TW 1 Temp Works Register

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Temporary Works Register

CONTRACT TITLE: CONTRACT NUMBER: DATE OF FIRST ISSUE:

SENIOR SITE REPRESENTATIVE: Signed CIRCULATED TO: DATE OF REVISION:

REVIEWED BY: Signed REVISION NUMBER:

Temporary Works Information Key Planned/Actual Dates

Design Brief Design 3rd Party Approval Method Statement Permits Comments

Permit to Load/Un-load
Design Check Category

required on
*TW Class (M,N,S)

3rd Party Approval

required (Y or N)
required (Y or N)

Date TW
By: Req’d Actual By; Req’d Actual By; Req’d Actual By; Req’d Actu Review Actual To To

(0,1,2,3)
Design Brief

site
Structure Description of Work al by Load Strike
number
Name Date Date Name/ Date Date Name/ Date Date Name/Org Date Date Name Date Date Date
Date /Org. Org.
Org.

Cores C & D Slipform to the cores S 3 Y MS


C&D

MS001 CRUCIFORM CAT 3 CHECK S 3 Y 5/3/14 MS 25/2/14 Waterm 25/2/ Steelarts/ 28/3/
25/2/14 Swanton
an 14 MPB 14

MS002 GF Slab Mobile crane access N 2 N 6/3/14 MS 6/3/14 Swanton 6/3/14 MPB 3/3/14
to cores and
Cruciform

MS003 GF Slab + B1 + Backprop for 500T S 2 N 25/3/14 MS 17/3/14 Swanton 17/3/14 MPB 17/3/1
B2 Crane 4

MS004 Core walls Timber Batten to N 2 N 20/3/14 MS 18/3/14 Swanton 18/3/14 MPB 28/2/1
walls for slipform / 4
Slipform
INt

MS005 Cores Access deck for N 2 N 3/3/14 MS 18/2/14 Harsco 25/2/14 MPB 28/2/1
slipform Cores C & D 4

MS006 Columns GF - Steel column boxes N 2 N 10/3/14 MS 20/2/14 Formfab 22/2/14 MPB 17/3/1
Podium 4
GF - Podium

MS007 Core C Walls Wall Shutters to Core N 2 N 24/3/14 MS 7/3/14 Harsco 10/3/14 MPB 17/13/
C to Podium level 14

MS008 Podium slab Falsework & N 2 N 7/4/14 MS 10/3/14 See Harsco 24/3/14 On-going N/A N/A N/A MPB 28/3/1
formwork to beams Const 4
and slab Prog

MS009 Tower Crane Tower Crane sign S 3 Y 21/4/14 LH 4/4/14 4/4/14 Select 4/4/14 4/4/14 Swanton 07/4/1 Select Issued N/A N/A N/A
Bracketry 4 Previo
usly

MS010 Podium slab Falsework & N 2 N 21/4/14 LH 05/4/14 Swanton 14/4/14


formwork to beams

TW1 Issue 1 20/10/2023 JCPDI CD TW REGISTER Page 1 of 3


Temporary Works Register

and slab

MS011 Podium slab Design of timber N 2 N N 21/4/14 LH 09/4/14 9/4/14 Swanton 14/4/14 17/4/14 N/A
formwork to the
sides of the beams
(4”x2” timber &
Plywood)

MS012 Block D upper Aluxo Falsework to


floor slabs Block D upper floor N 2 N 9/4/14 LH 9/4/14 9/4/14 Swanton 16/4/14 28/4/14 N/A N/A N/A
slabs s

RC Slab Wall Design of Logik


Gridline A/ C2- Formwork for the N 2 N 14/4/14 LH 9/4/14 9/4/14 Harsco 14/4/14 14/4/14 N/A N/A N/A
MS013
C6 Block C Ground Floor
RC Wall

Podium slabs Design of Podium


either side of the slabs either side of N 2 N 28/4/14 LH 21/4/14 21/4/14 Harsco 28/4/14 On-going N/A N/A N/A
MS014
Block C&D the Block C&D

