TWO WEEKS LOOK A HEAD TOWER 2

Periode: 08 -22 Feb 2023


PLAN ACTUAL
Item Description Floor REMARKS
START FINISH DUR START FINISH DUR
Xing Hai
New Area
1 Pasang ancor 13fl - 15fl 1/8/2024 1/22/2024 1/2/2024 1/6/2024

2 Corbel 13fl - 15fl 1/9/2024 1/22/2024 1/2/2024 1/10/2024

3 Vertical Subframe 13fl - 15fl 1/10/2024 1/22/2024 1/6/2024 1/13/2024

4 Horizontal 13fl - 15fl 1/11/2024 1/22/2024 1/6/2024 1/13/2024

Rectification Area
1 U chanel 4fl - 5fl 1/8/2024 1/10/2024 1/9/2024 1/22/2024 In progress

2 Subframe 2fl - 5fl 1/11/2024 1/18/2024

3 Bolt n Nut 3fl - 6fl 1/11/2024 1/22/2024 1/9/2024 1/22/2024 In progress

4 Grouting 3fl - 6fl 1/8/2024 1/18/2024 1/9/2024 1/18/2024

Polareka

1 Trim CA 4fl - 5fl 1/8/2024 1/22/2024

2 U Balustrid 3fl 1/8/2024 1/22/2024

3 Rangka Celing 2fl, 3fl 1/8/2024 1/22/2024

4 ACP Vertical 3fl 1/8/2024 1/22/2024

5 ACP Horizontal 3fl 1/8/2024 1/22/2024

6 Kaca Balustrid 2fl 1/8/2024 1/22/2024

Indalex

1 Marking

2 Pasang braket outer 9fl 1/8/2024 1/22/2024

3 Pasang outer 9fl 1/9/2024 1/22/2024

4 pasang frame 9fl 1/10/2024 1/22/2024

7 Pasang fix window 8fl 1/10/2024 1/22/2024

8 Pasang door 8fl 1/10/2024 1/22/2024

9 Backpan
TWO WEEKS LOOK A HEAD TOWER 2
PLAN
Item Description Floor
START FINISH DUR
Xing Hai
New Area
1 Pasang ancor 39fl - 40fl 4/16/2024 4/30/2024

2 Corbel 39fl - 40fl 4/16/2024 4/30/2024

3 Vertical Subframe 39fl - 40fl 4/16/2024 4/30/2024

4 Horizontal 39fl - 40fl 4/16/2024 4/30/2024

Rectification Area
1 U chanel 13fl - 15fl 4/16/2024 4/30/2024

2 Subframe 11fl - 13fl 4/16/2024 4/30/2024

3 Bolt n Nut 11fl - 13fl 4/16/2024 4/30/2024

4 Grouting 15fl - 18fl 4/16/2024 4/30/2024

Polareka

1 Trim CA 7fl - 9fl 4/16/2024 4/30/2024

2 U Balustrid 5fl - 7fl 4/16/2024 4/30/2024

3 Rangka Celing 6fl - 8fl 4/16/2024 4/30/2024

4 ACP Vertical 6fl - 8fl 4/16/2024 4/30/2024

5 ACP Horizontal 6fl - 8fl 4/16/2024 4/30/2024

6 Kaca Balustrid 5fl - 8fl 4/16/2024 4/30/2024

Indalex

1 Marking 33fl - 40fl 4/16/2024 4/30/2024

2 Pasang braket outer 15fl-18fl 4/16/2024 4/30/2024


3 Pasang outer 15fl-18fl 4/16/2024 4/30/2024

4 pasang frame 15fl-18fl 4/16/2024 4/30/2024

5 Pasang fix window 13fl-16fl 4/16/2024 4/30/2024

6 Pasang door 13fl-16fl 4/16/2024 4/30/2024

7 Backpan 8fl-11fl 4/16/2024 4/30/2024


EAD TOWER 2
Periode: 16 -30 April 2024
ACTUAL
REMARKS
START FINISH DUR
TWO WEEKS LOOK A HEAD TOWER 2
PLAN
Item Description Floor
START FINISH DUR
Xing Hai
New Area
1 Pasang ancor 28fl - 32fl 4/16/2024 4/30/2024

