Professional Documents
Culture Documents
SWP 01 Hot Work Permit
SWP 01 Hot Work Permit
23 If welding,the earthing connection is adjacent to the work site and earth return cable leads directly back to the welding
machine. The ship's structure should not be used as an earth return
24 Has the equipment to be used been inspected prior to starting work and found to be in good condition?
25 Is the fire main charged, hoses let out, monitors pointed out and all in good conditions?
IF ANY CHECK MARKS MUST BE PLACED IN THE SHADED AREAS, THEN THIS ITEM MUST BE
RECTIFIED BEFORE PROCEEDING
Atmosphere tests should be checked and recorded below PRIOR to COMMENCE any Hot Work:
READINGS
Hydrocarbon Oxygen
Toxic Gases / H2S
(If the space is adjacent to a Cargo or Bunker Tank)
Revision: 01.July.2022 Approved by MD Page 1 OF 1
SWP 01 Hot Work Permit
(Less than 1%) (21 %) (Specify gas & TLV) (See Note 1)
PROTECTIVE EQUIPMENT
Clothing Fire Extinguisher Gloves Boots
Safety harness Flashlight Hard Hat Hearing protection
Safety Line Gas Tester Respirator SCBA
Eye Protection Other
I HAVE READ THE ABOVE PERMIT AND WILL CARRY OUT THE WORK REQUIRED IN A SAFE MANNER.
THE WORK HAS BEEN COMPLETED AND ALL PERSONS UNDER MY SUPERVISION, ALL MATERIALS AND
EQUIPMENT HAVE BEEN WITHDRAWN.
Authorised officer in charge of work : Time : Date :
(Chief Officer / Chief Engineer)
Notes:
1. Immediately before hot work is started the officer responsible for safety precautions should examine the area where hot work is to be
undertaken, and ensure that the oxygen content is 21% by volume and that tests with a combustible gas indicator show not more than
1% LFL
2. Officer in charge of the work should ensure that atmosphere is continously monitoring by personnal gas meters. In addition, officer in
charge of safety should re-test the atmosphere after each break in work periods and also record the test results of atmosphere at regular
intervals which should not exceed 20 minutes.
3. If any other Permits are required, Hot Work Permit should be the last permit issued.
4. A Hot Work Permit can only cover a single space. A seperate permit should be approved for each intended task and location.
Work on fixtures/fittings in
cargo pumproom
Open deck aft of
accommodation
Location
Pumproom)
cargo tank
Minimu
area
m
Require
ments
Work
planing
meeting to
be held and
risk
√ √ √ √ √ √ √ √ √
assessment
completed.
Work in
designated
space with
shield or √
curtain
erected.
Aduquate
ventilation √ √ √ √ √ √
Confirmati
on from
master or
designate
that work
√
is OK to
proceed
Tank
atmosphere
checks
carried out
and entry
√ √ √
permit
issued.
Tank to be
washed
and gas √ √ √
freed.
Cargo
tanks to be
purged and
inerted to
not more
than%8 O2
√ √ √ √
and not
more than
%2
Work to be
carried out
further
than 500
mm from √ √ √
the tank
deck or
bulkheads.
Work to be
carried out
further
than 500
mm from
fuel oil
√ √ √ √
tank deck
or
bulkheads.
Local
cleaning to
be carried
out as per √ √ √ √
requiremen
ts
All
interconne
cting
pipelines
flushed
√ √ √
and
drained
Hot work
permit
approved
by Master
or
√ √ √ √ √ √ √ √
responsible
Officer