvement and in JV with Pyunghwa Engineering Consultants Construction Enterprise Mixay Construction
Maintenance Project Ltd., Korea Co., Ltd - State and Enterprise of
with Lao Transport Engineering Communication Construction
Consultant, Lao PDR (as sub-consultant) (R8CE - LMX - SECC JV)

Improvement and Maintenance of the National Road 13 South, Section 4 (Length 78 km) from (km 268+000) to (km 346+000) in Khammouane Province
RFI Summary
Month:
Chainage Length Inspection Name of the Witness by
RFI No. Milestone Description Side Inspection Time Contact No Remarks Status
From To (m) Date Contact person ISWS
I.Highway:
1. Paving Asphalt Concrete for Binder
MS14 323+600 323+700 LHS 100 08:30 AM Mr. Souliyanh 2098219622
Course (Round abou)
2. Paving Asphalt Concrete for Wearing
MS14 323+600 323+700 LHS 100 13:30 PM Mr. Souliyanh 2098219622
Course (Round about )
NR13SP4/HW/750 MS14 3. Scratch of Existing Pavements 344+500 344+900 LHS 400 28-03-2024 8 am -17 pm Mr. Souliyanh 2098219622

MS14 4. Construction for Top Base Course 344+500 344+900 LHS 400 8 am -17 pm Mr. Souliyanh 2098219622

MS14 5. Construction for Embankment Layer 6 344+900 345+200 RHS 300 8 am -17 pm Mr. Souliyanh 2098219622

MS13 1,Construction for Embankment Layer-1 299+600 299+800 RHS 200 8 am - 17 pm Mr. Bounsong 020 98558444

MS14 2.Scratch of Existing Pavements 344+500 344+900 LHS 400 8 am -17 pm Mr. Souliyanh 2098219622

MS14 3.Construction for Top Base Course 344+500 344+900 RHS 400 8 am -17 pm Mr. Souliyanh 2098219622
NR13SP4/HW/751 29-03-2024
MS14 4.Construction for Embankment Layer 6 345+200 345+740 RHS 540 8 am -17 pm Mr. Souliyanh 2098219622

MS14 5.Spraying for Prime Coat (MC70) 344+000 344+500 RHS 500 08:00 AM Mr. Souliyanh 2098219622

MS14 6.Commone Excavation for U Ditches 340+640 340+700 RHS 60 8 am -17 pm Mr. Souliyanh 2056806346

MS13 1.Construction for Embankment Layer-1 300+000 300+300 LHS 300 8 am - 17 pm Mr. Bounsong 020 98558444
NR13SP4/HW/752 30-03-2024
MS14 2. Construction for Embankment Layer 6 345+200 345+740 RHS 540 8 am -17 pm Mr. Souliyanh 2098219622

MS13 1.Construction for Embankment Layer-1 299+800 300+000 LHS 200 8 am -17 pm Mr. Bounsong 020 98558444

NR13SP4/HW/753 MS14 2. Construction for Embankment Layer 7 344+900 345+200 LHS 300 31-03-2024 8 am -17 pm Mr. Souliyanh 2098219622

MS14 3.Spraying for Prime Coat (MC70) 344+500 344+900 RHS 400 08:00 AM Mr. Souliyanh 2098219622

4. Construction for Base Course layer 1 of


MS14 340+000 340+300 RHS 300 8 am -17 pm Mr. Souliyanh 2098219622
Widening
NR13SP4/HW/754 MS14 2. Construction for Embankment Layer 7 345+200 345+740 RHS 540 01-04-2024 8 am -17 pm Mr. Souliyanh 2098219622

MS13 1.Construction for Embankment Layer-1 299+700 399+800 RHS 100 8 am - 17 pm Mr. Bounsong 020 98558444

4. Construction for Base Course layer 1 of


MS14 340+300 340+500 RHS 200 8 am -17 pm Mr. Souliyanh 2098219622
Widening

MS14 2. Construction for Embankment Layer 8 344+900 345+200 RHS 300 8 am -17 pm Mr. Souliyanh 2098219622

NR13SP4/HW/755 4. Paving Asphalt Concrete for Binder 02-04-2024


MS14 344+000 344+500 RHS 500 08:30 AM Mr. Souliyanh 2098219622
Course
MS13 1.Construction for Embankment Layer-1 299+500 399+700 LHS 200 8 am - 17 pm Mr. Bounsong 020 98558444

