HLE - Issue 03

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 15

ISSUE: 03 SUMMER 2020

THE HEAVY LIFT ENGINEER


...managing & delivering heavy lift projects

FEATURING
STOWAGE PLANS - WHAT BUILDING FABRICATION JIGS - IS EXCEPTION A-3.5 THE
YOU NEED TO KNOW 5 TOP TIPS SOLUTION TO HEAVY LIFT/
SEMI SUBMERSIBLE?

A MALIN GROUP PUBLICATION


THE HEAVYLIFT ENGINEER ISSUE 03

CONTENTS

EDITORIAL PAGE 5

STOWAGE PLANS - WHAT YOU NEED TO KNOW? PAGE 6

HEAVY LIFT TIP - GROUND BEARING UNDER TRAILERS PAGE 10

BUILDING FABRICATION JIGS - 5 TOP TIPS PAGE 12

BOOK RECOMMENDATIONS PAGE 15

HEAVY LIFT TIP - CRANES ON BARGES PAGE 16

LEARNING FROM LOCKDOWN PAGE 18

HEAVY LIFT TIP - DECK STRENGTH PAGE 20

IS EXCEPTION A-3.5 THE SOLUTION TO HEAVY LIFT/SEMI SUBMERSIBLE? PAGE 22

HEAVY LIFT TIP - HOOK HEIGHTS PAGE 26

ARTICLES | TIPS | VESSELS | NEWS & EVENTS


A PUBLICATION

2 3
THE HEAVYLIFT ENGINEER ISSUE 03

EDITORIAL
JOHN MACSWEEN
MANAGING DIRECTOR, MALIN GROUP

Welcome to our latest edition of the We have a selection of our helpful heavy
Heavylift Engineer, edition three. You can lift tips, covering everything from cranes
find issues one and two online to download on barges, to hook heights – and of course
(www.heavyliftengineer.com/magazine). our book reviews, to offer some helpful
recommendations for your next read.
It has been great to hear all of your
responses and feedback to date and I look Whether you are in shipbuilding, heavy
forward to your views on our latest edition. fabrication, power generation or mining,
the heavy lift engineer’s skill set is critical.
It has been a difficult 8 months, with No other engineering discipline, if you
companies forced to rethink their working decide to dive deep enough, offers such a
practices and colleagues adjusting to either range of technical challenges. We hope that
working from home, keeping occupied on this edition reflects that variety, offering
furlough - or continuing work as an essential something of interest to you, regardless of
worker. Whilst difficult and at times your background.
isolating, the Covid crisis has also offered
a learning opportunity, from harnessing Please do get in touch if you have a topic
new technologies, to reviewing work life you would like to see covered or would like
balance. We look at this in more detail in to guest feature for a future release – and I
our special, lockdown lessons article. This is hope you enjoy this new edition!
teamed with a piece enumerating the top 5
tips on the build of fabrication jigs, including We would love to hear from you! Please send
the need to identify build methodology any questions to: heavyliftengineer@
from the beginning and things to consider malingroup.com.
when planning the factory acceptance test
(FAT). There is also an article on one of the Please also sign up for exciting future
most common, and crucial, elements of editions at:
any heavylift shipping project, the humble www.heavyliftengineer.com
stowage plan. Easy to do, and even easier
to do badly!

We also have a great article by Giles


Candy from Envirocleanse on ballast water
treatment, with a focus on how it may
affect heavy lift projects.

ARTICLES | TIPS | VESSELS | NEWS & EVENTS


A PUBLICATION

4 5
THE HEAVYLIFT ENGINEER ISSUE 03

and personnel be left open to allow for this. When


• provide specific advice on cargoes which considering the allocated space, it is
are known to create difficulties and hazards important to consider the cargo securing
regarding their stowage and securing method and materials and whether the
• advising on actions that may be taken addition of these will also fit into the
when in heavy sea conditions allocated space.
• advising on actions that may be taken to
remedy the effects of cargo shifting Cargo securing:
Cargo can be secured in several different
The CSS Code provides the advice; however, ways:
the overall responsibility of the vessel, crew • web lashings
and cargo always lies with the Master. • chain lashings
The Cargo Securing Manual is broken into • welded blockers/cleats
five chapters: • welded bridge plates
• Chapter 1 – General (Definitions and • welded braces
General Information) • twistlocks
• Chapter 2 – Securing Devices and
Arrangements The type of securing is dependent on
• Chapter 3 – Stowage and Securing of Non differing factors, the majority of which are
fig. 01/ typical Reel stowage Standardized and Semi-Standardized Cargo directed by a calculation of the seagoing
• Chapter 4 – Stowage and Securing of forces that will act on the cargo. In order to
Containers and other Standardized Cargo calculate the seagoing forces, the following
• Chapter 5 – Cargo Safe Access Plan information allows for the most accurate