500T propping Swantons to check


design current 500T N 2 N 25/4/14 LH 21/4/14 Swanton 23/4/14 25/4/14 N/A N/A N/A
MS015
propping design SC- s
704-102

Swantons to check
construction of N 2 N 8/5/14 LH 2/5/14 6/5/14 Swanton 8/5/14 8/5/14 N/A N/A N/A
MS016 Tower Crane
tower crane hoarding s
Hoarding

Swantons to design
(if required) the N 2 N 12/5/14 LH 9/5/14 9/5/14 Swanton 12/5/14 12/5/14 N/A N/A N/A
MS017 Backpropping of
backpropping to the s
Ground Floor
Ground floor Slab
slab
during the pouring of
the podium slab

MS018 Block C upper Aluxo Falsework to


floor slabs Block C upper floor N 2 N 16/6/14 LH 23/5/14 23/5/14 Swanton 30/5/14 28/4/14 N/A N/A N/A MPB 16/6/1
slabs s 4

Design check for the


striking & N 2 N 2/6/14 LH 28/5/14 28/5/14 IDH 2/6/14 Outstand N/A N/A N/A MPB 16/6/1
MS019 Suspended slabs
backpropping ing 4
requirements for the
suspended slabs
Podium - Roof

Capping Slab to Design of Falsework


Core C1 to capping slabs to N 2 N 9/6/14 LH 28/5/14 28/5/14 Harsco 3/6/14 5/6/14 N/A N/A N/A MPB 28/3/1
MS020
Core C1 4

TW1 Issue 1 20/10/2023 JCPDI CD TW REGISTER Page 2 of 3


Temporary Works Register
MS021

Falsework design for N 2 N 23/6/14 LH 2/6/14 2/6/14 IDH 6/6/14 27/6/14 N/A N/A N/A MPB 16/6/1
the staircase landings 4
Staircase
using cuplok & H20
Landings
beams

Carryout design
check to see if N 2 N 9/6/14 LH 5/6/14 5/6/14 Swanton 9/6/14 13/6/14 N/A N/A N/A
MS022 Ground Floor
backpropping is s
slab in area of
required to the
Block E
Ground floor Slab to
support site traffic

MS023 Cantidecks N 2 N 23/6/14 LH 18/6/14 18/6/14 IDH 23/6/14 25/6/14 N/A N/A N/A

MS024 Stair Flights Lifting points for Outstand


precast stair ing
N 2 N 4/7/14 LH 1/7/14 1/7/14 IDH 4/7/14 N/A N/A N/A

MS025 Suspended slabs Aluxo Falsework to N 2 N 2/9/14 LH 29/7/14 29/7/14 IDH 6/8/14 2/9/14 N/A N/A N/A MPB 16/6/1
Block D Levels 9-11 4
Block D Levels 9-
11

MS026 Climbing S 3 Y 18/9/14 LH 20/8/14 20/8/14 IDH 18/9/14 N/A N/A N/A MPB 15/9/1
Screens 4

MS027 Core E Walls Wall Shutters to Core N 2 N 3/10/14 MS 19/9/14 19/9/14 Harsco 26/9/14 N/A N/A N/A MPB 26/9/1
E to Podium level 4

MS028 Podium Hoist Falsework for N 2 N 29/9/14 MS 19/9/14 19/9/14 Harsco 24/9/14 N/A N/A N/A MPB 26/9/1
Infill Block F Podium Hoist Infill 4
Block F

MS029 Podium Phase 1 Falsework for N 2 N 20/10/14 MS 19/9/14 19/9/14 Harsco 10/10/14 N/A N/A N/A MPB 26/9/1
Block E Podium Phase 1 4
Block E

 Temporary Works Classifications are M = Minor, N = Normal, S = Special. For further descriptions of the various classes refer to __________ of the Control of Temporary Works Procedure

TW1 Issue 1 20/10/2023 JCPDI CD TW REGISTER Page 3 of 3

You might also like