MS13 1.Construction for Embankment Layer-1 299+400 299+700 RHS 300 8 am - 17 pm Mr. Bounsong 020 98558444
8:00 am -
MS13 1,Construction for Embankment Layer-1 299+200 299+500 LHS 300 Mr. Bounsong 020 98558444
17:00 pm
4. Construction for Base Course layer 1 of
MS14 340+000 340+500 LHS 500 8 am -17 pm Mr. Souliyanh 2098219622
NR13SP4/HW/756 Widening 03-04-2024
MS14 2. Construction for Embankment Layer 8 344+200 345+740 RHS 540 8 am -17 pm Mr. Souliyanh 2098219622
4. Paving Asphalt Concrete for Binder
MS14 344+500 344+900 RHS 400 08:30 AM Mr. Souliyanh 2098219622
Course
8:00 am -
MS13 1.Construction for Embankment Layer-1 299+100 299+200 LHS 100 Mr. Bounsong 020 98558444
17:00 pm
4. Construction for Base Course layer 1 of
MS14 299+100 299+400 RHS 300 8 am -17 pm Mr. Souliyanh 2098219622
Widening
NR13SP4/HW/757 04-04-2024
MS14 2. Construction for Embankment Layer 9 344+900 345+200 RHS 300 8 am -17 pm Mr. Souliyanh 2098219622

MS14 5.Spraying for Prime Coat (MC70) 344+000 344+900 LHS 900 08:00 AM Mr. Souliyanh 2098219622

MS14 6.Commone Excavation for U Ditches 340+800 340+880 LHS 80 8 am -17 pm Mr. Souliyanh 2056806346

8:00 am -
MS13 1.Construction for Embankment Layer-1 300+300 300+400 LHS 100 Mr. Bounsong 020 98558444
17:00 pm

MS14 2. Construction for Embankment Layer 9 345+200 345+740 RHS 540 8 am -17 pm Mr. Souliyanh 2098219622

NR13SP4/HW/758 MS14 3. Scratch of Existing Pavements 340+000 340+500 LHS 500 05-04-2024
8 am -17 pm Mr. Souliyanh 2098219622

MS14 4. Construction for Top Base Course 340+000 340+500 LHS 500 8 am -17 pm Mr. Souliyanh 2098219622

MS14 5.Commone Excavation for Ditches 345+740 346+000 LHS 260 8 am -17 pm Mr. Souliyanh 2056806346

8:00 am -
MS13 1.Construction for Embankment Layer-1 300+300 300+400 LHS 100 Mr. Bounsong 020 98558444
17:00 pm
MS14 2. Construction for Embankment Layer 9 344+900 345+200 LHS 300 8 am -17 pm Mr. Souliyanh 2098219622

MS14 3. Scratch of Existing Pavements 340+000 340+500 RHS 500 8 am -17 pm Mr. Souliyanh 2098219622
NR13SP4/HW/759 06-04-2024
MS14 4. Construction for Top Base Course 340+000 340+500 RHS 500 8 am -17 pm Mr. Souliyanh 2098219622
5. Paving Asphalt Concrete for Binder
MS14 344+000 344+900 LHS 400 08:30 AM Mr. Souliyanh 2098219622
Course
MS14 6.Commone Excavation for Ditches 345+740 346+000 LHS 260 8 am -17 pm Mr. Souliyanh 2056806346

8:00 am -
MS13 1.Construction for Embankment Layer-1 300+400 300+700 LHS 300 Mr. Bounsong 020 98558444
17:00 pm
MS14 2. Construction for Embankment Layer 9 345+200 345+740 LHS 540 8 am -17 pm Mr. Souliyanh 2098219622

NR13SP4/HW/760 MS14 3. Scratch of Existing Pavements 340+000 340+500 LHS 500 07-04-2024
8 am -17 pm Mr. Souliyanh 2098219622

MS14 4. Construction for Top Base Course 340+000 340+500 LHS 500 8 am -17 pm Mr. Souliyanh 2098219622

MS14 6.Commone Excavation for Ditches 340+700 340+740 RHS 40 8 am -17 pm Mr. Souliyanh 2056806346

1. Painting for Island for Roundabout. Km


MS10 323+640 8 am -17 pm Mr. Khamhou 2056806346
NR13SP4/HW/761 323+640 08-04-2024

MS14 2 .Spraying for Prime Coat (MC70) 340+000 340+500 RHS 500 10:30 AM Mr. Souliyanh 2098219622

MS13 1.Construction for Embankment Layer-1 300+700 301+000 LHS 300 8 am -17 pm Mr. Bounsong 020 98558444

NR13SP4/HW/762 MS14 2. Construction for Top Embankment 344+900 345+740 RHS 840 09-04-2024 8 am -17 pm Mr. Souliyanh 2098219622
NR13SP4/HW/762 09-04-2024

3. Paving Asphalt Concrete for Binder


MS14 340+000 340+500 RHS 500 09:30 AM Mr. Souliyanh 2098219622
Course

8:00 am -
MS13 1,Construction for Embankment Layer-1 300+700 301+000 RHS 300 Mr. Bounsong 020 98558444
17:00 pm