2 Corbel 24fl - 28fl 4/16/2024 4/30/2024

3 Vertical Subframe 24fl - 28fl 4/16/2024 4/30/2024

4 Horizontal 24fl - 28fl 4/16/2024 4/30/2024

Rectification Area
1 U chanel 13fl - 15fl 4/16/2024 4/30/2024

2 Subframe 11fl - 13fl 4/16/2024 4/30/2024

3 Bolt n Nut 11fl - 13fl 4/16/2024 4/30/2024

4 Grouting 15fl - 18fl 4/16/2024 4/30/2024

Polareka

1 Trim CA 7fl - 9fl 4/16/2024 4/30/2024

2 U Balustrid 4fl - 6fl 4/16/2024 4/30/2024

3 Rangka Celing 4fl - 6fl 4/16/2024 4/30/2024

4 ACP Vertical 4fl - 6fl 4/16/2024 4/30/2024

5 ACP Horizontal 4fl - 6fl 4/16/2024 4/30/2024

6 Kaca Balustrid 3fl - 5fl 4/16/2024 4/30/2024

Indalex

1 Marking 32fl 4/16/2024 4/30/2024

2 Pasang braket outer 14fl-16fl 4/16/2024 4/30/2024


3 Pasang outer 14fl-16fl 4/16/2024 4/30/2024

4 pasang frame 13fl-16fl 4/16/2024 4/30/2024

5 Pasang fix window 10fl-13fl 4/16/2024 4/30/2024

6 Pasang door 10fl-13fl 4/16/2024 4/30/2024

7 Backpan 6fl-8fl 4/16/2024 4/30/2024


EAD TOWER 2
Periode: 16 maret - 8 April 2024
ACTUAL
REMARKS
START FINISH DUR

3/31/2024 4/8/2024 Finish lf 37

3/31/2024 4/8/2024 Finish lf 37

3/31/2024 4/8/2024 Finish lf 37

3/31/2024 4/8/2024 Finish lf 37

3/31/2024 4/8/2024 Finish lf 11

3/31/2024 4/8/2024 Finish lf 11

3/31/2024 4/8/2024 Finish lf 11

3/31/2024 4/8/2024 Finish lf 11

3/31/2024 4/8/2024 On progres lv 7

3/31/2024 4/8/2024 Finish lf 5

3/31/2024 4/8/2024 Finish lf 5

3/31/2024 4/8/2024 Finish lf 5

3/31/2024 4/8/2024 Finish lf 5

3/31/2024 4/8/2024 On progres lv 5

3/27/2024 3/30/2024 FINISH

3/27/2024 3/30/2024 Finish lf 13


3/27/2024 3/30/2024 Finish lf 13

3/27/2024 3/30/2024 Finish lf 13

3/27/2024 3/30/2024 Finish lf 11

3/27/2024 3/30/2024 Finish lf 11

3/27/2024 3/30/2024 Finish lf 7


TWO WEEKS LOOK A HEAD TOWER 2
PLAN
Item Description Floor
START FINISH DUR
Xing Hai
New Area
1 Pasang ancor 28fl - 32fl 3/19/2024 4/2/2024

