Professional Documents
Culture Documents
MS-HVAC-EMBEDDED DUCT Final Rev 1
MS-HVAC-EMBEDDED DUCT Final Rev 1
INSTALLATION OF EMBEDDED
DUCT & FITTINGS
INSTALLATION OF EMBEDED
DUCT & Fittings
PROTON THERAPY CENTER
Contents
1.Scope of work
2.Purpose
3.Abbreviations
4.References
5.Responsibilities
6.Hazard Identification & Risk Assessment
7.Procedures
8.Attachments
1.Scope of work
This work for execution of embedded duct at Proton Therapy Center including the following
activities:
1. Procurement and storage of approved material.
2. Installation & Testing.
2.Purpose
This method statement defines the responsibilities, and describes the activities and procedures to be
implemented at site in accordance with relevant project specifications, approved details, of HVAC
embedded duct work.
3.Abbreviations
4.References
5.Responsibilities
5.1 The Mechanical Site Engineer (MSE) shall be responsible for the implementation of this Method
Statement.
A) Ensure availability of required material that compiled with approved submittal.
MEP QA/QC Dept. AB MS-Embedded Ducts & Fittings
MEP Subcontractor:
5.2 The LLJV Surveyor shall be responsible for providing the correct reference, elevation, invert level,
location and position at site if required.
5.2.1 The Mechanical Foreman shall be responsible for the following:
5.2.1.1 Guide the Workmen to execute the work in a safe manner.
5.2.1.2 Check the material is approved.
5.2.1.3 Installation works are undertaken in accordance with recognized procedures.
5.3 Mechanical Quality Control Inspector (MQCI) shall be responsible for the following:
5.3.1 Continuously monitoring site execution work and material to be ensure compliance with
approved Project Specifications.
5.3.2 Timely inspections with Site Engineer/ staff. Ensuring the works are compliant & complte
prior to issuing for inspection to LLJV & DAR.
The safety measures for this work, especially in the proper use of tools; equipment has and shall be the
responsibility of the Mechanical Foreman. The MSE and Safety Engineer shall oversee the proper
implementation at site as per approved Project Specifications.
All safety risk shall be identified by the MSE prior to work commencing & the relevant tool box talk
initiated , if needed.
7.Procedures
b) Joints / Seams:
Beaded sleeve flange joint shall be use or as per the approved sample for
round duct.
All ductwork Seams and Joints shall be sealed airtight using sheet metal
duct sealant or as per approved sample.
All duct crossing the concrete and expansion joint shall be provided with
a duct expansion joint or as applicable.
c) Insulation:
Embedded duct shall be insulated with a fiberglass thermal
insulation .For reference see Table 1 Proton Therapy Embedded Ducts as
attached.
Vapor barrier coating or as per approved materials. See Table 1 as
attached.
d) Leakage TEST:
Leakage test shall be applied according to SMACNA or any approved
procedure.
e) Attenuator & Vibration:
Attenuators and vibration Isolator shall be apply according to noise
criteria requirement.
7.2.2 TRENCH OR WALL CLOSING
a) General:
Pouring of concrete shall only be done upon completion, inspection and
acceptance of the work by DAR.
All embedded ducts should PASS the required test before closing the
trench or walls.
MEP QA/QC Dept. AB MS-Embedded Ducts & Fittings
MEP Subcontractor:
However, copies of the approved drawings, detailed drawing, material submittal and brochures for
proper implementation of this work.