MS14 2. Construction for Top Embankment 344+900 345+740 LHS 840 8 am -17 pm Mr. Souliyanh 2098219622
NR13SP4/HW/463 10-04-2024
MS14 3. Scratch of Existing Pavements 340+000 340+500 RHS 500 8 am -17 pm Mr. Souliyanh 2098219622

MS14 4. Construction for Top Base Course 340+000 340+500 RHS 500 8 am -17 pm Mr. Souliyanh 2098219622

MS14 5. Construction for Sub base of Widening 345+740 346+000 LHS 260 8 am -17 pm Mr. Souliyanh 2098219622

8:00 am -
MS13 1,Construction for Top Embankment 300+700 301+000 RHS 300 Mr. Bounsong 020 98558444
17:00 pm
8:00 am -
MS13 2,Construction for Top Embankment 300+000 300+300 RHS 300 Mr. Bounsong 020 98558444
17:00 pm

MS14 3. Construction for Top Sub grade 344+900 345+740 LHS 840 8 am -17 pm Mr. Souliyanh 2098219622
NR13SP4/HW/464 11-04-2024
MS14 4. Construction for Top Sub grade 344+900 345+740 RHS 840 8 am -17 pm Mr. Souliyanh 2098219622

MS14 5. Construction for Sub base of Widening 345+740 346+000 RHS 260 8 am -17 pm Mr. Souliyanh 2098219622

MS14 6. Spraying for Prime Coat (MC-70) 340+000 340+500 LHS 500 8 am -17 pm Mr. Souliyanh 2098219622

Date : 12-04-2024 - 20-04-2024 Work No Activity because Lao New Year Festival

8:00 am -
NR13SP4/HW/465 MS13 1,Construction for Top Embankment 300+300 300+500 RHS 200 19-04-2024 Mr. Bounsong 020 98558444
17:00 pm

8:00 am -
NR13SP4/HW/466 MS13 1,Construction for Top Embankment 300+300 300+500 LHS 200 20-04-2024 Mr. Bounsong 020 98558444
17:00 pm

8:00 am -
NR13SP4/HW/467 MS13 1,Construction for Top Embankment 300+500 300+700 LHS 200 21-04-2024 Mr. Bounsong 020 98558444
17:00 pm

1,Construction for Top Embankment 300+700 300+900 LHS 200


8:00 am -
MS13 Mr. Bounsong 020 98558444
17:00 pm

NR13SP4/HW/468 2,Construction for Top Embankment 300+500 300+900 RHS 400 22-04-2024

3. Painting for Traffic Markings


MS10 (Reflectorozed Maring and Tactile edge 323+640 8 am -17 pm Mr. Khamhou 2056806346
Line) of Main Road for Roundabout.

23-04-2024 No activity (Buddha day)


1. Filling for Box culvert Layer 1 Km
8:00 AM Mr. Souliyanh 2056806346
343+067 LHS
MS14

NR13SP4/HW/469 2. Construction for Sub grade Layer 1 344+900 345+740 LHS 840 24-04-2024 8 am -17 pm Mr. Souliyanh 2098219622

3,Construction for Top Embankment 300+900 301+000 LHS 100


MS13 8 am - 17 pm Mr. Bounsong 020 98558444
4,Construction for Top Embankment 300+900 301+000 RHS 100

1. Construction for Top Embankment 301+000 301+100 LHS 100

MS13 8 am - 17 pm Mr. Bounsong 020 98558444

2. Construction for Top Embankment 301+000 301+100 RHS 100


NR13SP4/HW/470 25-04-2024
3.Commone Excavation for U Ditches 340+740 340+800 RHS 60 8 am -17 pm

4. Construction for Sub grade Layer 1 345+740 346+000 LHS 260 8 am -17 pm
MS14 Mr. Souliyanh 2056806346

5. Filling for Box culvert Layer 1 Km


342+400
8:00 AM

1,Construction for Top Embankment 299+700 300+000 LHS 300


8:00 am -
MS13 Mr. Bounsong 020 98558444
17:00 pm
2,Construction for Top Embankment 299+700 300+000 RHS 300

NR13SP4/HW/471 26-04-2024
3. Paving Asphalt Concrete for Binder
340+000 340+500 LHS 500 09:30 AM
Course
4. Construction for Top Sub grade 345+740 346+000 LHS 260 8 am -17 pm
MS14 Mr. Souliyanh 2098219622
5. Construction for Sub Base 344+900 345+200 LHS 300 8 am -17 pm