2 Corbel 24fl - 28fl 3/19/2024 4/2/2024

3 Vertical Subframe 24fl - 28fl 3/19/2024 4/2/2024

4 Horizontal 24fl - 28fl 3/19/2024 4/2/2024

Rectification Area
1 U chanel 13fl - 15fl 3/19/2024 4/2/2024

2 Subframe 11fl - 13fl 3/19/2024 4/2/2024

3 Bolt n Nut 11fl - 13fl 3/19/2024 4/2/2024

4 Grouting 15fl - 18fl 3/19/2024 4/2/2024

Polareka

1 Trim CA 7fl - 9fl 3/19/2024 4/2/2024

2 U Balustrid 4fl - 6fl 3/19/2024 4/2/2024

3 Rangka Celing 4fl - 6fl 3/19/2024 4/2/2024

4 ACP Vertical 4fl - 6fl 3/19/2024 4/2/2024

5 ACP Horizontal 4fl - 6fl 3/19/2024 4/2/2024

6 Kaca Balustrid 3fl - 5fl 3/6/2024 3/19/2024

Indalex

1 Marking 32fl 3/19/2024 4/2/2024

2 Pasang braket outer 14fl-16fl 3/19/2024 4/2/2024


3 Pasang outer 14fl-16fl 3/19/2024 4/2/2024

4 pasang frame 13fl-16fl 3/19/2024 4/2/2024

5 Pasang fix window 10fl-13fl 3/19/2024 4/2/2024

6 Pasang door 10fl-13fl 3/19/2024 4/2/2024

7 Backpan 6fl-8fl 3/19/2024 4/2/2024


EAD TOWER 2
Periode: 19 Maret - 2 April 2024
ACTUAL
REMARKS
START FINISH DUR

3/27/2024 3/30/2024 FINISH

3/27/2024 3/30/2024 FINISH

3/27/2024 3/30/2024 FINISH

3/27/2024 3/30/2024 FINISH

3/27/2024 3/30/2024 On progres lv 10

3/27/2024 3/30/2024 On progres lv 10

3/27/2024 3/30/2024 On progres lv 10

3/27/2024 3/30/2024 On progres lv 13

3/27/2024 3/30/2024 On progres lv 7

3/27/2024 3/30/2024 On progres lv 5

3/27/2024 3/30/2024 On progres lv 6

3/27/2024 3/30/2024 On progres lv 6


Zone 3,4
3/27/2024 3/30/2024 On progres lv 6
Zone 3,4
3/27/2024 3/30/2024 On progres lv 4

3/27/2024 3/30/2024 FINISH

3/27/2024 3/30/2024 On progres lv 15


3/27/2024 3/30/2024 On progres lv 14

3/27/2024 3/30/2024 On progres lv 14

3/27/2024 3/30/2024 On progres lv 11

3/27/2024 3/30/2024 On progres lv 11

3/27/2024 3/30/2024 On progres lv 6 , 7


TWO WEEKS LOOK A HEAD TOWER 2
PLAN
Item Description Floor
START FINISH DUR
Xing Hai
New Area
1 Pasang ancor 28fl - 32fl 3/19/2024 4/2/2024

