TW 1 Temp Works Register
TW 1 Temp Works Register
TW 1 Temp Works Register
Design Brief Design 3rd Party Approval Method Statement Permits Comments
Permit to Load/Un-load
Design Check Category
required on
*TW Class (M,N,S)
required (Y or N)
required (Y or N)
Date TW
By: Req’d Actual By; Req’d Actual By; Req’d Actual By; Req’d Actu Review Actual To To
(0,1,2,3)
Design Brief
site
Structure Description of Work al by Load Strike
number
Name Date Date Name/ Date Date Name/ Date Date Name/Org Date Date Name Date Date Date
Date /Org. Org.
Org.
MS001 CRUCIFORM CAT 3 CHECK S 3 Y 5/3/14 MS 25/2/14 Waterm 25/2/ Steelarts/ 28/3/
25/2/14 Swanton
an 14 MPB 14
MS002 GF Slab Mobile crane access N 2 N 6/3/14 MS 6/3/14 Swanton 6/3/14 MPB 3/3/14
to cores and
Cruciform
MS003 GF Slab + B1 + Backprop for 500T S 2 N 25/3/14 MS 17/3/14 Swanton 17/3/14 MPB 17/3/1
B2 Crane 4
MS004 Core walls Timber Batten to N 2 N 20/3/14 MS 18/3/14 Swanton 18/3/14 MPB 28/2/1
walls for slipform / 4
Slipform
INt
MS005 Cores Access deck for N 2 N 3/3/14 MS 18/2/14 Harsco 25/2/14 MPB 28/2/1
slipform Cores C & D 4
MS006 Columns GF - Steel column boxes N 2 N 10/3/14 MS 20/2/14 Formfab 22/2/14 MPB 17/3/1
Podium 4
GF - Podium
MS007 Core C Walls Wall Shutters to Core N 2 N 24/3/14 MS 7/3/14 Harsco 10/3/14 MPB 17/13/
C to Podium level 14
MS008 Podium slab Falsework & N 2 N 7/4/14 MS 10/3/14 See Harsco 24/3/14 On-going N/A N/A N/A MPB 28/3/1
formwork to beams Const 4
and slab Prog
MS009 Tower Crane Tower Crane sign S 3 Y 21/4/14 LH 4/4/14 4/4/14 Select 4/4/14 4/4/14 Swanton 07/4/1 Select Issued N/A N/A N/A
Bracketry 4 Previo
usly
and slab
MS011 Podium slab Design of timber N 2 N N 21/4/14 LH 09/4/14 9/4/14 Swanton 14/4/14 17/4/14 N/A
formwork to the
sides of the beams
(4”x2” timber &
Plywood)
Swantons to check
construction of N 2 N 8/5/14 LH 2/5/14 6/5/14 Swanton 8/5/14 8/5/14 N/A N/A N/A
MS016 Tower Crane
tower crane hoarding s
Hoarding
Swantons to design
(if required) the N 2 N 12/5/14 LH 9/5/14 9/5/14 Swanton 12/5/14 12/5/14 N/A N/A N/A
MS017 Backpropping of
backpropping to the s
Ground Floor
Ground floor Slab
slab
during the pouring of
the podium slab
Falsework design for N 2 N 23/6/14 LH 2/6/14 2/6/14 IDH 6/6/14 27/6/14 N/A N/A N/A MPB 16/6/1
the staircase landings 4
Staircase
using cuplok & H20
Landings
beams
Carryout design
check to see if N 2 N 9/6/14 LH 5/6/14 5/6/14 Swanton 9/6/14 13/6/14 N/A N/A N/A
MS022 Ground Floor
backpropping is s
slab in area of
required to the
Block E
Ground floor Slab to
support site traffic
MS023 Cantidecks N 2 N 23/6/14 LH 18/6/14 18/6/14 IDH 23/6/14 25/6/14 N/A N/A N/A
MS025 Suspended slabs Aluxo Falsework to N 2 N 2/9/14 LH 29/7/14 29/7/14 IDH 6/8/14 2/9/14 N/A N/A N/A MPB 16/6/1
Block D Levels 9-11 4
Block D Levels 9-
11
MS026 Climbing S 3 Y 18/9/14 LH 20/8/14 20/8/14 IDH 18/9/14 N/A N/A N/A MPB 15/9/1
Screens 4
MS027 Core E Walls Wall Shutters to Core N 2 N 3/10/14 MS 19/9/14 19/9/14 Harsco 26/9/14 N/A N/A N/A MPB 26/9/1
E to Podium level 4
MS028 Podium Hoist Falsework for N 2 N 29/9/14 MS 19/9/14 19/9/14 Harsco 24/9/14 N/A N/A N/A MPB 26/9/1
Infill Block F Podium Hoist Infill 4
Block F
MS029 Podium Phase 1 Falsework for N 2 N 20/10/14 MS 19/9/14 19/9/14 Harsco 10/10/14 N/A N/A N/A MPB 26/9/1
Block E Podium Phase 1 4
Block E
Temporary Works Classifications are M = Minor, N = Normal, S = Special. For further descriptions of the various classes refer to __________ of the Control of Temporary Works Procedure