Sobha Limited

CHECKLIST FOR ON-SITE INSPECTION


ACTIVITY: STONE MASONRY
Project: Date:
Location:

NOTE:- Please  appropriate box or enter readings as per requirements

SN DESCRIPTION YES NO NA REMARKS/CLARIFICATIONS

1 Name, date and number of the drawing


PRE CONSTRUCTION CHECKS
Check the availability of the latest relevant drawings and
2 [ ] [ ] [ ]
specifications.
Check the availability of the required number of stones for the
3 [ ] [ ] [ ]
day's work.
4 Surface preparation has been done before the start of work. [ ] [ ] [ ]
Are the stones for masonry work clean and according to the
5 [ ] [ ] [ ]
required dimensions ?
6 Is the deleterious content in the sand within 5% ? [ ] [ ] [ ]
7 Check if the water used for mortar mixing is potable ? [ ] [ ] [ ]
CHECKS DURING CONSTRUCTION

8 Check if mortar mixing is being done on MS sheets. [ ] [ ] [ ]


Is mortar mix proportion maintained as per specifications
9 [ ] [ ] [ ]
using measurement boxes ?
10 Has the mortar been consumed within 30 minutes of mixing ? [ ] [ ] [ ]
11 Are the vertical keys & horizontal bonds staggered ? [ ] [ ] [ ]

12 Are the horizontal bond stones at 1m intervals in each course. [ ] [ ] [ ]

13 Are the vertical keys kept at 1m intervals in each course ? [ ] [ ] [ ]


Is the maximum height of construction done in a day's work 3
14 [ ] [ ] [ ]
courses or 660mm whichever is less ?
Are the dates painted on the top most course of masonry at
15 [ ] [ ] [ ]
the end of day's work ?
POST CONSTRUCTION CHECKS

16 Are the erected walls perfectly vertical ? [ ] [ ] [ ]


Are the dates on the top most course of masonry at the end
17 [ ] [ ] [ ]
of day's work ?
18 Is sufficient spray curing being done to the mortar joints ? [ ] [ ] [ ]
19 Are the mortar joints of uniform color ? [ ] [ ] [ ]
20 Is the masonry work free from cracks ? [ ] [ ] [ ]

Checked by: Approved by:

Name : Name:
Sign: Sign:
Date: Date:

1 of 1 10/02/2015
Sobha Limited

CHECKLIST FOR ON-SITE INSPECTION


ACTIVITY: BLOCK MASONRY
Project: Date:
Location:

NOTE:- Please  appropriate box or enter readings as per requirements

SN DESCRIPTION YES NO NA REMARKS/CLARIFICATIONS

1 Name, date and number of the drawing


PRE CONSTRUCTION CHECKS
Check the availability of the latest relevant drawings and
2 [ ] [ ] [ ]
specifications.
Check the availability of the required number of concrete
3 [ ] [ ] [ ]
blocks for the day's work.
Check if the surface preparation has been done before the start
4 [ ] [ ] [ ]
of work.
5 Is the deleterious content in the sand within 5% ? [ ] [ ] [ ]
Are all the electrical conduits raised to appropriate height
6 [ ] [ ] [ ]
before block work starts ?
Hacking and splatter dash works have been done on all the
7 concrete surfaces where the block work will be coming into [ ] [ ] [ ]
contact.
8 Check if the water used for mortar mixing is potable ? [ ] [ ] [ ]
Ensure that the concrete blocks are sprinkled with water just
9 [ ] [ ] [ ]
before using them for masonry.
CHECKS DURING CONSTRUCTION
Check if the marking course has been cured for a minimum of
10 [ ] [ ] [ ]
one day.
11 Check if mortar mixing is being done on MS sheets. [ ] [ ] [ ]
Is the mortar mix proportion maintained as per specifications
12 [ ] [ ] [ ]
using measurement boxes ?
Ensure that the mortar is being consumed within 30 minutes of
13 [ ] [ ] [ ]
its mixing.
14 Is the course under the beam bottom built with full blocks ? [ ] [ ] [ ]
Is the gap between the beam bottom and the top most course
15 [ ] [ ] [ ]
thoroughly packed with mortar ?
A concrete band (1:2:4 concrete) of thickness 100mm, laid
16 with 6 to 8mm steel rods embedded inside, after every 4 [ ] [ ] [ ]
courses, for walls of width 100mm.
Are the sizes of the mortar joints uniform and not more than
17 [ ] [ ] [ ]
10mm.
Ensure that the height of construction to be done in a day's
18 [ ] [ ] [ ]
work is not more than 5 courses.
POST CONSTRUCTION CHECKS

