Professional Documents
Culture Documents
Camerron Road Project - Level 1 - Draft 01
Camerron Road Project - Level 1 - Draft 01
Draft 01
Level 1
ID Task Name Duration Start Finish Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
A M J J A S O N D J F M A M J J A S O N D J F M
1 Cameroon Road Project 535 d Wed 08/05/24 Mon 23/02/26
2 Feasibility phase 15 d Wed 08/05/24 Mon 27/05/24
9 Engineerin & Design 60 d Mon 27/05/24 Wed 07/08/24
20 Mobilisation 30 d Mon 27/05/24 Tue 02/07/24
22 Project Cost 60 d Mon 27/05/24 Wed 07/08/24
31 Heatlh & Safety 30 d Wed 07/08/24 Thu 12/09/24
33 Procurement 120 d Wed 07/08/24 Wed 01/01/25
38 Logistics 90 d Wed 01/01/25 Tue 22/04/25
41 Construction 250 d Tue 22/04/25 Mon 23/02/26
Page 1