STOWAGE PLANS - Using the guidelines laid out by the IMO, in


combination with the predominant industry
answer:

• weight of the cargo

WHAT YOU NEED TO KNOW standards, we can look to answer the


aforementioned queries.
• accurate position of the Cargo’s Centre
of Gravity (CoG), in relation to a base
point on the vessel
Does the cargo fit in the allocated • dimensions between the transverse
space? and longitudinal supports in relation to
WRITTEN BY GRAHAM THOMAS Vessel owners and charterers can supply the CoG
PROJECT ENGINEER, MALIN ABRAM vessel particulars, which will allow you • accurate dimensions of the vessel
to find the right vessel for the specific being used for the transportation
A lot of considerations must be taken into The International Maritime Organization cargo. Many vessels have multiple holds • nature of transportation, in terms
account when creating a stowage plan. (IMO) has developed guidelines which must for carrying cargo, which are normally of expected sea state and weather
• Does the cargo fit in the allocated space? be followed when carrying cargo. This is the numbered starting at the bow and moving conditions
• What will be used to secure the cargo? Code of Safe Practice for Cargo Stowage and aft.
• How will personnel stow and secure the Securing (CSS Code). It is also a mandatory We would recommend the use of “Planning
cargo? requirement for vessels to carry a Cargo Within the particulars, hold dimensions and Execution of Marine Operations –
• Is the deck strong enough to take the Securing Manual (CSM) specific to their should be supplied for each hold. Hold DNVGL-ST-N001” as the industry Standard
cargo? cargo carrying capability. capacity can also be referred to in different to comply with. From the seagoing forces
• Does the cargo need segregated? ways depending on the type of vessel: we can find the transverse and longitudinal
The CSS Code provides an international • it is often measured in cubic metres, forces that will act upon the cargo, and
The safe stowage and securing of cargo standard to promote the safe stowage and stating the Grain/Bale capacity whether there will be any uplift present.
is dependent on the proper planning, securing of cargoes. It manages this by: • when carrying containers, TEU (Twenty
execution and supervision of the process. • ensuring that ship owners and operators Foot Equivalent Units) is referred to Once the seagoing forces are known,
The cargo should be stowed and secured in utilise the ship for its intended purpose the type of securing can be chosen. This
such a way which does not put the ship or • providing advice to ensure vessels are There may be cases where the cargo will depend on how the cargo has been
personnel in any risk. Improper stowage and equipped with proper cargo securing means dimensions are greater than the allowable constructed.
securing can put the vessel, crew and other • providing advice on cargo stowage and height in the hold. With permission from • Are there any lashing points on the
cargo into a potentially hazardous situation. securing to minimize risks to the ship the vessel owner, the hatch covers can cargo?