6.Commone Excavation for Ditches 340+860 340+900 RHS 40 8 am -17 pm


8:00 am -
MS13 1,Construction for Top Embankment 299+400 299+700 LHS 300 Mr. Bounsong 020 98558444
17:00 pm
NR13SP4/HW/472 27-04-2024
MS14 2. Construction for Sub Base 344+900 345+200 LHS 300 8 am -17 pm Mr. Souliyanh 2098219622

MS14 1. Construction for Sub Base 344+900 345+200 RHS 300 8 am -17 pm Mr. Souliyanh 2098219622
NR13SP4/HW/473 28-04-2024
MS13 2. Construction for Top Embankment 299+400 299+700 RHS 300 8:00 am - 17:00 pmMr. Bounsong 020 98558444

NR13SP4/HW/474 MS14 1. Construction for Sub Base 345+200 345+740 RHS 540 29-04-2024 8 am -17 pm Mr. Souliyanh 2098219622

1,Construction for Top Embankment 299+080 299+400 LHS 320


8:00 am -
MS13 Mr. Bounsong 020 98558444
17:00 pm
2,Construction for Top Embankment 299+080 299+400 RHS 320

NR13SP4/HW/475 3. Scratch of Existing Pavements 344+900 345+200 RHS 300 30-04-2024 8 am -17 pm

MS14 Mr. Souliyanh 2098219622


NR13SP4/HW/475 30-04-2024

MS14 4. Construction for Top Base Course 344+900 345+200 RHS 300 8 am -17 pm Mr. Souliyanh 2098219622

5. Construction for Sub Base 345+200 345+740 LHS 540 8 am -17 pm


01-05-2024 No activity (Labor day)

1. Scratch of Existing Pavements 345+200 345+500 RHS 300 8 am -17 pm

MS14 2. Construction for Top Base Course 345+200 345+500 RHS 300 8 am -17 pm Mr. Souliyanh 2098219622

NR13SP4/HW/476 3. Construction for Sub Base 345+740 346+000 RHS 260 02-05-2024 8 am -17 pm

4, Construction for sub-grade Layer-1 300+300 300+600 LHS 300


8:00 am -
MS13 Mr. Bounsong 020 98558444
17:00 pm
5, Construction for sub-grade Layer-1 300+300 300+600 RHS 300

1. Scratch of Existing Pavements 345+200 345+500 RHS 300 8 am -17 pm

MS14 2. Construction for Top Base Course 345+200 345+500 RHS 300 8 am -17 pm Mr. Souliyanh 2098219622
NR13SP4/HW/477 03-05-2024
3. Construction for Sub Base 345+740 346+000 LHS 260 8 am -17 pm

8:00 am -
MS13 4, Construction for sub-grade Layer-1 299+060 299+300 RHS 240 Mr. Bounsong 020 98558444
17:00 pm

1. Scratch of Existing Pavements 345+200 345+500 LHS 300 8 am -17 pm

MS14 2. Construction for Top Base Course 345+200 345+500 LHS 300 8 am -17 pm Mr. Souliyanh 2098219622

NR13SP4/HW/478 3. Commone Excavation for U Ditches 340+680 340+700 LHS 20 04-05-2024 8 am -17 pm

4, Construction for sub-grade Layer-1 299+060 299+300 LHS 240


8:00 am -
MS13 Mr. Bounsong 020 98558444
17:00 pm
5, Construction for sub-grade Layer-1 299+300 299+600 RHS 300

1, Construction for sub-grade Layer-1 299+300 299+700 LHS 400


8:00 am -
MS13 Mr. Bounsong 020 98558444
17:00 pm
2, Construction for sub-grade Layer-1 299+600 299+700 RHS 100
NR13SP4/HW/479 05-05-2024
3. Scratch of Existing Pavements 345+200 345+500 LHS 300 8 am -17 pm
MS14 Mr. Souliyanh 2098219622
4. Construction for Top Base Course 345+200 345+500 LHS 300 8 am -17 pm

8:00 am -
MS13 1, Construction for sub-grade Layer-1 299+300 299+700 LHS 400 Mr. Bounsong 020 98558444
17:00 pm
2. Commone Excavation for U Ditches 341+000 341+100 RHS 100 8 am -17 pm
NR13SP4/HW/480 06-05-2024
MS14 3. Scratch of Existing Pavements 345+500 345+800 RHS 300 8 am -17 pm Mr. Souliyanh 2098219622

4. Construction for Top Base Course 345+500 345+800 RHS 300 8 am -17 pm
07-05-2024 No activity (Buddha day)
8:00 am -
MS13 1, Construction for sub-grade Layer-1 299+700 300+000 RHS 300 Mr. Bounsong 020 98558444
17:00 pm
NR13SP4/HW/481 08-05-2024
MS14 4. Construction for Top Base Course 345+500 345+800 LHS 300 8 am -17 pm Mr. Souliyanh 2098219622