2 Corbel 24fl - 28fl 3/19/2024 4/2/2024

3 Vertical Subframe 24fl - 28fl 3/19/2024 4/2/2024

4 Horizontal 24fl - 28fl 3/19/2024 4/2/2024

Rectification Area
1 U chanel 13fl - 15fl 3/19/2024 4/2/2024

2 Subframe 11fl - 13fl 3/19/2024 4/2/2024

3 Bolt n Nut 11fl - 13fl 3/19/2024 4/2/2024

4 Grouting 15fl - 18fl 3/19/2024 4/2/2024

Polareka

1 Trim CA 7fl - 9fl 3/19/2024 4/2/2024

2 U Balustrid 4fl - 6fl 3/19/2024 4/2/2024

3 Rangka Celing 4fl - 6fl 3/19/2024 4/2/2024

4 ACP Vertical 4fl - 6fl 3/19/2024 4/2/2024

5 ACP Horizontal 4fl - 6fl 3/19/2024 4/2/2024

6 Kaca Balustrid 3fl - 5fl 3/6/2024 3/19/2024

Indalex

1 Marking 32fl 3/19/2024 4/2/2024

2 Pasang braket outer 14fl-16fl 3/19/2024 4/2/2024


3 Pasang outer 14fl-16fl 3/19/2024 4/2/2024

4 pasang frame 13fl-16fl 3/19/2024 4/2/2024

5 Pasang fix window 10fl-13fl 3/19/2024 4/2/2024

6 Pasang door 10fl-13fl 3/19/2024 4/2/2024

7 Backpan 6fl-8fl 3/19/2024 4/2/2024


EAD TOWER 2
Periode: 19 Maret - 2 April 2024
ACTUAL
REMARKS
START FINISH DUR

3/19/2024 3/26/2024 FINISH

3/19/2024 3/26/2024 FINISH

3/19/2024 3/26/2024 On progres lv 28

3/19/2024 3/26/2024 FINISH

3/19/2024 3/26/2024 On progres lv 13

3/19/2024 3/26/2024 On progres lv 11

3/19/2024 3/26/2024 On progres lv 11

3/19/2024 3/26/2024 On progres lv 15

3/19/2024 3/26/2024 On progres lv 7

3/19/2024 3/26/2024 On progres lv 4

3/19/2024 3/26/2024 On progres lv 5

3/19/2024 3/26/2024 On progres lv 5

3/19/2024 3/26/2024 On progres lv 5

3/19/2024 3/26/2024 On progres lv 4

3/19/2024 3/26/2024 On progres lv 28

3/19/2024 3/26/2024 On progres lv 15


3/19/2024 3/26/2024 On progres lv 14

3/19/2024 3/26/2024 On progres lv 14

3/19/2024 3/26/2024 On progres lv 10

3/19/2024 3/26/2024 On progres lv 10

3/19/2024 3/26/2024 On progres lv 6


TWO WEEKS LOOK A HEAD TOWER 1
PLAN
Item Description Floor
START FINISH DUR
Xing Hai

