For water supply projects (Ashi town & Agamsa fincha town) bid
document requirement
1. Multiple awards to one bidder shall not be permitted.
2. Company business license needs :- WWC, WWGC and grade 3 and above for electromechanical work permit 3. Specific company experience:-with in the latest 5 years in water supply projects. 4. Key personnel specific experience: - needs in water supply projects. 5. Project location:-out of Addis Ababa in Oromia region in different woreda towns. Ashi town 702km far from Addis Ababa and Agamsa fincha 315km far from Addis Ababa(we need check security issues). 6. Language: - all documents translated/ autonticated to English/afan oromo. 7. Project duration: - Ashi town 540 days & Agamsa fincha town 720 days. 8. Valid ISO-certificate for pipes and electro technical equipment. 9. Price adjustment:-is allowed after 12 months for more than 18 month project duration projects. 10.JV up to 3 is permitted.