Daily Report Utility 25 April 2024

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Utility Plant - Construction Daily Monitoring Report

Cut off date 24 April 2024


Last Cumm Remark
Activity Total Cummulative Progress Remaining Unit Cummulative (%) BL Start BL Finish Start Finish Status
Progress
Civil
2U03 - River Water Regulation Pool
Foundation 23-May-23 02-Oct-23 23-Mar-23
Excavation 26880 25200 25200 0 1680 m3 93,75% On Progress
Rebar Installation 80 58 58 0 22 ton 72,50% On Progress
Rebar Fabrication 80 55 55 0 25 ton 68,75% On Progress Pool 2 lean concrete
Forrmwork Installation 600 570 570 0 30 m2 95,00% On Progress Pool 1 Start Excavation and
Concrete Pouring 1435 705 705 0 730 m3 49,13% On Progress Geomembrane Installation
Geomembrane Paving 23650 17600 17600 0 6050 m2 74,42% On Progress
GeoTextile Paving 24000 16150 16150 0 7850 m2 67,29% On Progress
Aerated Block Masonry 300 140 140 0 160 m2 46,67% On Progress
2U03 - Water Purification Plant
Foundation 23-Mar-24
Rebar Making 4 3 3 0 1 ton 75,00% On Progress
Rebar Binding 4 4 4 0 0 ton 100,00% Finish
Template Installation 100 100 100 0 0 m2 100,00% Finish
Concrete Pouring 93 93 93 0 0 m3 100,00% Finish
Aerated Block Masonry 300 100 90 10 200 33,33% On Progress
Formwork Removal On Progress
2U04 - Booster Pump House
2U07 - Production Wastewater Treatment
Foundation 26-Jul-23 05-Oct-23 06-Mar-23
Rebar Fabrication 355 350 350 0 5 ton 98,59% On Progress
Rebar Installation 355 350 350 0 5 ton 98,59% On Progress
Excavation 11080 11000 11000 0 80 m3 99,28% On Progress
Formwork Installation 7500 7300 7300 0 200 m2 97,33% On Progress
Concrete Pouring 2630 2384,5 2384,5 0 245,5 m3 90,67% On Progress
2U08 - Domestic Sewage Treatment
Foundation 06-Apr-23 07-Aug-23 23-Apr-23
Rebar Fabrication 65 65 65 0 0 ton 100,00% Finish
Rebar Installation 65 65 65 0 0 ton 100,00% Finish 10 Ton Arrived at site
Formwork Installation 578 578 578 0 0 m2 100,00% Finish
Concrete Pouring 495 495 495 0 0 m3 100,00% Finish
2U06 - Rainwater Pool
Foundation 30-Apr-23 22-Aug-23 12-May-23
Rebar Fabrication 730 720 720 0 10 ton 98,63% On Progress
Rebar Installation 730 720 720 0 10 ton 98,63% On Progress
Formwork Installation 5914 5814 5814 0 100 m2 98,31% On Progress
Concrete Pouring 4251,5 4216,5 4216,5 0 35 m3 99,18% On Progress
Backfiling 1000 1000 1000 0 0 m3 100,00% Finish
2E01 - Water Intake
Foundation 14-Jun-23 19-Oct-23 07-Dec-23 29-Jan-24
Earth excavation 6000 4300 4300 0 1700 m3 71,67% On Progress
Rebar making 130 82 82 0 48 ton 63,08% On Progress
Rebar binding 130 80 80 0 50 ton 61,54% On Progress
Template Intallation 1800 1400 1400 0 400 m2 77,78% On Progress
Concrete pouring 1000 714 714 0 286 m3 71,40% On Progress
Intake Structure Spun pile core concrete 63 40 40 0 23 63,49% On Progress
2D05 - Chemical Water Treatment
Foundation
Rebar Installation 204000 203997,03 203997,03 0 2,97 kg 99,999% On Progress
