Professional Documents
Culture Documents
MS-HVAC-EMBEDDED PIPES and FITTINGS Final Rev.1
MS-HVAC-EMBEDDED PIPES and FITTINGS Final Rev.1
MS-HVAC-EMBEDDED PIPES and FITTINGS Final Rev.1
INSTALLATION OF EMBEDDED
PIPES & FITTINGS
INSTALLATION OF EMBEDED
PIPES & FITTINGS
Contents
1.Scope of work
2.Purpose
3.Abbreviations
4.References
5.Responsibilities
6.Hazard Identification & Risk Assessment
7.Procedures
8.Attachments
1.Scope of work
This work for execution of embedded Piping at Proton Therapy Center including the following
activities:
1. Procurement and storage of approved material.
2. Installation & Testing.
2.Purpose
This method statement defines the responsibilities, and describes the activities and procedures to be
implemented at site in accordance with relevant project specifications, approved details, materials, of
embedded piping work.
3.Abbreviations
4.References
5.Responsibilities
5.1 The Mechanical Site Engineer (MSE) shall be responsible for the implementation of this Method
Statement.
A) Ensure availability of required material that compiled with approved submittal.
5.2 The LLJV Surveyor shall be responsible for providing the correct reference, elevation, invert level,
location and position at site if required.
5.2.1 The Mechanical Foreman shall be responsible for the following:
5.2.1.1 Guide the Workmen to execute the work in a safe manner.
5.2.1.2 Check the material that is approved.
5.2.1.3 Installation works are undertaken in accordance with recognized procedure.
5.3 Mechanical Quality Control Inspector (MQCI) shall be responsible for the following:
5.3.1 Continuously monitoring site execution work and material to be ensure compliance with
approved Project Specifications.
5.3.2 Timely inspections with Site Engineer & staff. Ensuring the works are compliant & complete
prior to issuing for inspection to LLJV & DAR
The safety measures for this work, especially in the proper use of tools, equipment’s and materials
shall be the responsibility of the Mechanical Foreman. The MSE and Safety Engineer shall oversee the
proper implementation at site as per approved Project Specifications.
All safety risk shall be identified by MSE prior to work commencing & the relevant toolbox talk
initiated, if needed.
7.Procedures
End caps or blind flanges at the end openings must be installed directly
after cleaning to avoid dirt inlet during and after mounting.
After a partial completion of the piping or system, checking shall be
done according to the system location, invert level, type sizes of material
installed according to the latest approved shop drawing and other
recognized reference document.
b) Joints / Connection:
Joints on all permanently concealed pipes shall be welded. At
dismantling points or where the pipe work is connected to an appliance,
flanges shall be used or any approved substitute.
The number of welded connections must be kept minimum to avoid
stresses in the pipelines.
Minimum two long radius elbows shall be used on the embedded water
pipes to provide cooling water in all electrical rooms, the cyclotron pit
and the beam line area. Reference BID 5.15.2 page 35 of 72.
c) Insulation:
Embedded piping shall be insulated with a fiberglass board with a sheet
metal cladding / a vapor barrier or as per approved materials. As shown
in Table 1. Proton Therapy Center Embedded pipes.
All joints or connection shall be open until the leakage test will be done.
d) Leakage TEST / CLEANING:
All pipes shall be clean and leak tested.
Leakage test pressure shall not exceed the material pressure rating or 1.5
times the working pressure rating.
e) Vibration Damping:
Vibration damping shall be installed according to the system
requirements or as per the approved materials. See Table 1. Proton
Therapy Center Embedded pipes as attached.
MEP QA/QC Dept. AB MS-Embedded Pipes & Fittings
MEP Subcontractor:
However, copies of the approved drawings, detailed Section drawing, material submittal and
brochures for proper implementation of this work.
25 mm Elastomeric,
closed-cell rubber 25 mm Class O,
4 insulation, 60 kg/m3, Denso tape wrap. Denso tape wrap Armaflex (Armacell)
for vibration or equal.
damping.
5 GI cladding (.6 mm GI cladding (.6 mm
-- --
thickness) thickness)
6 Denso tape wrap
Denso tape wrap -- --