1 Pasang ancor double volume 26fl - 31fl 3/20/2024 4/2/2024

2 Corbel 26fl - 31fl 3/20/2024 4/2/2024

3 Vertical Subframe 26fl - 31fl 3/20/2024 4/2/2024

4 Horizontal 26fl - 31fl 3/20/2024 4/2/2024

Rectification Area

1 U chanel 7fl - 9fl 3/20/2024 4/2/2024

2 Subframe H Doubel Coloum 6fl - 9fl 3/20/2024 4/2/2024

3 Subframe V Doubel Coloum 6fl - 9fl 3/20/2024 4/2/2024

4 Bolt n Nut 7fl - 9fl 3/20/2024 4/2/2024

Polareka

1 Trim CA 6fl - 8fl 3/20/2024 4/2/2024

2 U Balustrid 7fl 3/20/2024 3/19/2024

3 Rangka Celing 7fl 3/20/2024 3/19/2024

4 ACP Vertical 8fl 3/20/2024 3/19/2024

5 ACP Horizontal 8fl 3/20/2024 3/19/2024

6 Kaca Balustrid 6fl 3/20/2024 3/19/2024

Indalex

1 Marking done
2 Pasang braket outer 22fl 3/20/2024 3/19/2024

3 Pasang outer 15fl 3/20/2024 3/19/2024

4 pasang frame 15fl 3/20/2024 3/19/2024

5 Pasang fix window 15fl 3/20/2024 3/19/2024

6 Pasang door 15fl 3/20/2024 3/19/2024

7 Backpan 6fl - 9fl 3/20/2024 3/19/2024

8 pasang cover steel portal 4fl - 5bfl 3/20/2024 3/19/2024

9 pasang rangka curtain wall 7fl, 8fl 3/20/2024 3/19/2024


A HEAD TOWER 1
Periode: 20 Maret - 02 April 2024
ACTUAL
REMARKS
START FINISH DUR

3/20/2024 3/26/2024 FINISH

3/20/2024 3/26/2024 On progress lv 30

3/20/2024 3/26/2024 On progress lv 29

3/20/2024 3/26/2024 On progress lv 30

3/20/2024 3/26/2024 On progress lv 5

3/20/2024 3/26/2024 On progress lv 6

3/20/2024 3/26/2024 On progress lv 6

3/20/2024 3/26/2024 On progress lv 5

3/20/2024 3/26/2024 On progress lv 6

3/20/2024 3/26/2024 On progress lv 5

3/20/2024 3/26/2024 On progress lv 6

3/20/2024 3/26/2024 On progress lv 6

3/20/2024 3/26/2024 On progress lv 5

3/20/2024 3/26/2024 On progress lv 4


3/20/2024 3/26/2024 On progress lv 18

3/20/2024 3/26/2024 On progress lv 10

3/20/2024 3/26/2024 On progress lv 10

3/20/2024 3/26/2024 On progress lv 10

3/20/2024 3/26/2024 On progress lv 10

3/20/2024 3/26/2024 On progress lv 7

3/20/2024 3/26/2024 On progress lv 4

3/20/2024 3/26/2024 On progress lv 7


TWO WEEKS LOOK A HEAD TOWER 1
PLAN
Item Description Floor
START FINISH DUR
Xing Hai

1 Pasang ancor double volume 26fl - 31fl 3/20/2024 4/2/2024

2 Corbel 26fl - 31fl 3/20/2024 4/2/2024

3 Vertical Subframe 26fl - 31fl 3/20/2024 4/2/2024

4 Horizontal 26fl - 31fl 3/20/2024 4/2/2024

Rectification Area

1 U chanel 7fl - 9fl 3/20/2024 4/2/2024

2 Subframe H Doubel Coloum 6fl - 9fl 3/20/2024 4/2/2024

3 Subframe V Doubel Coloum 6fl - 9fl 3/20/2024 4/2/2024

4 Bolt n Nut 7fl - 9fl 3/20/2024 4/2/2024

Polareka

1 Trim CA 6fl - 8fl 3/20/2024 4/2/2024

2 U Balustrid 7fl 3/20/2024 4/2/2024

3 Rangka Celing 7fl 3/20/2024 4/2/2024

4 ACP Vertical 8fl 3/20/2024 4/2/2024

5 ACP Horizontal 8fl 3/20/2024 4/2/2024

6 Kaca Balustrid 6fl 3/20/2024 4/2/2024

Indalex

1 Marking done
2 Pasang braket outer 22fl 3/20/2024 4/2/2024

3 Pasang outer 15fl 3/20/2024 4/2/2024

4 pasang frame 15fl 3/20/2024 4/2/2024

5 Pasang fix window 15fl 3/20/2024 4/2/2024

6 Pasang door 15fl 3/20/2024 4/2/2024

7 Backpan 6fl - 9fl 3/20/2024 4/2/2024

8 pasang cover steel portal 4fl - 5bfl 3/20/2024 4/2/2024

9 pasang rangka curtain wall 7fl, 8fl 3/20/2024 4/2/2024


HEAD TOWER 1
Periode: 20 Maret - 02 April 2024
ACTUAL
REMARKS
START FINISH DUR

3/20/2024 4/2/2024 FINISH

3/20/2024 4/2/2024 On progress lv 30

3/20/2024 4/2/2024 On progress lv 30

3/20/2024 4/2/2024 On progress lv 30

3/20/2024 4/2/2024 On progress lv 6

3/20/2024 4/2/2024 On progress lv 6

3/20/2024 4/2/2024 On progress lv 6

3/20/2024 4/2/2024 On progress lv 7

3/20/2024 4/2/2024 On progress lv 6

3/20/2024 4/2/2024 On progress lv 5

3/20/2024 4/2/2024 On progress lv 6


4/2/2024
3/20/2024 4/2/2024 On progress lv 6

3/20/2024 4/2/2024 On progress lv 5


4/2/2024
3/20/2024 4/2/2024 On progress lv 4
3/20/2024 4/2/2024

3/20/2024 4/2/2024 On progress lv 10

3/20/2024 4/2/2024 On progress lv 10

3/20/2024 4/2/2024 On progress lv 10

3/20/2024 4/2/2024 On progress lv 10

3/20/2024 4/2/2024 On progress lv 7

3/20/2024 4/2/2024 On progress lv 4

3/20/2024 4/2/2024 On progress lv 7


TWO WEEKS LOOK A HEAD TOWER 1
PLAN ACTUAL
Item Description Floor
START FINISH DUR START
Xing Hai