19 Are the diagonals of block masonry marking course equal ? [ ] [ ] [ ]


20 Are corners of the masonry walls at right angles ? [ ] [ ] [ ]
21 Are the erected masonry walls plumb and in level ? [ ] [ ] [ ]
Are the dimensions of all openings, like windows, doors etc. as
22 [ ] [ ] [ ]
per requirement ?
23 Are the vertical joints of the block masonry staggered ? [ ] [ ] [ ]
24 Has the mortar joints curing been done for 7 days ? [ ] [ ] [ ]
25 Is there any color variations in the mortar joints ? [ ] [ ] [ ]
26 Is the masonry work free from cracks ? [ ] [ ] [ ]
Has the date of construction been painted on the top most
27 [ ] [ ] [ ]
course of the masonry at the end of day's work ?

Checked by: Approved by:

Name : Name:
Sign: Sign:
Date: Date:

1 of 1 10/02/2015
Sobha Limited

CHECKLIST FOR ON-SITE INSPECTION


ACTIVITY: BRICK MASONRY
Project: Date:
Location:

NOTE:- Please  appropriate box or enter readings as per requirements

SN DESCRIPTION YES NO NA REMARKS/CLARIFICATIONS

1 Name, date and number of the drawing


PRE CONSTRUCTION CHECKS
Check the availability of the latest relevant drawings and
2 [ ] [ ] [ ]
specifications.
Check the availability of the required number of bricks for the
3 [ ] [ ] [ ]
day's work.
check if the surface preparation has been done before the
4 [ ] [ ] [ ]
start of work.
5 Is the deleterious content in the sand within 5% ? [ ] [ ] [ ]
Hacking and splatter dash works have been done on all the
6 concrete surfaces where the blockwork will be coming into [ ] [ ] [ ]
contact.
7 Check if the water used for mortar mixing is potable ? [ ] [ ] [ ]
Ensure that the bricks are immersed in water for 24hours
8 [ ] [ ] [ ]
before using them for masonry.
CHECKS DURING CONSTRUCTION
Check if the marking course has been cured for a minimum of
9 [ ] [ ] [ ]
one day.
10 Check if mortar mixing is being done on MS sheets. [ ] [ ] [ ]
Is the mortar mix proportion maintained as per specifications
11 [ ] [ ] [ ]
using measurement boxes ?
Ensure that the mortar is being consumed within 30 minutes
12 [ ] [ ] [ ]
of its mixing.
A concrete band (1:2:4 concrete) of thickness 100mm, laid
13 with 6 to 8mm steel rods embedded inside, after every 4 [ ] [ ] [ ]
courses, for walls of width 100mm.
Are the sizes of the mortar joints uniform and not more than
14 [ ] [ ] [ ]
10mm.
Ensure that the height of construction to be done in a day's
15 [ ] [ ] [ ]
work is not more than 5 courses.
POST CONSTRUCTION CHECKS

16 Are the diagonals of block masonry marking course equal ? [ ] [ ] [ ]


17 Are corners of the masonry walls at right angles ? [ ] [ ] [ ]
18 Are the erected masonry walls perfectly vertical ? [ ] [ ] [ ]
Are the dimensions of all openings like windows, doors etc. as
19 [ ] [ ] [ ]
per requirement ?
20 Are the vertical joints of the brick masonry staggered ? [ ] [ ] [ ]
21 Has the mortar joints curing been done for 7 days ? [ ] [ ] [ ]
22 Is there any color variations in the mortar joints ? [ ] [ ] [ ]
23 Is the masonry work free from cracks ? [ ] [ ] [ ]
Has the date of construction been painted on the top most
24 [ ] [ ] [ ]
course of the masonry at the end of day's work ?

Checked by: Approved by:

Name : Name:
Sign: Sign:
Date: Date: