CIVIL WORKS FOR BOUNDARY WALL AT KPGF CCI

Daily Progress Report


REPORTED BY AREAA BANU MUKHTAR CONSTRUCTION -LLP
REPORT NO 73
DATE 18-Dec-2023
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Skilled Labour Steel Fixer

Skilled Labour Carpenter


Admin and Account
Staff &
Project Manager

Security Guard
Workers
HSE engineer
Site in Charge

survey helper
Store keeper

SubEngineer

Supervisor
Electician
Surveyor

Labour

Mason

Driver

Total
Strength 0 1 1 1 1 1 0 1 0 3 4 1 0 1 0 1 16
Today WEATHER oC

Drain Concrete completed till end. Morning 16


Afternoon 26

EQUIPMENT Required Current


No Equipment
1 Water Bozzer 1 1
2 Pick up(double cabine) 1 1
3 Hilti drill machine 1 1
4 Grinder 9" 3 3
5 pally cutter 2 2
6 vibrator petrol 2 2
7 vibrator electrical 2 2
8 Level Machine 2 2
9 Generator 6KVA 1 1
10 Compactor 2 2
11 LED Lights 6 6
12 Store Container 40ft 1 1
13 Generator 3KVA 1 1
14
15
16
Tomorrow
No Material Unit In Stock
1 Timbers(4"x4"x10') nos 300.00
2 timbers(4"x4"x5') nos 100.00
3 timbers(3"x3"x3') no 200.00
4 Scaffolding pipes 20ft nos 60.00
5 Scaffolding pipes 10ft nos 50.00
6 Scaffolding rigid joint nos 100.00
7 MS Plates(1200mmx750mm) nos 148.00
8 Scaffolding pipes(6') nos 50.00
9 carogated sheets 10'x3.5' nos 10.00
10 Binding wire kgs 20.00
11 Tie Rods 16mmx5ft full set nos 200.00
12 Ply wood nos 25.00
TOTAL PROGRESS COMPLETE REMAINING

1 New wall Block work 100% 0%


2 Column new wall 100% 0%
3 Drain Excavation 100% 0%
4 Drain Concrete 100% 0%
5
6
7
8
NOTES/REMARKS

Contractor Client
CIVIL WORKS FOR BOUNDARY WALL AT KPGF CCI
DAILY PROGRESS PICTURES
Date: 12/18/2023

5. 6.