Professional Documents
Culture Documents
Construction Projects DS12
Construction Projects DS12
Introduction
As per an objective definition, the delay in construction sector is defined as ‘time overrun
after the completion of a contract or beyond the date agreed upon by the parties for
delivery of the project’ (Kumar, 2006). A project’s success depends upon the most efficient
channelizing and utilizing of the resources available, and smart control of the sequential
activities to manage the deadlines; ensuring adherence to time duration, adequate use of
supplies and manpower. Even with the latest technology and project management
techniques, construction projects face delays and see the postponement of their completion
deadlines. This shows that time overrun is still is still critical and a significant problem. This
has become a global phenomenon and resides in both the developing and developed
countries. The problem of construction delays become a more crucial in countries where the
economic growth is significantly linked with the construction industry. Delays significantly
leads to poor cost performance of the projects; time extension incurs extended fixed
overheads, delay in prospectus earning from the project and extended timeline for credit
returns.
The paper reviews various studies and derives reasons for the delays in construction project,
they are of varying nature from country to country, while having numerous common factors
contributing to this cause as well. Studies generally focus their derivations on national basis
and considers large scale projects relative to the country’s economy and development. It is
noted that; financial problems, delay in payments, and rising inflation etc are the most
common factors contributing to the delays for developing countries, whereas changes in
specifications by clients, planning and calculation errors, delay in decisions on part of client
are the most common causes in developed countries (Assaf and Al-Hejji 2006, Pourrostam et al.
2011, Kumar 2016, Samarghandi et al. 2016, Tafazzoli and Shrestha 2017).Additionally, time and cost
overruns tend to be the most common delay factors seen in all countries irrespective of
development level (Sarıkaya 2010, Kikwasi 2012, Sunjka and Jacob 2013, Kuşakçı et al. 2017).
There are also delay factors that are shaped by localised conditions, owing to internal or external
factors contributing to that area. Here is a localised case of Turkey to shed light on rather few
outlying factors for the delay. September 2016 data shows that Thrace is the only region where
housing prices have appreciated by around 20% in Turkey (Sezgin and Aşarkaya 2017). Edirne is one
of the cities in that region. Rapid construction activities of the neighbouring cities have contributed
to the appreciation in Edrine, where investors and construction companies pumped money to
increase the construction activities. Figure 1a shows the comparison of number of building permits
for construction and the construction sector behaviour from 2007 to 2016. Consequently, the
number of building production in Edirne has spiked compared to the previous turnover in every
period in which the country's economy has shown positive improvement. However, it is observed
that the difference between the number of building permits and the number of occupancy permits is
increasing day by day (Figure 1(b)). The basic reason for this outcome is; the construction of the
buildings are not made in accordance with the relevant legislation, so the required changes take time
and thus the completion of the project is delayed (D. Aydin and E. Mihlayanlar,2018).
This study source was downloaded by 100000874839805 from CourseHero.com on 12-14-2023 02:55:43 GMT -06:00
https://www.coursehero.com/file/64824098/Construction-Projects-DS12docx/
Numerous inquiries have been done to overview the reasons for delay in development
wanders. Mansfield et al. (1994) jotted the reasons for delays and taken a toll attack in
development expands in Nigeria. The results concluded that the noteworthy factors are
financing issues and instalment for wrapped up works, destitute contact administration,
variations in location conditions, inadequacy of materials, and poor project planning.
Ogunlana and Promkuntong (1996) recognized reasons for delays in development expands in
Bangkok, Thailand and differentiated and diverse deferrals and fetched overpowers to
choose in the event that there are one of a kind issues that create delays. They sketched out
the reasons for delay within the development commerce as being in three issues .
Inherent insufficiencies or deficiencies in business foundation, majorly the supply of
assets.
Issues highlighted by the customers or advisors further adds to iterations.
Problems put up by the contractual worker ineptitudes.
Mezher and Tawil (1998) has directed a review on the reasons for extensions of time in the
construction industry of Lebanon from the perspective of owners, contractors and design
companies. It was concluded that owners had more concerns over the monetary issues,
contractors viewed authoritative connections just like the generally significant, and
consultants put the project management issues to be the most important factors for delays.
This study source was downloaded by 100000874839805 from CourseHero.com on 12-14-2023 02:55:43 GMT -06:00
https://www.coursehero.com/file/64824098/Construction-Projects-DS12docx/
Chan and Kumaraswamy (1998) reviewed the issues for construction delays in Hong Kong as
observed by customers, contractors and consultants, and inspected what may add to
lowered productivity. The review uncovered contrasts in perception of the relative
significance of elements including financing and instalments for finished works, poor
contract management, changes in site conditions, deficiency of materials, and inadequate
planning.
Al-Moumani (2000) overviewed the delaying factors on 130 public projects in Jordan, and
the outcomes showed that the basic driver of delays in construction of public projects
identify with designer, client changes, climate, site issues, delayed conveyances, and
budgetary matters.
Following is the general sequence that follows the end to end execution of a project.
Types of Delays
The small to large factors on instances could be categorised in varying types, to better assess
their impact and subsequent solutions to deter their effect on construction delays. So, it is
necessary to thoroughly understand the categories of delays, in order to effective approach
in mitigation of their effect and objectively devise solutions to avoid them.
Concurrent delays.
