Download as pdf or txt
Download as pdf or txt
You are on page 1of 15

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/239386643

Behavior, Analysis, and Design of an Instrumented Link Slab Bridge

Article in Journal of Bridge Engineering · May 2005


DOI: 10.1061/(ASCE)1084-0702(2005)10:3(331)

CITATIONS READS
27 4,816

2 authors, including:

Mervyn Kowalsky
North Carolina State University
143 PUBLICATIONS 6,680 CITATIONS

SEE PROFILE

All content following this page was uploaded by Mervyn Kowalsky on 20 April 2015.

The user has requested enhancement of the downloaded file.


Behavior, Analysis, and Design of an Instrumented Link
Slab Bridge
Kenneth M. Wing, S.M.ASCE,1 and Mervyn J. Kowalsky, A.M.ASCE2

Abstract: Presented in this paper are the results of a research project on the monitoring and assessment of the first link slab jointless
bridge in the state of North Carolina. The structure was instrumented with a remote data acquisition system and monitored for over a year.
In addition, a controlled load test was conducted in an effort to determine the demand on the link slab under known loads. A procedure
for the limit-states design of a link slab system is also presented. Results indicate that while the crack size in the link slab exceeded the
design level, the link slab fulfilled its function. Furthermore, the rotational demand from the large controlled loads as well as the traffic
loads was similar in magnitude to the thermal induced rotations due to the difference in temperature between the top and bottom of the
bridge.
DOI: 10.1061/共ASCE兲1084-0702共2005兲10:3共331兲
CE Database subject headings: Slabs; Bridges; Joints; Monitoring; North Carolina; Rehabilitation.

Introduction Research Objective, Motivation and Methods


The objective of the research described in this paper is to assess
The North Carolina Department of Transportation 共NCDOT兲 is
the performance of the first jointless link slab bridge in North
currently involved in a bridge rehabilitation and replacement pro-
Carolina through the use of remote instrumentation and a variety
gram where each of the state’s bridges is assessed to determine its
of testing and analysis methods. The motivation for the research
rehabilitation needs. One of the bridges identified for rehabilita-
stems from the desire to determine if the bridge design assump-
tion is located in Waynesville, N.C. The structure is on US High-
tions were valid, and if necessary, to propose changes to the de-
way 23-74 bypass, a major thoroughfare to Great Smokey Moun- sign concept. The most important assumption that requires veri-
tains National Park, and spans over Plott Creek and State Road fication was the assumption that link slab bridge girders can be
1173, in Haywood County, N.C. There are two bridges 共referred assumed to be simply supported for dead and live load.
to as the Plott Creek bridge in this paper兲, one for the east bound The primary methods used to investigate the performance of
lanes, and one for the west bound lanes. Each of the bridges the bridge consist of a full-scale live load test and long-term
originally carried two lanes of traffic. As part of the rehabilitation monitoring under seasonal and service level loading. This is aided
project, an additional lane was added to each bridge, which re- by a remote solar-powered data acquisition system that allows
sulted in additional columns and a complete redesign of the steel collection of data at specified intervals. In addition to the experi-
girder and concrete deck superstructure. mental studies, an analytical model of the bridge was developed
Prior to the design of the new superstructure, research by in an effort to predict the performance of the bridge link slab
Caner and Zia 共1998兲 led to the development of a design concept under specified loads.
for jointless bridges where the locations for expansion joints are
replaced with continuous link slabs, with the objective being to Review of Link Slab Design Concept
reduce the number of expansion joints. By reducing the number
of expansion joints, the bridge maintenance costs decrease. The
Research by Caner and Zia „1998…
west bound Plott Creek bridge on US Highway 23-74 was se-
lected as a demonstration for the jointless bridge deck concept by In jointless bridge decks, the traditional expansion joints are re-
the NCDOT. As a result, a unique opportunity to instrument and placed with “Link Slabs” which are the portion of the deck that
test the link slab design concept on a full-scale bridge was pre-
sented.