ARTICLES | TIPS | VESSELS | NEWS & EVENTS


A PUBLICATION

6 7
THE HEAVYLIFT ENGINEER ISSUE 03

• How is the cargo supported where strongest part of the deck (see Figure 2). stowage plan. In some cases, it may be few standards that we would recommend
it makes contact with the deck/ necessary to install the vertical restraint that you generally adhere to, these being,
dunnage? Welded bridge plates are used when on the cargo prior to lifting onboard BS5950 (British Standard – Structural use
• Is it being carried on a specially connecting a piece of cargo to a the vessel. Another instance where a of steelwork in building), AISC 360-10
designed transportation frame? transportation frame, a good example of cherry picker may be required is when (American institute of Steel Construction –
this would be when transporting offshore disconnecting the lifting equipment from Specification for Structural Steel Buildings),
Web Lashings are relatively light, fairly reels (see Figure 2). the cargo. Lloyd’s Register (Rules and regulations for
easy to use and also due to their material, the classification of ships) and Eurocode 3
the majority being made from polyester, An important aspect to consider when Deck Strength (Design of steel structures).
don’t cause as much damage to the cargo. choosing welded seafastenings are the Within the vessel particulars that you
However, they are susceptible to wear location of fuel tanks or other flammable should receive from the owner or charterer, When loading cargoes with a high point
and chafe, especially if being used across liquids or gases that may be stowed there should be information on the deck loading, it is important to land them to
edges. onboard the vessel. Since heat produced strength of the vessel. This is normally suitable load spreading mats/dunnage,
during the welding process could pose presented in the units’ tonne per metre in order to prevent any damage to the
The rubber (or similar) protection should a fire or explosion risk if exposed to squared (T/m2). If loading cargo with a vessel’s deck. It is also important to
be used to help protect the lashings. flammable materials, the vessel’s owner high point loading, deck strength checks consider the friction coefficient of the load
Web lashings are also not recommended or operator should always be consulted should be carried out to tie into primary spreading devices, as this will affect the
for use on exposed decks of a vessel, or to ensure it is safe to weld in the desired structure within the vessel. There are a results of seagoing forces being calculated.
on a barge where the lashings cannot location.
be checked. The webbing material can
deteriorate when exposed to salt water Twistlocks are used to secure containerised
and UV rays from the sun. It is important to cargo. The twistlocks attach to the vessel’s
know the Minimum Breaking Load (MBL) of deck in pre-set positions, where the four
the lashing you are working with, and that corners of a container would land, and the
they are certified. container is placed on top of them. Once
the container is in position, a lever is used
Chain Lashings are heavy and can be quite on the twistlock to lock the container in
cumbersome when moving around the place.
deck/hold of a vessel. Care must be taken
when moving the chains around a piece Stowage and Securing Method
of cargo to prevent any damage from The majority of cargoes will be lifted using
occurring, especially to painted surfaces. either a shore side crane or the vessel’s
It is important, as with the web lashing, crane, from the quayside, either into
to know the MBL of the chain you are the hold or onto the deck of the vessel,
working with, and that the chains have straight into their final position. However,
been tested and certified. some smaller cargoes may then need
manoeuvred once on the vessel. This may
Welded blockers/cleats are specified be done with the use of a forklift, and in
dependant on the findings from the this instance, it would be important to
seagoing forces. Blockers tend to be consider the forklifts manoeuvrability and
used when the only considerations are dimensions when creating a stowage plan.
transverse and longitudinal forces; and
cleats should be specified whenever When uplift is calculated in the seagoing
additional restraint is required from forces, additional vertical restraint is fig. 02/ typical stowage plan
uplift. When using blockers or cleats it is required on the cargo. This may involve
important to know the vessel’s underdeck working at height, when using web or
framing in relation to the piece of cargo, chain lashings for the vertical restraint,
therefore an accurate drawing of the which in turn may require the use of a
vessel would be extremely useful. When cherry picker (or similar). Again, if this is
welding the blockers or cleats to the deck the case then the manoeuvrability and
it is important to do this in line with the dimensions of the machinery on the vessel
underdeck framing, as this will be the should be considered when creating a

ARTICLES | TIPS | VESSELS | NEWS & EVENTS


A PUBLICATION

8 9
THE HEAVYLIFT ENGINEER ISSUE 03

HEAVY LIFT TIP


GROUND BEARING UNDER
TRAILERS

Checking the suitability of the ground Individual Wheel Footprint


under modular trailers is formed of two If we look at a tyre under no load it is
aspects, ground bearing pressure (GBP) round, whereas under full load it has a
and surface composition. There are flat spot. The pressure inside the tyre will
different ways to calculate GBP, the two remain constant. The GBP local to the tyre
most common of which are shadow area will depend on the load on the trailers, the
and wheel footprint. pressure in the tyres and consequently the
size of the flat spot. The GBP would then
Shadow area be found in much the same way as the
This is simply a case of taking the area shadow area, dividing the total load by the
of the trailer and dividing it by the gross total area provided by the flat spots under
weight acting on the trailer. Quite often each wheel.
engineers will divide by the payload
weight, forgetting about the weights of For a thin surface, such as a barge deck or
the trailer, powerpacks and any packing similar, where there will be no distribution
steel. There are also various interpretations of load, the wheel footprint is a more
of what the “shadow area” is. These can realistic choice to check loadings. For
range from end axle to end axle and typical ground, the shadow area is more
bare trailer width, to overall trailer plan + likely to be valid and offers a simpler
200mm. check. Always compare the applied
GBP against the supplied ground bearing
For the shadow area to be valid the ground capacity to ensure the ground is capable of
surface needs to capable of receiving the taking the loads.
loads and transmitting it further down into
the subsoil without any deformation or
failure. This leads into the topic of surface
composition and suitability of the surface
to transmit the loads in this way. Therefore
the typical calculation of shadow area is of
the length of the trailer axle units x basic
width. Anything additional to this could
need further justification with respect to
surface composition. fig. 03/ typical trailer