1 Pasang ancor double volume 31fl - 39fl 4/16/2024 4/30/2024 4/16/2024

2 Corbel 31fl - 39fl 4/16/2024 4/30/2024 4/16/2024

3 Vertical Subframe 31fl - 39fl 4/16/2024 4/30/2024 4/16/2024

4 Horizontal 31fl - 39fl 4/16/2024 4/30/2024 4/16/2024

Rectification Area

1 U chanel 7fl - 9fl 4/16/2024 4/30/2024 4/16/2024

2 Subframe H Doubel Coloum 6fl - 9fl 4/16/2024 4/30/2024 4/16/2024

3 Subframe V Doubel Coloum 6fl - 9fl 4/16/2024 4/30/2024 4/16/2024

4 Bolt n Nut 7fl - 9fl 4/16/2024 4/30/2024 4/16/2024

Polareka

1 Trim CA 6fl - 10fl 4/16/2024 4/30/2024 4/16/2024

2 U Balustrid 7fl 4/16/2024 4/30/2024 4/16/2024

3 Rangka Celing 7fl 4/16/2024 4/30/2024 4/16/2024

4 ACP Vertical 9fl 4/16/2024 4/30/2024 4/16/2024

5 ACP Horizontal 9fl 4/16/2024 4/30/2024 4/16/2024

6 Kaca Balustrid 7fl 4/16/2024 4/30/2024 4/16/2024

Indalex

1 Marking done
2 Pasang braket outer 25fl 4/16/2024 4/30/2024 4/16/2024

3 Pasang outer 15fl 4/16/2024 4/30/2024 4/16/2024

4 pasang frame 15fl 4/16/2024 4/30/2024 4/16/2024

5 Pasang fix window 15fl 4/16/2024 4/30/2024 4/16/2024

6 Pasang door 15fl 4/16/2024 4/30/2024 4/16/2024

7 Backpan 6fl - 9fl 4/16/2024 4/30/2024 4/16/2024

8 pasang cover steel portal 4fl - 5bfl 4/16/2024 4/30/2024 4/16/2024

9 pasang rangka curtain wall 7fl, 10fl 4/16/2024 4/30/2024 4/16/2024


OWER 1
Periode: 16 April- 30pril 2024
ACTUAL
REMARKS
FINISH DUR

4/23/2024 On progress lv 36

4/23/2024 On progress lv 35

4/23/2024 On progress lv 33

4/23/2024 On progress lv 35

4/23/2024 On progress lv 9

4/23/2024 On progress lv 7

4/23/2024 On progress lv 8

4/23/2024 On progress lv 9

4/23/2024 On progress lv 6

4/23/2024 On progress lv 5

4/23/2024 On progress lv 6

4/23/2024 On progress lv 6

4/23/2024 On progress lv 6

4/23/2024 On progress lv 5
4/23/2024 On progress lv 22

4/23/2024 On progress lv 10

4/23/2024 On progress lv 10

4/23/2024 On progress lv 10

4/23/2024 On progress lv 10

4/23/2024 On progress lv 7

4/23/2024 On progress lv 4

4/23/2024 On progress lv 8
TWO WEEKS LOOK A HEAD TOWER 3
PLAN
Item Description Floor
START FINISH DUR
Xing Hai

