Request For Inspection

(RFI)
[IKAN] RDMP - Refinery Unit V
Project : Unit / Area : 068
Balikpapan Project

RFI No : RFI-R-ET15-IW-00770 Discipline : IW

Enviromate Technology
Subcontractor : Request Date : 2024-04-05
International

Inspection Detail

1. Inspection Date / Time 2024-04-06 / 09:00

2. Construction Activity Insulation - Equipment (Reformer Area)_U068

3. Inspection Activity Surface Preparation

ISO DWG NO .
- 26071-675-V1Z-MBHH-00099
4. Description - 26071-V1Z-013001H01-00087
- 26071-V1Z-013001H01-00088
- 26071-675-V1Z-MBHH-00204

26071-100-VSC-IN3-00003 (INSPECTION AND TEST PLAN FOR


5. DWG No or Reference
INSULATION WORK)

6. Attachment (Inspection Item List) ㅁ YES ㅁ No

Remark
Steam reformer part .
- Air Duct from APH II to SMR Baterry limit
- Combustion Air Duct Header
- Combustion Air Duct Manifolds
- Combustion Air Finger Ducts
- Air Duct from SMR battery limit Air duct header

Contractor
Subcontractor IPMT
Construction QA/QC

Name

Signature

Date
INSPECTION REPORT FOR
HOT SERVICE INSULATION
RDMP RU-V Balikpapan
Project : Report No :
(ISBL/OSBL) Project

Area / Unit : Date :

Location : Tag/Line No. :

Insulation Type : DWG No. :

Result
No Check List Remark
Accept Reject N/A

1 Material Verification

1.1 No damage and deformation, clean, dry and oil free

1.2 Storage condition


(Moisture-Proof and MFR’s Guidelines)

1.3 Type, Dimension, Thickness, Density

1.4 Approved by MAR (Material Approved Request) or TQ

2 Surface Preparation

2.1 Surface Cleanliness : Free from Oil, Dust, Rust and Dry

2.2 Removing All Temporary Supports

2.3 Completion of Pre-Task


(Pressure-test, Painting, Tracing, etc.)

2.4 Insulation Support / Collar (if required)

2.5 Enough space for required thickness to adjacent obstruction


Note :

Inspection Result : □ Accept □ Conditionally Accept □ Reject

Inspection by Subcontractor Contractor IPMT

Name

Signature

Date

Form No. : ITR-IN-001-1


INSPECTION REPORT FOR
COLD INSULATION
RDMP RU-V Balikpapan
Project : Report No :
(ISBL/OSBL) Project

Area / Unit : Date :

Location : Tag/Line No. :

Insulation Type : DWG No. :

Result
No Check List Remark
Accept Reject N/A

1 Material Verification

1.1 No damage and deformation, clean, dry and oil free

1.2 Storage condition


(moisture-proof, proper temperature / humidity)

1.3 Type, Dimension, Thickness, Density

1.4 Approved by MAR (Material Approved Request) or TQ

2 Surface Preparation

2.1 Surface Cleanliness : Free from Oil, Dust, Rust and Dry

2.2 Removing All Temporary Supports

2.3 Completion of Pre-Task (Pressure-test, Painting, Tracing, etc.)

2.4 Insulation Support / Collar (if required)

2.5 Enough space for required thickness to adjacent obstruction

Note :

Inspection Result : □ Accept □ Conditionally Accept □ Reject

Inspection by Subcontractor Contractor IPMT

Name

Signature

Date

Form No. : ITR-IN-002-1