Assignment 1
Submitted by : Ankita Parekh
Roll No. : 19AR10008
Given:
● One RMC Truck will be loaded at a time at the batching plant
● One Pump will operate with one RMC Truck at a time
● Equipment Availability:
○ Batching Plant: 1 ( per day capacity: 225cum)
○ RMC Truck: 5 (Maximum)
○ Concrete Pump: 5 (Maximum)
○ Surface Vibrator: as per requirement
RMC Truck
Loading time Travel time (in mins) Discharge time
(in mins) (in mins)
Batch to Site Site to Batch
20 20 10 30
Total Productivity
Length of Pavement Breadth of Pavement Thickness of Pavement
3000 40 0.5
Volume (cum) 60000
(Given)Per day Capacity of Plant (cum) 225
Batching plant
Capacity of batching plant 225
Capacity of 1 truck 10
Number of trips 23
Cost Calculation
Cost RMC Truck (in Rs.) Cost : Concrete Pump (in Rs.) Cost : Surface Vibrator (in Rs.)
As can be seen from the chart above, we need 4 trucks to complete the job. When truck C arrives on site, pump 1 would have already
discharged the cement of Truck A.
Hence, 2 pumps are sufficient.
RMC Truck
No. of truck No. of driver No. of helper
1 1 1
4 4 4
Concrete Pump
Time Difference between 2 trucks 40
Discharge time 30
1 Pump can serve 2 trucks
No. of Pump No. of operator No. of helper
1 1 1
2 2 2
Vibrator
5 Vibrators per Concrete Pump
No. of Pump No. of Vibrator No. of Labour
1 5 15
2 10 30
Construction and Project Management