23) R A For Installation of Kerbstone and Paving Blocks
23) R A For Installation of Kerbstone and Paving Blocks
23) R A For Installation of Kerbstone and Paving Blocks
Rare (1) 1 2 3 4 5
Possible (2) 2 4 6 8 10
Likely (3) 3 6 9 12 15
Often (4) 4 8 12 16 20
Frequently / Almost
5 10 15 20 25
Certain (5)
Absolutely Unacceptably High
15 – 25 Extreme Risk Activity or industry should not proceed in current form
Unacceptably High
8 – 12 High Risk Activity /industry should be modified to include remedial planning and action and be subject to detailed OSH
assessment
Acceptable but must be managed at as Low as Reasonably Practicable “ALARP”
4–6 Moderate Risk Activity or Industry can operate subject to management and / modification
Acceptable without required further action
1–3 Low Risk No action required unless escalated of risk is possible
Verified by: Approved by:
Project Manager: Client
_____________________Signature: ________________Date / / Name: ________________________Signature: _______________Date: / /
OSH Manager
Name: Saji Varghese Signature: Date: 19/10/2018
DISTRIBUTION: Original to: Site HSE File Copy to: HSE Department
OSHAD – SF. Version 3.0 Controlled Copy: Printed copy of this document is uncontrolled.
CLIENT: CONSULTANT:
OSHAD – SF. Version 3.0 Controlled Copy: Printed copy of this document is uncontrolled.
CLIENT: CONSULTANT:
OSHAD – SF. Version 3.0 Controlled Copy: Printed copy of this document is uncontrolled.
CLIENT: CONSULTANT:
OSHAD – SF. Version 3.0 Controlled Copy: Printed copy of this document is uncontrolled.
CLIENT: CONSULTANT:
proactive
leadership
OSHAD – SF. Version 3.0 Controlled Copy: Printed copy of this document is uncontrolled.
CLIENT: CONSULTANT:
to be carried out on
different intervals .
Name: Saji Varghese Signature: Date:19th/ 05 /2018 DISTRIBUTION: Original to: Site HSE File Copy to: HSE Department