ARTICLES | TIPS | VESSELS | NEWS & EVENTS


A PUBLICATION

10 11
THE HEAVYLIFT ENGINEER ISSUE 03

You could compose a book on the practise Height Restrictions


of building fabrication jigs - covering 16’ 1” (4.9m) clears motorway bridges at
everything from design and identification of 16’ 6”
build method, to the value of black builds
and testing phases involved. Here however, Trailer overhang (rear)
we would like to share our top five tips to < 3’ 6” (1067mm) No legal
consider when working on or with a jig requirements
fabrication project. < 6’ 0” (1828mm) End board
< 9’ 10” (2997mm) End & side
1. Ensure jigs are designed within boards
movable dimensions (height width) for > 9’ 10” (2997mm) End & side
road moves. boards, 2nd
man & police
Road Transport Restrictions (UK) notice
One critical aspect of every design is the Note:
logistics of transporting the jig to site after Over 3.5m width, provision of “private
fabrication, for first use. At the design stage, escort” covers requirement for 2nd Man
if required, the jigs can be designed as a (attendant).
flat pack kit of parts that can be assembled
at site. This avoids any requirements for Hauliers will in most case use this option.
escort vehicles and/or police escorts which
can not only increase costs but also delay 2. Identify build method from the
projects due to availability. Please refer to outset
road move guidelines: www.gov.uk/esdal- Fail to prepare, prepare to fail. Before
and-abnormal-loads commencing with the fabrication phase,
consideration must be given to the
Width Restrictions planning and build methodology. For
< 2.9m Within Gauge more complex details that require a large
>2.9m <3.5m Notify police & local amount of local welding, you may wish to

BUILDING FABRICATION JIGS - >3.5m <5.0m


councils 2 clear days
notice
2nd Man required, notify
sub-assemble the units in their pre-weld
state (i.e after tack welding together).
This ensures that all the mating faces are

5 TOP TIPS >4.3m <6.1m


police & local councils 2
clear days’ notice
private escort required.
accurately aligned prior to full welding.
During welding the intense heat can often
distort the steelwork and misalign the
See note below. mating faces resulting in additional efforts
WRITTEN BY ROSS MARSHALL >5.0m <6.1m VR1 required (www. being required, not to mention additional
PROJECT MANAGER, MALIN ABRAM highways.gov.uk/esdal), time and costs. It is better to catch this
notify police 2 clear days distortion at this stage rather than fully
notice weld and try fit misaligned joints after
>6.1m Special Order required welding, as by that point it’s far too late.
27.4m O/all Length≤ 150
Te GVW 3. Ensure Section sizes and grades are
readily available when designing
Length Restrictions Another issue that arises time and time
Max length 27.4m without special order. again is specifying section sizes that are
2nd Man over 18.3m not readily available. Having seen it before,
If drawbar trailer above exclusive of tractor the design phase closes out, the client is

fig. 04/ fabrication jig in production

ARTICLES | TIPS | VESSELS | NEWS & EVENTS


A PUBLICATION

12 13
THE HEAVYLIFT ENGINEER ISSUE 03

happy, enquiries for procurement go out it is a good opportunity to inspect and


BOOK RECOMMENDATIONS...
and at this point it becomes apparent that assess the structure before it is finally
the sections are not available. It is then dispatched.
back to the drawing board. By having
a designer’s manual/guide, it helps aid Therefore, ensuring all is as it should be SKUNKWORKS This book tells the true story behind
Lockheed’s legendary Skunk Works
book covers a great deal in an easy to
digest way.
design engineers throughout the design before arriving on site, usually the process BY BEN R. RICH & LEO from the perspective of the second
phase in choosing off the shelf sections would be as follows: man to take the reins and who carried Layered through all of this are
from the outset. These design guides are JANOS the flame of Kelly Johnson through leadership lessons and great stories
extremely useful, based upon years of two further decades of incredible behind the development of iconic and
lessons learned. success. There is not much marine ground breaking planes such as the
or even heavy lift in here, but the U2 spy-plane, SR-71 Blackbird and the
4. Green story of how to deliver research and F-117 Stealth Bomber.
As these jigs are generally suited to mate development that results in actual .
with another unit or piece of equipment products delivered against aggressive
there is often a consideration for green technological and competitive barriers
material to be left on. Generally speaking, has lessons that ring true and we can
this green would then be removed in situ learn a lot from today.
when the mating unit is surveyed and an
accurate interface is established. From the advocacy of tight knit small
When designing transportation jigs it is teams, supremely focused on a single
always a good idea to identify the mating goal, to lessons on where to play
unit so that considerations can be made for loose with controls and processes
tolerance and overlengthening materials. that can sometimes inhibit a team’s
development and reactiveness, the
5. Black Builds & Factory Acceptance
Testing (FAT)
When time permits its often a very
beneficial process to black build steelwork
before progressing to the surface finish
phase of a project. The term black build
“How generalists triumph in a
specialised world…“
must be assimilated becomes greater
with each passing year.
RANGE
refers to the process of assembling all BY DAVID EPSTEIN
components of the structure in their Much has been made of the 10,000 This is something that we talk about
pre-finished state. i.e before any surface hour rule and the concept that early in these pages regularly. In the
finishing takes place such as shotblasting specialisation is needed to excel in field of heavy lift engineering new
and/or painting. Doing this ensures life. In his book, David Epstein makes technologies are being perpetually
that all of the components fit and align a convincing case that breakthroughs developed and released. In order
as intended before committing to the in todays modern world, with its ever to effectively deliver across the full
finishing stages. Subsequently, if any increasing depth of specialisations, offering of modern turnkey heavy
issues do arise at this stage then they can will come from generalists who lift projects, you need to compliment
be rectified in a timely manner. If not, then have a specialism in one subject but depth in a chosen core field with a
you may have to redo the paint job , if command knowledge of many more. solid foundation in all the others.
areas are to be reworked.
There are a large number of
If the black build is not possible for compelling examples in the book,
whatever reason, a last precautionary some of which have been contested,
measure is to hold a Factory Acceptance but the core premise suggests,
Test or “FAT” – this acts as the review as the body of knowledge in the
stage before the structure is dis-assembled world on any given topic increases
and dispatched to site. Although this is at a never ending pace, it drives a
usually done after the structure is painted, perpetual narrowing and deepening
of specialities. Simply put, to be an
expert, the volume of knowledge that

