Plumbing Water Supply Multimedia Filter System Testing and Commissioning Checklist

Sl.No Task Description

1 Pre-Commissioning

Visually inspect all piping, valves, instrumentation, and


1.1 System Inspection
equipment for damage, leaks, or improper installation.
Verify electrical connections are correct and secure. Ensure
1.2 Electrical Inspection
proper grounding.
Confirm the water source meets system design requirements
1.3 Water Source Verification
(pressure, flow rate, water quality).
Verify the type and quantity of filtration media loaded in each
1.4 Filtration Media Loading
vessel corresponds to the design specifications.
Ensure the backwash line is free of obstructions and sized
1.5 Backwash Line Inspection
appropriately for flow rate.
Verify the drain line is properly vented and sized to handle
1.6 Drain Line Inspection
backwash discharge.
Calibrate all pressure gauges, flow meters, and other
1.7 Instrument Calibration
instruments according to manufacturer's recommendations.

1.8 Pre-Operational Flushing Flush the entire system to remove any debris or contaminants.

2 Commissioning

Start the filter system and gradually increase flow rate to


2.1 System Startup
design capacity.
Conduct performance tests to verify flow rate, pressure, and
2.2 Performance Testing
water quality meet design criteria.
Perform a backwash cycle to ensure proper media cleaning
2.3 Backwash Testing
and effluent disposal.
Verify the control system operates valves, pumps, and other
2.4 Control System Verification
equipment according to setpoints.
Review all test results and ensure the system meets
2.5 System Acceptance
performance specifications.
Compile all commissioning records, test results, and
2.6 Documentation
calibration certificates.
d Commissioning Checklist

Yes/ No Remarks