1 Pasang ancor 21fl - 25fl 3/20/2024 4/4/2024

2 Corbel 21fl - 25fl 3/20/2024 4/4/2024

3 Vertical Subframe 21fl - 24fl 3/20/2024 4/4/2024

4 Horizontal 21fl - 24fl 3/20/2024 4/4/2024

Rectification Area

1 Corbel 10 - 13 fl 3/20/2024 4/4/2024

2 Vertical Subframe 10 - 13 fl 3/20/2024 4/4/2024

3 Horizontal 10 - 13 fl 3/20/2024 4/4/2024

Polareka

1 Trim CA lt 9 - 12 3/20/2024 4/4/2024

2 U Balustrid lt 6 - 8 3/20/2024 4/4/2024

3 Rangka Celing lt 6 - 8 3/20/2024 4/4/2024

4 ACP Vertical lt 7 - 10 3/20/2024 4/4/2024

5 ACP Horizontal lt 7 - 10 3/20/2024 4/4/2024

6 Kaca Balustrid lt 6 - 8 3/20/2024 4/4/2024

Indalex
1 Marking done

2 Pasang Steel Support lt 26 - lt 30 3/20/2024 4/4/2024

3 Pasang outer lt 20 -22 3/20/2024 4/4/2024

4 pasang frame lt 20 -22 3/20/2024 4/4/2024


5 Timber Floor - Unit
6 Under layer + Timber floor Installaton L2 21-Dec-23 20-Dec-23

7 Pasang fix window lt 20 -22 3/20/2024 4/4/2024

8 Pasang door lt 20 -22 3/20/2024 4/4/2024

9 Backpan lt 8 - 10 3/20/2024 4/4/2024


A HEAD TOWER 3
Periode: 20 mar - 04 apr 2024
ACTUAL
REMARKS
START FINISH DUR

3/20/2024 4/4/2024 in progress lv 28

3/20/2024 4/4/2024 in progress lv 27

3/20/2024 4/4/2024 in progress lv 25 (zone 1)


in progress lv 17 (zone 2)

3/20/2024 4/4/2024 in progress lv 26 (zone 1)


in progress lv 18 (zone 2)

3/20/2024 4/4/2024 in progress lv 10 onprogress

3/20/2024 4/4/2024 in progress lv 9 on progress

3/20/2024 4/4/2024 in progress lv 10 on progress

3/20/2024 4/4/2024 in progress lv 9

3/20/2024 4/4/2024 in progress lv 7

3/20/2024 4/4/2024 lv 7 on progress

3/20/2024 4/4/2024 lv 7 on progress

3/20/2024 4/4/2024 lv 6 on progress

3/20/2024 4/4/2024 in progress lv 7


3/20/2024 4/4/2024 lv 28 onprogress

3/20/2024 4/4/2024 lv 20 onprogress

3/20/2024 4/4/2024 lv 20 onprogress

3/20/2024 4/4/2024 lv 20 onprogress

3/20/2024 4/4/2024 lv 20 onprogress

3/20/2024 4/4/2024 lv 11 onprogress


TWO WEEKS LOOK A HEAD TOWER 3
PLAN
Item Description Floor
START FINISH DUR
Xing Hai

1 Pasang ancor 21fl - 30fl 4/16/2024 4/30/2024

2 Corbel 21fl - 30fl 4/16/2024 4/30/2024

3 Vertical Subframe 21fl - 29fl 4/16/2024 4/30/2024

4 Horizontal 21fl - 30fl 4/16/2024 4/30/2024

Rectification Area

1 Corbel 10 - 13 fl 4/16/2024 4/30/2024

2 Vertical Subframe 10 - 13 fl 4/16/2024 4/30/2024

3 Horizontal 10 - 13 fl 4/16/2024 4/30/2024

Polareka

1 Trim CA lt 9 - 12 4/16/2024 4/30/2024

2 U Balustrid lt 6 - 8 4/16/2024 4/30/2024

3 Rangka Celing lt 6 - 8 4/16/2024 4/30/2024

4 ACP Vertical lt 7 - 10 4/16/2024 4/30/2024

5 ACP Horizontal lt 7 - 10 4/16/2024 4/30/2024

6 Kaca Balustrid lt 6 - 8 4/16/2024 4/30/2024

Indalex
1 Marking lt.30

2 Pasang Steel Support lt 26 - lt 33 4/16/2024 4/30/2024

3 Pasang outer lt 20 -23 4/16/2024 4/30/2024

4 pasang frame lt 20 -23 4/16/2024 4/30/2024


5 Timber Floor - Unit
6 Under layer + Timber floor Installaton L2 21-Dec-23 20-Dec-23

7 Pasang fix window lt 20 -23 4/16/2024 4/30/2024

8 Pasang door lt 20 -23 4/16/2024 4/30/2024

9 Backpan lt 10 - 15 4/16/2024 4/30/2024


A HEAD TOWER 3
Periode: 16 APR - 30 APR 2024
ACTUAL
REMARKS
START FINISH DUR

in progress lv 28

in progress lv 27

in progress lv 25 (zone 1)
in progress lv 17 (zone 2)