ARTICLES | TIPS | VESSELS | NEWS & EVENTS


A PUBLICATION

14 15
THE HEAVYLIFT ENGINEER ISSUE 03

HEAVY LIFT TIP


CRANES ON BARGES

The incident at Alphen aan den Rijn ballasting, but it is important to note that
revealed a number of safety issues that this is rarely as quick as the crane can
occur when a crane is used on a barge. The take load. Any movement in the barge
collapse of the two mobile construction will result in the crane limits discussed
cranes which were standing on barges above becoming close to being exceeded.
highlighted several serious shortcomings In addition to the above, any angle in the
that should have been addressed during barge deck can also result in a change in
the preparations for the lift, as well the lift radius increasing load on the crane
as recommendations to improve risk components further.
management following the investigation.
Although using cranes on barges is Crane lifts on land require serious planning
common practice, there are critical matters for a range of matters, including lift radius,
that need to be considered before the lift ground conditions and load dimensions.
commences. However, when the lift calls for the crane
to be on a floating platform, the risks and
Mobile cranes are designed to be used on issues become even more complex. As
level ground. A mobile crane driver will well as needing to determine the reduced
be meticulous about getting the crane lifting capacity of the crane due to the
level when setting the outriggers. This is factors listed above, the stability of the
because the slew ring bearings on land- whole system also needs to be considered.
based cranes are limited, typically, in The vertical centre of gravity is a significant
out-of-level capacity by two degrees. Once factor in the stability of the barge and
you exceed this figure at maximum load, knowing where this is at all stages of a
slew ring failure is a strong possibility. dynamic lift is paramount. In the case of
In addition, the fleet angle of crane rope cranes on floating vessels, factors such as
acting on the sheaves at the tip of the jib the fact that on lifting a cargo clear the
is also limited. The sheaves are designed effect of the cog moves immediately to
for a vertical load, with only a slight out-of- the boom tip. Always ensure you have
plane allowance. specialist assistance and that proper
thought is given to the various elements
Although a typical flat top barge will have that come into play when a crane is
a level surface, the equilibrium of the subject to the dynamics of a barge.
barge will be affected by several factors
such as the load, ballasting and wind/
wave conditions. As soon as you introduce
an off centre load onto a barge - say by
lifting a load using a crane - the barge
will want to tilt. This can be countered by fig. 05/ barge and crane in situ

ARTICLES | TIPS | VESSELS | NEWS & EVENTS


A PUBLICATION

16 17
THE HEAVYLIFT ENGINEER ISSUE 03

LOCKDOWN
LESSONS
WRITTEN BY JOHN A. MACSWEEN
MANAGING DIRECTOR, MALIN GROUP

These unusual times have had a lot written The furlough provisions from the
about them on key issues such as struggles government were a welcome relief and a
with mental health, business cutbacks, huge help however, we made some errors
regulations and government assistance at the start - from initial interpretation on
and what it means to try and work when what is acceptable while on furlough to
at home with the entire family. I thought I failing to immediately update claims when
would share our experiences and mistakes folk come off furlough in a rush to service
in case it provides any assistance to others. work that comes in.