Fromwork Installation 4705 4705 4705 0 0 m2 100,00% Finish
Steel Embeded / Anchor 248 248 248 0 0 pcs 100,00% Finish
Concrete 1625 1604 1604 0 21 m3 98,71% On Progress
Steel Erection of Chemical water system 141 141 141 0 0 ton 100,00% Finish
Spun pile core concrete 31 31 31 0 0 pcs 100,00% Finish
Spun pile top cute off 31 31 31 0 0 pcs 100,00% Finish
Uditch Rebar 40668,48 78,18 77,26 0,92 40590,3 kg 0,19% On Progress
Uditch Formwork 1773 424,3 419,3 5 1348,7 m2 23,93% On Progress
Uditch Concrete 248,51 10 10 0 238,51 m3 4,02% On Progress
Rebar Making 17 17 17 0 0 ton 100,00% Finish
Rebar Binding 17 16,5 16,5 0 0,5 ton 97,06% On Progress
Template Intallation 1200 1150 1150 0 50 m2 95,83% On Progress
Concrete pouring 310 72 72 0 238 m3 23,23% On Progress
Mechanical
2U03 - River Water Regulation Pool
Mechanical Work 26/3/2024
Mechanical Instal 15 11,5 11,5 0 3,5 ton 76,7% On Progress
Pipe Instal 45 44,2 44,2 0 0,8 m 98,22% On Progress
2U03 - Water Purification Plant
Mechanical Work 21-Dec-23 17-Mar-24 04-Sep-23
Water Purification Mechanical Instal 240 223 223 0 17 ton 92,9% On Progress
Water Purification Pipe Instal 50 47,5 47,5 0 2,5 m 95,00% 08-Aug-23 15-Sep-23 On Progress
2U04 - Booster Pump House
Mechanical Work 19-Feb-24
Non-standard tank installation 166,4 163 163 0 3,4 ton 97,96% On Progress
Mechanical Installation 22,6 22,6 22,6 0 0 ton 100,00% Finish
Pipe Installation 30 29,5 29 0,5 0,5 ton 98,33% On Progress
2E01 - Water Intake
Mechanical Work
Rebar making 3 3 3 0 0 ton 100,00% Finish
Rebar binding 3 3 3 0 0 ton 100,00% Finish
Template Installation for Pipe Network 350 350 350 0 0 m2 100,00% Finish
Piping Installation 2E01 (01) 10 0 0 0 10 ton 0,00% On Progress
Piping Installation 2E01 (02) 2000 1070 1060 10 930 ton 53,50% On Progress
Electrical pipes are embedded 785 52 52 0 733 6,62% On Progress
Equipment Installation 15 6 0 6 9 ton 40,00% On Progress
Concrete pouring 152 97 97 0 55 m3 63,82% On Progress
2U06 - Rainwater Pool
Mechanical Work
Pipe Installation 5,2 4,5 4,5 0 0,7 m 86,54% 08-Aug-23 15-Sep-23 On Progress
2U07 - Production Wastewater Treatment
Mechanical Work 15-Mar-24
Equipment Installation 50 23 23 0 27 ton 46,00% On Progress
Piping Installation 85 39 39 0 46 ton 45,88% On Progress
2U08 - Domestic Sewage Treatment
Mechanical Work 15-Mar-24
Equipment Installation 50 45 45 0 5 ton 90,00% On Progress
Piping Installation 10 9,2 9,2 0 0,8 ton 92,00% On Progress
Electrical
2U03 - Water Purification
2U04 - Booster Pump House
2E01 - Water Intake
2U06 - Rainwater Pool
2U07 - Production Wastewater Treatment
2U08 - Domestic Sewage Treatment
2D05 - Chemical Water Treatment

2E01 Water Intake 2U03 Water Purfication Plant


2U03 River Regulating Water Pool

2U06 Rain Water Collecting Pool 2U04 Booster Pump House 2U07 Waste Water Treatment

2D05 Chemical Water Treatment 2U08 Domestic Sewage Treatment