DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

LOCATION :

ITEM NO. : 105


DESCRIPTION : Sub-Grade Preparation

QUANTITY : 3600.00
UNIT : sq.m.

A. MATERIALS QTY. UNIT UNIT COST AMOUNT

None

Sub-Total for A

B. EQUIPMENT NO. OF UNIT DAY RATE/DAY AMOUNT

Mini Road Roller 1 20 8,800.00 176,000.00


Service Vehicle w/ Water Tank 1 20 2,800.00 56,000.00

Sub-Total for B 232,000.00


C. LABOR NO. OF PERSON DAY RATE/DAY AMOUNT
Construction Foreman 1 20 925.00 18,500.00
Laborers 12 20 515.00 123,600.00

Sub-Total for C 142,100.00


D. TOTAL DIRECT COST (A + B + C) 374,100.00
E. DIRECT UNIT COST 103.92