1
Graduate Research Assistant, Dept. of Civil Engineering, North
Carolina State Univ., Raleigh, NC 27695.
2
Assistant Professor, Dept. of Civil Engineering, North Carolina State
Univ., Raleigh, NC 27695.
Note. Discussion open until October 1, 2005. Separate discussions
must be submitted for individual papers. To extend the closing date by
one month, a written request must be filed with the ASCE Managing
Editor. The manuscript for this paper was submitted for review and pos-
sible publication on August 11, 2003; approved on May 3, 2004. This
paper is part of the Journal of Bridge Engineering, Vol. 10, No. 3, May
1, 2005. ©ASCE, ISSN 1084-0702/2005/3-331–344/$25.00. Fig. 1. Link slab design concept

JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005 / 331


Fig. 2. Plott Creek bridge in Haywood County, N.C.

connects two adjacent simple-span girders 共El-Safty 1994兲. Tra- penetrate into the slab. However, this situation is preferable to a
ditional bridge deck joints pose many problems with regards to traditional expansion joint as less water penetrates to the bearing
bridge maintenance. For example, water penetration through the below the girder.
joint damages the girder end bearings and supporting structures. To the knowledge of the writers, the only formal design ap-
In addition, debris accumulation within the expansion joint pre- proach for link slab bridges was proposed by Caner and Zia
vents the expansion of the deck and damages the joint.
共1998兲 as discussed below. The reader may refer to Figs. 1 and 2
One alternative to expansion joints, which are expensive to
for graphical representations of the link slab design concept while
install and maintain, are link slabs. Link slabs reduce both the
installation and maintenance costs associated with traditional reading the description below.
joints. It should also be noted that under normal service loads fine 1. Design each span of the bridge as if it was simply supported.
cracks might develop in the link slab and still allow water to Do not account for the effects of the link slab since the

Fig. 3. Bridge layout

332 / JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005


Fig. 4. Section of link slab

stiffness of the link slab is much smaller than the stiffness of 3. Determine the maximum end rotations of the simply sup-
the composite girders. ported girders when subjected to service loads. Impose those
2. To further reduce the stiffness of the link slab, provide a rotations on the link slab and determine the maximum mo-
debonding length of 5% of the girder spans. The reduction in ment in the link slab using gross section properties 共which is
stiffness of the link slab minimizes the stresses that will de- conservative since cracks will occur in the link slab兲.
velop by distributing the curvature over a larger area. Studies 4. Design the link slab reinforcement based on the calculated
show that debonding up to 5% does not affect the force de- moment, using a conservative working stress, such as 40% of
formation behavior of the structure 共El-Safty 1994兲. the yield strength of the reinforcing bar.