The last point is perhaps the most For example, we had put some senior
common. I had a quote passed to me by a staff on furlough and told them to do no
colleague that noted this is not a period of work but maintain a watching brief on
working from home, but one of trying to do their critical projects and flag up to those
work while forced to stay at home. This is still working if anything needs done… this
not semantics but an important difference. is not permitted. In another example, we
I have had a half clothed six year old come had a director on furlough under similar We also operate in a range of sectors. One doing things. The economic effects of
into Teams meetings and ask that I tell conditions and then failed to take him off of these, transport and shipping, is deemed this situation in certain industries will
everyone on the call how old he is. I have when he had to go on site for a rush job, critical and so here we can continue to reverberate for years. The overarching
had our last chicken (fox got the rest a few compounding the error. Similarly, we had a work. But to do so, we have to put in message to owners and managers
weeks ago) photo bomb a meeting. This is draughtsman re skill and do some training place procedures to ensure the setup and though is that the risks to your business
not business as normal and the message to to be able to work in Inventor… which working of a safe, temporary, marine site. are greater than just getting revenue
our staff is to do your best, but don’t worry is permitted… but one of the models he through the door, hard as that may be.
if you have not logged your allotted hours created of a hatch found its way into a bid We also have a small fabrication facility Legislative compliance, staff well being,
(and be careful if you are logging a lot as an example graphic… which is not. based in Scotland, working on a range and even just the day to day good running
more as work and home life blur together). of projects from defence to renewables. of your business processes and updating
My advice? Get guidance and do a root and We had implemented procedures and when required, which under normal
The effect this lockdown has had on staff branch review now and learn the lessons processes that allowed continuation of circumstances is par for the course, all
forced to stay at home, in our experience, so you can declare and correct errors as we safe work. There was some confusion need a part of your time as well.
is also wide and varied. Some thrive, some did. We were lucky when a staff member in our sector though, whether or not
don’t. I have heard from most that there pointed out these out to us which made this was permitted in Scotland and we But don’t lose sight of the positives – time
are good days and bad days. Celebrate the us quickly stop and re-assess. We found stood the team down for a week while for training, increased use of technology
good days and give yourself and your staff errors in a minority of over 60 claims we investigated. Fortunately a clarifying and especially in our own case, a
time to recover from the bad ones. It has, made, but nevertheless whether errors in question in the Scottish Assembly made reminder of the tenacity and team spirit
however, lessened our apprehension for interpretation or procedure, mistakes they the position clear and allowed us to restart of colleagues, even in the toughest times.
working from home and it has forced us all certainly were. If we had not done the projects deemed critical,with all the right And most of all, if at home, welcome the
to employ the technology we had at our review, these would have compounded procedures in place. opportunity to turn commuting time into
fingertips but were not utilising fully. When and we possibly would have sailed on to a family time.
back, first task for us will be a review with disaster. Wider government support for the fall
everyone to see what positive lessons can out from this will need to be far reaching
come from this experience. as everyone adjusts to a new way of

ARTICLES | TIPS | VESSELS | NEWS & EVENTS


A PUBLICATION

18 19
THE HEAVYLIFT ENGINEER ISSUE 03

HEAVY LIFT TIP


DECK STRENGTH

When selecting a suitable vessel to In addition to the above, the loads due
transport project cargo, you often receive to the motion of the ship are often-
a very basic specification for the ship overlooked, i.e. the combination of static
itself, informing you of the ship’s main weight, heave acceleration and either roll
particulars and hold size. A key factor or pitch accelerations and motions. The
that is considered at this stage is the hold ships motions will increase these local
dimension; i.e. whether the project cargo deck loads further.
will fit. Sometimes the global deck load
capacity is considered, but this only tends If not properly engineered, there is risk
to be with respect to the Cargo's overall that the ship’s deck structure becomes
footprint area and weight vs the ship’s damaged due to extreme loads, which
deck capacity in tonnes per square metre. could lead to the cargo being damaged or
lost. However, the issue can be mitigated
Consider a hypothetical cargo weighing through structural analysis of the vessel’s
200 Te with a foot print of 10m x 8m (or deck structure in way of the supports
80m2). This would show a static deck load and implementing load-spreading where
of 2.5Te/m2, acceptable for most cargo required.
vessels, regardless of whether the cargo
is stowed on the tank-top, tween deck or In any case, you should always look to
hatch covers. engage a highly-skilled engineer – such
as a structural engineer or naval architect
However, issues can arise once the vessel - who can perform such checks on the
has been booked and further details of the vessels deck structure where there are
cargo are then later released. Suddenly it concerns over the deck strength.
is noted that the cargo has bearing pads or
support feet (4 off at 0.3m X 0.3m each)
and it is not permitted to support the cargo
anywhere else. Now we realise that the
static weight of 200Te is supported on a
total contact area of 0.36m2; the total area
of the supporting feet.
It should be clear that the static loading
has now increased from 2.5 Te/m2 to
555.5Te/m2 a significant increase in local
deck load.
fig. 06/ support secured on deck

ARTICLES | TIPS | VESSELS | NEWS & EVENTS


A PUBLICATION

20 21
THE HEAVYLIFT ENGINEER ISSUE 03

Regulation A-3 Exceptions…. discharge, pumped or gravity. This is


attractive for all vessels as treatment/
5. the discharge of Ballast Water and conditioning by in-line BWTS during

IS EXCEPTION A-3.5 THE SOLUTION Sediments from a ship at the same location
where the whole of that Ballast Water and
those Sediments originated and
discharge is the source of many non-
compliant BW discharges.