Excusable or non-excusable delays.
Critical or non-critical delays.
Compensable or non-compensable delays.
The delays can also fall into more than one category, so its imperative to accurately
characterize them to develop a better understanding of it. Like, excusable/non-excusable
could also be concurrent or non-concurrent. Furthermore, economic historian Robert E.
Wright proposes that construction delays are fundamentally caused by post contractual
This study source was downloaded by 100000874839805 from CourseHero.com on 12-14-2023 02:55:43 GMT -06:00
https://www.coursehero.com/file/64824098/Construction-Projects-DS12docx/
market power, inaccurate information sharing, bid gaming or changes over artistry. Unless
these are fully resolved, the delays are bound to occur having negative cost implications.
Concurrent Delays
An event where more than one factor contributes to the delay, and they occur simultaneously to
impact the delaying of the project. However, these delays may or may not entitle a contractor to
claim for a compensation. More importantly, the causes should overlap, rather than the delay
itself.
Compensable or non-compensable
A delay where there is no share of the contractor or his contribution into extending of time
are compensable delays, external or natural factors contribute to cause compensable delays,
where the contractor is deserving of time extensions or monetary compensations. If the
contractor is solely responsible for the occurrence in delay, they are clearly non-
compensable delays. However, either of them may fall into critical or non-critical segments
or may or may not be concurrent in nature.
This study source was downloaded by 100000874839805 from CourseHero.com on 12-14-2023 02:55:43 GMT -06:00
https://www.coursehero.com/file/64824098/Construction-Projects-DS12docx/
Causes of Delay
Consultant’s Duty
Consulting site staff being absent
Inadequate technical expertise on its behalf
Inadequate administrative expertise
Deficient supervision and direction of orders on site.
Inaccurate reporting
Contractors Duty
Inferior aptitude or work experience
Lacking in site work
Lower profitability of work
Lower financial efficiency
Deficient supplies and resources on site
Delays in on site decisions
Delaying of souring material
Poor budget management
Poor on site management
Owner’s Liabilities
Working information being absent
Delaying in decision making
Delayed funding and payments.
Poor coordination with onsite team.
Frequent changes in design or other determinants of the work.
External Factors
This study source was downloaded by 100000874839805 from CourseHero.com on 12-14-2023 02:55:43 GMT -06:00
https://www.coursehero.com/file/64824098/Construction-Projects-DS12docx/
Material unavailable
Absence of necessary equipment
Site conditions being inappropriate (soil, area etc)
Inadequate financial conditions
Changes in regulations
Unprecedented delays in transportation
Conclusion
This study source was downloaded by 100000874839805 from CourseHero.com on 12-14-2023 02:55:43 GMT -06:00
https://www.coursehero.com/file/64824098/Construction-Projects-DS12docx/
There could be numerous factors that are generalised in delaying of construction projects,
that overlap or coincide into making extensions in timelines, cost overruns and financial
inefficiencies. Then there is a pool of factors that is localised to economies, societies or small
areas where the project is being conducted. It could be concluded, that to enhance the
project efficiency and reduce the time, the associated people and researchers take an
accurate account of the generalised factors that could be anticipated, and what measures or
resources they may arrange for in order to deter their impact. If there may be cost overruns
due to criticalities in designs, they may arrange for extra finances to cater the issues, over
they may procure extra material to make the supplies sufficient.
Further, they may take an account of probable localised factors that could contribute to the
delay, those are relevant to the community or a nation they’re operating in; a political unrest
owing to an upcoming election, a change in season that may bring extensive rainfall, new
budgetary announcements expected etc. This would help them better plan for the
unprecedented events that would delay a project. Good statistical or a quantitative
approach can assist in minimizing the delays or its effects. However, there is no absolute
solution to this matter in hand and no accurate description of the reasons that may come
up.
References
Sweis, G., Sweis, R., Hammad, A.A. and Shboul, A., 2008. Delays in construction
projects: The case of Jordan. International Journal of Project Management, 26(6), pp.665-
674.
Abd El-Razek, M.E., Bassioni, H.A. and Mobarak, A.M., 2008. Causes of delay in
building construction projects in Egypt. Journal of construction engineering and
management, 134(11), pp.831-841.
Alaghbari, W.E., Kadir, M.R.A. and Salim, A., 2007. The significant factors causing delay
of building construction projects in Malaysia. Engineering, Construction and
Architectural Management.
Alaghbari, W.E., Kadir, M.R.A. and Salim, A., 2007. The significant factors causing delay
of building construction projects in Malaysia. Engineering, Construction and
Architectural Management.
Haseeb, M., Bibi, A. and Rabbani, W., 2011. Problems of projects and effects of delays in
the construction industry of Pakistan. Australian journal of business and management
research, 1(5), pp.41-50
D. Aydin and E.Mihlayanlar, 2018. Causes and Effects of Construction Projects
Delays: A Local Case.
This study source was downloaded by 100000874839805 from CourseHero.com on 12-14-2023 02:55:43 GMT -06:00
https://www.coursehero.com/file/64824098/Construction-Projects-DS12docx/
This study source was downloaded by 100000874839805 from CourseHero.com on 12-14-2023 02:55:43 GMT -06:00
https://www.coursehero.com/file/64824098/Construction-Projects-DS12docx/
Powered by TCPDF (www.tcpdf.org)