Fig. 5. Bridge instrumentation layout

JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005 / 333


Fig. 6. Thermocouple locations

5. Limit the crack width using the crack control criteria of the
AASHTO specifications. Fig. 8. Strain gauge layout in Span A
This proposed method was based on the results of analytical
studies and a test program conducted by Caner and Zia 共1998兲.
Their test program consisted of two large scale test specimens
both of composite construction. One test specimen was a continu- curve with a slight superelevation. The original structure had
ous reinforced concrete deck slab cast on two simple-span steel three interior expansion joints. After the rehabilitation, only the
beams. The other test specimen was a similar deck cast on precast centermost expansion joint remained. The other two interior ex-
reinforced concrete beams. The test procedure for both types of pansion joints were replaced with link slabs, with one of them
specimens was similar. Each specimen was tested using four com- being instrumented to monitor the performance of the link slab.
mon support configurations to determine if different support con- Fig. 4 illustrates the position of expansion joints and link slabs in
ditions would produce different behaviors of the link slab. For the bridge, while Fig. 2 is a section drawing of the link slab
each test, the specimens were loaded to no more than 40% of the showing the details and reinforcement. The link slab was de-
estimated ultimate load capacity to observe the behavior in the signed for a girder end rotation of 0.002 rad using the proposed
elastic range. The load was applied incrementally and data for the design procedure developed by Caner and Zia 共1998兲.
steel and concrete strains, loads, crack growth, and deflections
were collected for each increment 共Caner and Zia 1998兲.
Bridge Instrumentation
Design of the Plott Creek Bridge Rehabilitation
In 1997, the NCDOT identified a suitable bridge in Haywood Locations and Types of Instruments Used
County, N.C. to implement the use of a link slab to reduce the The performance of the link slab was monitored with instrumen-
number of expansion joints. The structure carried two lanes of tation placed as shown in Fig. 5. To measure temperature at the
traffic and was being widened to accommodate a third traffic lane. structure and also within the deck, there were 16 thermocouples at
The original structure, which was built in 1965, underwent a re- different positions along the structure. These devices were FF-
habilitation in 1998 where the abutments were modified from K-24 Omega thermocouples. The maximum temperature that
conventional to integral abutments by embedding the girder ends these particular gauges can read is 200°C. There were 12 thermo-
into the abutment concrete. In addition, another pier was added couples located inside of the bridge deck and four attached to the
and the cap-beams were extended to support the additional girder steel girders. At each location within the deck, there was a gauge
line. Fig. 3 is a picture of the entire Plott Creek bridge in Hay- at the top of the slab and one at the bottom of the slab 共see Fig. 6兲.
wood County. The new superstructure is located on a horizontal To measure strain in the structure there were electrical resis-
tance strain gauges, as well as vibrating wire strain gauges. The
electrical resistance strain gauges were type CEA-06-250UW-120
gauges from Micro-Measurements. There were 12 electrical resis-
tance strain gauges located within the structure. Six of the gauges
were located in the bridge deck and six were attached to the steel
girders. At each location there was a gauge at the top of the deck
and also at the bottom of the deck. There was also a gauge at the
top, middle, and bottom of two of the girders 共see Figs. 7 and 8兲.
All exposed electrical resistance gauges were weatherproofed
with Micro-Measurements M-Coat D and Scotch 3M Mastic tape.
Unfortunately, these gauges proved to be unreliable and little use-
ful information was obtained from them.
The vibrating wire strain gauges were type EM-5 from
Roctest. The gauge was approximately 18 cm long with two end
disks of 2.5 cm diameter. The gauge has a range of 3,300 micro-
strain. Not only do these gauges measure strain, they also contain
a thermistor, which determines the temperature at the location of
Fig. 7. Strain gauge layout over Bent 1 the gauge.

334 / JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005


Fig. 9. 共a兲 Linear variable differential transform 共LVDT兲 layout and 共b兲 LVDT stands

There were 16 Schaevitz DC-SE Series linear variable differ- were bolted to the cap beam, and the LVDTs mounted to the
ential transformers 共LVDTs兲 positioned on the bridge as shown in stands with plastic grips. Note that in Fig. 9共b兲 only two gauges
Fig. 5. They were attached to stands that were designed by Wag- are visible. The other two gauges supported by the stand are on
ner 共2001兲 which were attached to the bents at the desired loca- the other side of the girder web.
tions as shown in Fig. 9共a兲. The stands, shown in Fig. 9共b兲, were The LVDTs mounted on the stands were used to determine the
placed between girders at locations marked by the triangles in
girder end rotations based on the measured displacements. Three
Fig. 5. Each stand supported a total of four gauges. Stands placed
different LVDT stroke lengths were used to instrument the struc-
between the interior girders 共girder line 4兲 measured deformation
relative to adjacent stiffeners, while stands placed on the exterior ture: 50, 12, and 7 mm. As previously mentioned, at each location
girders 共girder line 5兲 measured deformation relative to aluminum there were four devices: two connected to the end of each adja-
angles that were attached with epoxy to the girders. The stands cent girder at different heights 共see Fig. 9兲.

JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005 / 335


Table 1. Loads Used during Live Load Test 共kN兲
Load 1 Load 2 Load 3 Load 4
Axle left/right left/right left/right left/right
1a 21.53/ 19.93 20.55/ 20.19 21.17/ 21.44 22.95/ 22.69
2 13.97/ 16.28 20.11/ 22.24 25.98/ 28.91 40.83/ 44.66
3 15.39/ 14.77 19.39/ 20.73 25.62/ 28.38 39.77/ 44.57
4 10.05/ 8.36 28.20/ 21.44 35.76/ 45.37 46.88/ 58.54
5 8.54/ 8.36 23.58/ 17.08 31.05/ 40.66 46.35/ 56.40
Total 137 214 304 424
a
Axle 1 is in front of the truck.

Description of the Campbell Scientific Remote holes at the base which allow the wires from the gauges and the
Solar-Powered Data Acquisition System other equipment to enter. Each box was equipped with a moisture
indicator card to guard against moisture intrusion as well as locks
Power was supplied to the data acquisition system by a BP24 12
to prevent the equipment inside from being vandalized. For fur-
V, 24 A hour lead acid battery which was charged by an onsite
ther details regarding the data acquisition system, see Warren
MSX10 solar panel 共1994兲. The solar panel was positioned to
共2000兲.
minimize the potential for vandalism while receiving ample sun-
light to power the system. The solar panel and battery were con-
nected directly to a CH12R volt charge regulator, which limits the
power supply to the associated instruments in the event of a Live Load Test
power surge.
The charge regulator was connected directly to the central pro- Load History
cessing unit, which was a CR23X-4M datalogger 共1998c兲 capable
of 4 MB of data storage. The datalogger controls all operations of The live load test was conducted in June of 2001 and consisted of
the multiplexers and stored data from the gauges until the data is four prescribed load levels positioned on the bridge at two differ-
retrieved. The software used to control the collection of the data, ent locations. The first location was selected to produce the maxi-
communicate with the datalogger, and setup telecommunications mum positive moment in one of the spans adjacent to the link slab
used at this project site was PCW208 Datalogger Programming 共Position One兲 while the second location was selected to produce
Software 共1998d兲. the maximum negative moment in the link slab 共Position Two兲.
There were two models of multiplexers used at this site. The The magnitudes of the loads that were selected were based on
first multiplexer was the AM416 Multiplexer 共1996兲 which was the capacity of the truck that was to be used to apply the loads to
the central collection point for thermocouples, electrical resis- the bridge, as well as the maximum allowable overload condition.
tance strain gauges, vibrating wire strain gauges, and LVDTs. The The first load used was the weight of the empty truck: 137 kN.
second multiplexer, model AM25T 共1998a兲 was the central col- The third load used was close to the maximum allowable load for
lection point for the thermocouples. All of the gauges previously the specified truck without the need of a permit, which in this case
discussed were connected directly to the appropriate multiplexer. was 304 kN. The second load used was approximately halfway in
Data from these gauges was stored in the datalogger and down- between the first and third loads 共214 kN兲. The fourth and final
loaded remotely through the use of a COM200 9600 baud modem load that was used for the test was 424 kN. This was the largest
共1998b兲. allowable permit load that the North Carolina Department of
The last component of the data acquisition was three ENC Motor Vehicles 共DMV兲 allowed for this bridge. Table 1 lists the
16/ 18 weatherproof enclosures. These enclosures have small loads that were used during the test, while Fig. 10 is a diagram of

Fig. 10. Truck positions on bridge

336 / JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005


Fig. 11. Truck positions during live load testing: 共a兲 maximum positive moment; and 共b兲 maximum negative moment

the wheels and axles of the truck. The truck location on the bridge 共2.006/ 2.438兲 ⫻ 21.53 kN and 共1.048/ 2.438兲 ⫻ 19.93 kN. Table 2
for each of the two positions is shown in Fig. 11. lists the loads for the girder four run, and Table 3 lists the loads
for the girder five run. The girder four run is the model in which
girder four was analyzed and likewise the girder five run was the
Expected Bridge Performance
model in which girder five was analyzed. The abutment was mod-
A model was developed using the computer program Visual eled with a fixed joint and the expansion joint was modeled with
Analysis 共2000兲 to predict the girder end rotations during the live a roller joint. The link slab was modeled using a pinned connec-
load test. Only Spans A and B were incorporated into the model. tion at the girder end bearings of the two adjacent girders. The
The other half of the bridge is not instrumented and an expansion stiffness of the composite girders and link slab were calculated by
joint separates the two halves. Only one girder line was modeled transforming the concrete into an effective area of steel.
at a time. The loads were positioned along the girders at the same
locations that the wheel loads were during the test, with one point
Test Results
load used for each axle. The load that was used was a combina-
tion of the two wheel loads for each axle, assuming simple span The results of the live load test were compared to those obtained
behavior of the deck. Tables 2 and 3 list the loads that were from the Visual Analysis model. Figs. 12共a–f兲 represent the results
entered into the computer model for the two different instru- of this comparison where the truck is placed to generate maxi-
mented girders. These loads were obtained by multiplying the mum positive moment in Span B, while Figs. 13共a–f兲 provide the
wheel loads by the ratio of the distance the wheels were from the results for the truck position which generates maximum negative
girder to the girder spacing. In effect, this is the load that is moment at the link slab. In each of Figs. 12 and 13, six graphs for
carried by the modeled girder. For example, the 26.26 kN load the six girder ends where rotation can occur are shown. Also, in
used for girder four, axle one, was achieved by adding each graph, “V.A.” represents the results from the Visual Analysis

Table 2. Girder 4 Loads 共kN兲 Table 3. Girder 5 Loads 共kN兲


Load Load
Axle 1 2 3 4 Axle 1 2 3 4
1 26.26 25.57 26.62 28.61 1 10.95 11.09 11.78 12.46
2 18.48 26.08 33.78 52.75 2 8.94 12.22 15.88 24.53
3 19.00 24.85 33.25 51.84 3 8.11 11.39 15.59 24.48
4 11.86 32.39 48.89 63.69 4 4.59 11.78 24.92 32.16
5 10.61 26.72 42.99 62.33 5 4.59 9.38 22.33 30.98
Total 86.20 135.60 185.53 259.23 Total 37.19 55.86 90.50 124.61

JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005 / 337


Fig. 12. Comparison of experimental and analytical results for Position 1, maximum+ moment: 共a兲 Girder A4 at the link slab; 共b兲 Girder B4 at
the link slab; 共c兲 Girder B4 at the expansion joint; 共d兲 Girder A5 at the link slab; 共e兲 Girder B5 at the link slab; and 共f兲 Girder B5 at the expansion
joint

model, while “L.L.T.” represents the results from the live load worth noting that the apparent nonlinear behavior in terms of
test. In each figure, a diagram indicates the truck position as well force versus rotation is due to the fact that the relative magnitudes
as the location where the rotation is plotted 共shown as an ellipse兲. of the axle loads change with each run, thus changing the point of
Numerical results for the tests and analysis are also shown in the resultant total load, which leads to nonlinearity in the force
Tables 4–7. Note that the rotations from the live load tests were versus rotation plots. Clearly, one of the results from Fig. 12共b兲
obtained by dividing the difference of the LVDT readings at each
appears to be unreliable, however, the remaining data points agree
location by the vertical distance between the LVDTs.
reasonably well with the analysis results. It is also worth noting
From Figs. 12 and 13, good agreement is generally seen be-
tween the recorded and estimated values. This indicates that the that the rotations were higher in Span B than in Span A when the
load distribution formulas provide a reasonable estimate of girder truck was placed to generate maximum moment in the respective
demands. In each case, the vertical axis represents total load spans 共see Fig. 12兲. This is expected due to the presence of the
while the horizontal axis represents the rotations at the point iden- integral abutment at the beginning of Span A and the free end at
tified by an ellipse in the sketch included within each figure. It is the end of Span B.

338 / JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005


Fig. 13. Comparison of experimental and analytical results for Position 2, maximum− moment: 共a兲 Girder A4 at the link slab; 共b兲 Girder B4 at
the link slab; 共c兲 Girder B4 at the expansion joint; 共d兲 Girder A5 at the link slab; 共e兲 Girder B5 at the link slab; and 共f兲 Girder B5 at the expansion
joint

Table 4. Rotations 共rad兲 Due to Maximum Negative Moment 共Computer Model兲


Load
共kN兲 A4-N B4-S B4-N A5-N B5-S B5-N
0 0 0 0 0 0 0
137 0.000080 0.000079 0.000077 0.000035 0.000033 0.000031
214 0.000110 0.000180 0.000185 0.000045 0.000066 0.000066
304 0.000143 0.000271 0.000284 0.000068 0.000138 0.000147
424 0.000187 0.000368 0.000393 0.000089 0.000183 0.000195

JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005 / 339


Table 5. Rotations 共rad兲 Due to Maximum Positive Moment 共Computer Model兲
Load
共kN兲 A4-N B4-S B4-N A5-N B5-S B5-N
0 0.000000 0.000000 0.000000 0.000000 0.000000 0.000000
137 0.000051 0.000150 0.000195 0.000021 0.000065 0.000084
214 0.000082 0.000274 0.000403 0.000033 0.000112 0.000155
304 0.000113 0.000396 0.000599 0.000056 0.000195 0.000300
424 0.000161 0.000571 0.000848 0.000077 0.000278 0.000417

Table 6. Rotations 共rad兲 Due to Maximum Negative Moment 共Live Load Test兲
Load
共kN兲 A4-N B4-S B4-N C4-S A5-N B5-S B5-N C5-S
0 0.000000 0.000000 0.000000 0.000000 0.000000 0.000000 0.000000 0.000000
137 0.000045 0.000026 0.000049 0.000005 0.000019 0.000042 0.000056 0.000001
214 0.000071 0.000046 0.000232 0.000005 0.000062 0.000117 0.000079 0.000002
304 0.000136 0.000102 0.000454 0.000005 0.000114 0.000200 0.000182 0.000006
424 0.000148 −0.000037 0.000524 0.000016 0.000110 0.000272 0.000224 0.000007

Table 7. Rotations 共rad兲 Due to Maximum Positive Moment 共Live Load Test兲
Load
共kN兲 A4-N B4-S B4-N C4-S A5-N B5-S B5-N C5-S
0 0.000000 0.000000 0.000000 0.000000 0.000000 0.000000 0.000000 0.000000
137 0.000070 0.000083 0.000119 0.000016 0.000043 0.000080 0.000126 −0.000008
214 0.000094 0.000835 0.000286 0.000022 0.000052 0.000177 0.000176 0.000021
304 0.000171 0.000204 0.000595 0.000027 0.000133 0.000289 0.000397 0.000016
424 0.000234 0.000149 0.000703 0.000076 0.000143 0.000409 0.000452 0.000020

Table 8. Daily Temperature Ranges 共Celsius兲 for Thermocouples Near Top of Bridge Deck
Value Top B4 Top A4 Top A 4-5 Top B 4-5 Top A5 Top B5
Maximum 14.32 18.09 17.10 16.88 N/A 18.43
Minimum 0.21 0.55 0.46 0.48 N/A 0.60
Average 6.86 9.80 8.99 8.86 N/A 9.93
Note: N/A⫽not available.

Table 9. Daily Temperature Ranges 共Celsius兲 for Thermocouples Near Bottom of Bridge Deck
Value Bottom B4 Bottom A4 Bottom A 4-5 Bottom B 4-5 Bottom A5 Bottom B5
Maximum 15.42 20.03 16.05 15.53 16.35 15.96
Minimum 0.45 0.62 0.47 0.47 0.54 0.56
Average 7.82 10.93 8.25 8.01 8.68 8.23

Table 10. Daily Temperature Ranges 共Celsius兲 for Thermocouples on the Girders
Value Bottom Steel Mid B4 Bottom Steel Mid B5 Bottom Steel Mid A5 Bottom Steel Mid A4
Maximum 16.68 21.81 22.05 21.20
Minimum 0.58 0.00 0.00 0.00
Average 8.53 9.00 9.47 8.94

Table 11. Yearly Temperature Ranges 共Celsius兲 for Thermocouples Near Top of Bridge Deck
Value Top B4 Top A4 Top A 4-5 Top B 4-5 Top A5 Top B5
Maximum 27.47 35.54 34.70 35.32 N/A 36.12
Minimum −8.66 −11.12 −10.77 −10.41 N/A −10.90
Note: N/A⫽not available.