TO HEAVY LIFT/SEMI SUBMERSIBLE? provided that no mixing with unmanaged


Ballast Water and Sediments from other
areas has occurred. If mixing has occurred,
Second, and most applicable to heavy
lift operators: The ballast tank is the
“treatment event”. This means a semi-
the Ballast Water taken from other submersible can enter a project location
WRITTEN BY GILES CANDY areas is subject to Ballast Water with its tanks registered as treated and
ENVIROCLEANSE LLC Management in accordance with this neutralized “ready for discharge” - whether
Annex. partially full or not does not matter. Once
at the project location the vessel can flood
At first glance it seems as though this any tanks by pump or gravity, and then
I have been involved with Ballast Water realities of what could be described as exception should apply to a heavy lift discharge any tanks, by pump or gravity
Treatment since 2002 when the inventor of niche maritime operations. The extent of vessel. However, when reviewed with and will not have to treat any of that water
the Venturi Oxygen Stripping BWTS (BWTS), the impact both; numerically, the number careful attention to operations and ballast until moving to the next location.
Peter McNulty, came into my office and of vessels and operators, and operationally, tank construction it is soon understood
announced he had a great idea for a Ballast to the safe economic completion of work an in-place flood and drain operation will In the language of the exception; the water
Water Treatment System – VOS. Being a is, I believe, wildly underestimated by leave much untreated ballast trapped in and sediments in the tanks as the vessel
project manager at a company completing regulators. the tanks with no way for an in-line BWTS enters the project location have been fully
terrestrial water treatment, this statement to go back and treat. It does not matter “managed”. This fully managed water can
meant nothing to me. How things change… I had extended meetings in Holland if the flood and drain is by gravity or be mixed with local water and discharged
introducing VOS and actively discussed pumped, the exception will not apply. This in the same location. As the vessel sails
I remember Peter’s call in 2004, “The getting the Dutch Administration to is a very unforgiving situation for many away it will have to treat those tanks
Convention is Final” and went to work for propose an Exception to be added to HL operations and until recently there was again, but the in “location” operations can
his N.E.I. Treatment Systems company in The Convention specifically for semi- no way around either cleaning tanks or all be completed without treatment.
2006. N.E.I.’s VOS is a valid no filter BWTS, submersible Heavy Lift operations. In treating all ballast waters.
the first BWTS to be “IMO” Type Approved 2010 The Netherlands presented MEPC 61 It is unfortunate the U.S. ballast water rules
in 2007. Sometime after that we were with a document clearly describing the At MEPC 63 (2011) and MEPC (64 (2012) do not have the same Exception (VIDA may
approached to write a proposal for the “operational barriers” for these vessels, Holland and Singapore submitted “Internal change this, lobbying will help), but for the
Pioneer Spirit. I did a double take of the but no specific exception was passed. Circulation” BWTS (ICBWTS) as solutions rest of the world a vessel which needs to
ballasting numbers, then had a long call This leaves heavy lift vessels all having to for semi-submersible and drill rigs complete in-place ballasting/deballasting
with the representative engineers. That comply with the The Convention. There is respectively. The submittals described how operations can do so without treatment.
was the first time I really got to think no recourse, only clean tanks before every an ICBWTS meets A-3.5 but did not list any
about the issues facing a semi-submersible in-place flood and discharge operation, or commercially available systems. From an operational point of view, an
heavy lift vessel or rig trying to operate treat all ballast water whether used for, ICBWT has many fundamental advantages
in compliance with the ballast water in-place ballasting, trim, transit ballasting Why does an ICBWTS satisfy Exception for most vessel types; no filters, no
regulations. The best I could come up with or otherwise. A-3.5? An ICBWTS makes each ballast power use in port, no change to cargo
at the time was that VOS did not use filters tank its own treatment event, there is or ballasting activities, no matter BW
and was not flow constrained, normal The IMO’s BW Convention does list five no untreated residual. This does lead to quality, reduced impact of failures - the
operation would require a VERY large Exceptions which allow a vessel to a larger control program and additional vessel is at sea, control over compliance
system though. discharge without completing treatment piping, but it makes two fundamental (today’s sleeper issue in the BW regulatory
IF the conditions of the Exception are differences regarding compliance. field) etc. Internal Circulation can be a
The rapid in-place flooding and deballasting met. The fifth Exception, A-3.5, looks as fundamentally more elegant solution to
of a semi-submersible vessel is the “thing” though it should fit HL operations, allowing First: Treatment and neutralization is BW compliance for a commercial vessel.
which allows a semi-sub to do its job in a vessel with a conventional BWTS to recorded in the tank before discharge Internal Circulation is the way for a Heavy
the way it was engineered to do – and complete in-place ballasting/deballasting, commences so the vessel’s technical Lifter to satisfy Exception A-3.5.
there is no lack of specialized engineering without treatment: compliance with the TA Certificate is
on these vessels. But the IMO and U.S. BW already recorded before discharge begins,
regulations remain deaf to the operational no conditioning or treatment during