in progress lv 26 (zone 1)
in progress lv 18 (zone 2)

in progress lv 10 onprogress

in progress lv 9 on progress

in progress lv 10 on progress

in progress lv 9

in progress lv 7

lv 7 on progress

lv 7 on progress

lv 6 on progress

in progress lv 7
lv 28 onprogress

lv 20 onprogress

lv 20 onprogress

lv 20 onprogress

lv 20 onprogress

lv 11 onprogress
TWO WEEKS LOOK A HEAD TOWER 3
PLAN
Item Description Floor
START FINISH DUR
Xing Hai

1 Pasang ancor 17fl - 22fl 6/3/2024 19/05/2024

2 Corbel 17fl - 22fl 6/3/2024 19/05/2024

3 Vertical Subframe 17fl - 22fl 6/3/2024 19/05/2024

4 Horizontal 17fl - 22fl 6/3/2024 19/05/2024

Rectification Area

1 Corbel lt10 6/3/2024 19/05/2024

2 Vertical Subframe 10fl 6/3/2024 19/05/2024

3 Horizontal 10fl 6/3/2024 19/05/2024

Polareka

1 Trim CA lt 8 - 11 6/3/2024 19/05/2024

2 U Balustrid lt 5 - 8 6/3/2024 19/05/2024

3 Rangka Celing lt 6 - 8 6/3/2024 19/05/2024

4 ACP Vertical lt 6 - 10 6/3/2024 19/05/2024

5 ACP Horizontal lt 6 - 9 6/3/2024 19/05/2024

6 Kaca Balustrid lt 5 - 8 6/3/2024 19/05/2024

Indalex

1 Marking done
2 Pasang Steel Support lt 26 - lt 30 6/3/2024 19/05/2024

3 Pasang outer lt 16 -21 6/3/2024 19/05/2024

4 pasang frame lt 16 -21 6/3/2024 19/05/2024


5 Timber Floor - Unit
6 Under layer + Timber floor Installaton L2 21-Dec-23 20-Dec-23

7 Pasang fix window lt 16 -21 6/3/2024 19/05/2024

8 Pasang door lt 16 -21 6/3/2024 19/05/2024

9 Backpan lt 7 - 10 6/3/2024 19/05/2024


HEAD TOWER 3
Periode: 06 - 19 maret 2024
ACTUAL
REMARKS
START FINISH DUR

4/3/2024 19/05/2024 in progress lv 21

4/3/2024 19/05/2024 in progress lv 21

4/3/2024 19/05/2024 in progress lv 20

4/3/2024 19/05/2024 in progress lv 21

4/3/2024 19/05/2024 in progress lv 10 onprogress

4/3/2024 19/05/2024 in progress lv 9 on progress

4/3/2024 19/05/2024 in progress lv 9 on progress

4/3/2024 19/05/2024 in progress lv 9

4/3/2024 19/05/2024 in progress lv 7

4/3/2024 19/05/2024 lv 6 on progress

4/3/2024 19/05/2024 lv 6 on progress

4/3/2024 19/05/2024 lv 6 on progress

4/3/2024 19/05/2024 in progress lv 6


4/3/2024 19/05/2024 lv 25 onprogress

4/3/2024 19/05/2024 lv 19 onprogress

4/3/2024 19/05/2024 lv 18 onprogress

4/3/2024 19/05/2024 lv 18 onprogress

4/3/2024 19/05/2024 lv 18 onprogress

4/3/2024 19/05/2024 lv 8 onprogress