ARTICLES | TIPS | VESSELS | NEWS & EVENTS


A PUBLICATION

22 23
THE HEAVYLIFT ENGINEER ISSUE 03

fig. 08/ inTank BWTS in situ - single unit serving all four pontoons

If IC is such a good solution, why are there Lifts from NYK, MR’s from Enterprises
no ICBWTS on the market? For years the and VLCC’s from Pantheon Tankers and a
Cold Harbour inert gas based ICBWTS has leading ME VLCC owner operator, with half
been available but without USCG Type a dozen systems now installed.
Approval. More recently another ICBWTS
has come to market; Using DNV-GL as the Significantly for semi-submersible vessels,
Independent Laboratory inTank was USCG/ Diamond Offshore installed inTank aboard
IMO Type Approved last year. inTank is a their recommissioned semi-submersible rig
BWTS product of Envirocleanse LLC based in the Ocean Onyx. This sale was specifically
Houston Texas. because inTank allows a semi-submersible
to complete its normal operations with
As an independent Consultant in 2016, I minimal disruption due to ballast water
read the first Press Release for the inTank treatment.
BWTS. I’d not heard of Envirocleanse, but
I’d heard of Berkshire Hathaway, the owner
of their parent company so I reached out
to Matt Hughes, VP at Envirocleanse. I was
soon sure this ICBWTS would make it to
market, now it has.
inTank has received orders for; Capes from
fig. 07/ Ocean Onyx Deckhouse CMB Bocimar and Alpha Bulkers, Heavy

ARTICLES | TIPS | VESSELS | NEWS & EVENTS


A PUBLICATION

24 25
THE HEAVYLIFT ENGINEER ISSUE 03

HEAVY LIFT TIP


HOOK HEIGHTS

Most people involved in heavy lift and at the various radii of the lift. As the
cargo loading operation are familiar with mobile crane booms out (increasing
the term ‘Hook Height’ describing the radius) the available hook height
vertical distance from the ground up to the decreases as a function of the boom
highest point the crane hook can go. length and radius of interest. Thus we
need to consider the hook height at
When it comes to loading project cargo the following radii; initial lift, hatch
or any crane lift really, getting this wrong coaming or vertical obstruction and set
could be the difference between being down.
able to complete the lift or not. So, what
are the factors that could adversely affect It should be noted that although you can
the ‘Hook Height’ (HH) of a lift? get a crane capable of lifting a particular
weight at the required radius it may not
• Height of cargo lift points, the higher have the available hook height when the
these are the less height there is left 4 points above are considered and a large
for the lift. crane may be required.
• Lift rigging; the height of the rigging
between the hook and cargo lifting When discussing your lifting requirements
points, this height is added to the with your designated ‘Appointed Person,’
height of the lift points and the total make sure they are given all the relevant
subtracted from the hook height. information with respect to lifting radii,
The rigging arrangement will further obstructions, height of lift points and lift
reduce the available hook height. rigging requirements. Early engagement
• Height of hatch coaming above quay with a suitable lifting specialist will help to
side during lift, or any other vertical ensure you have the right crane with the
obstruction we need to lift over. On available hook height to perform the lift.
tidal berths the height of the hatch
coaming will vary with the state
of tide, i.e. at high water the hatch
coaming will be at the highest point
above the quay and so this height
is also subtracted from the available
hook height.
• Crane specification; when using mobile
cranes for lifting cargo we need to
take care to consider the available
hook height for the total lift weight fig. 09/ crane with high hook height

ARTICLES | TIPS | VESSELS | NEWS & EVENTS


A PUBLICATION

26 27
HEAVYLIFT MAGAZINE • DESIGN OF SHIP
COMING EDITION 4 BUILD AND
TRANSPORTATION
• CONSIDER
AUTUMN TRANSPORTING
BEFORE IT'S TOO LATE
CRADLES FOR FLOAT
OFF LAUNCHES
2020 • MOORING ANALYSIS

To receive future exciting editions, please register at www.heavyliftengineer.com


A MALIN GROUP PUBLICATION
SOUTH ROTUNDA
100 GOVAN ROAD
PACIFIC QUAY
GLASGOW
G51 1AY
WWW.MALINGROUP.COM

You might also like