340 / JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005


Table 12. Yearly Temperature Ranges 共Celsius兲 for Thermocouples Near Bottom of Bridge Deck
Value Bottom B4 Bottom A4 Bottom A 4-5 Bottom B 4-5 Bottom A5 Bottom B5
Maximum 32.00 37.37 32.32 33.24 34.43 32.67
Minimum −9.63 −11.26 −9.78 −9.49 −9.82 −9.61

Long-Term Monitoring of internal temperature. Nonetheless, it is also possible that rain-


fall on the top of the deck or wind blown radiant heat could also
cool off the top of the deck, resulting in the variations shown in
Overview
Fig. 14.
In order to assess long term performance of the link slab, the Using the temperature difference from the top to bottom of the
bridge was monitored over the course of an entire year. During bridge, the expected rotations for an entire year were calculated
the long-term monitoring phase, the data was acquired at 2 h and plotted in Figs. 15–18 along with the measured thermal rota-
intervals. At each 2 h interval, the system was activated and data tions based on the LVDT readings. The rotations are shown as
was collected for 2 min. During the course of the 2 min that the referenced from the condition at the first day of recording. There-
data acquisition system was activated, approximately 40 readings fore the rotations on subsequent days were obtained by subtract-
were taken of each gauge. The speed of acquisition during the 2 ing the rotation at day “x” from the rotation at day “1.” By defi-
min of activity was controlled by the rate at which the vibrating nition, this can also include some rotations due to service loading,
wire gauges could be scanned. Unfortunately, these gauges took however, these rotations were generally small compared to the
approximately 3 s to read, thus limiting the rate at which the other thermal induced rotations.
gauges could be scanned. Nonetheless, by reading the gauges From these figures it can be seen that the expected thermal
continuously, the possibility exists to assess girder end rotations rotations were larger than the measured thermal rotations. This is
due to traffic loads during the 2 min of activity. All graphs in this not surprising since the recorded changes in temperature are
section that plot “day” on the horizontal axis start with “day 1” as somewhat erratic as was discussed earlier and attributed to mo-
January 1. mentary variations in surface temperature.

Daily Temperature Variations


Overall Link Slab Performance
It is common for the range of temperatures throughout a typical
day to be in excess of 15°C at the bridge site. Tables 8–10 display
The design rotation for the link slab, which was obtained by as-
the maximum and minimum temperature ranges for the different
suming simply supported girders, was 0.002 rad. Rotations of this
thermocouples over the course of a day. The average daily tem-
magnitude were never achieved, even during the overload condi-
perature difference is also presented. The gauge located in the top
tion. All of the rotations during the live load test were much
of the deck at the midspan of girder A5 was not working properly,
lower. As stated before, fine cracks may appear in the jointless
hence it is omitted from the tables.
bridge deck at the link slab location under normal service loads.
Fig. 19 shows a picture of the crack located in the link slab for the
Seasonal Temperature Variations Plott Creek bridge. It is estimated that the crack width was 1.6
While the daily temperature variations can be in excess of 15°C, mm, which is very small when compared to the width of tradi-
the yearly temperature variations can be in excess of 45°C. Tables tional expansion joints. It should also be noted that during the live
11–13 display the maximum and minimum temperature ranges for load test there was no notable change in the width of the crack. At
the different thermocouples over the course of a year. Again, the this project site a transverse saw cut was made along the link slab
gauge located in the top of the deck at the midspan of girder A5 to control the cracking. It was recommended that the crack be
is not working properly. Fig. 14 is a graph representing the tem- filled with a hot poured sealant to improve its serviceability
perature at the underside of the girder minus the temperature at 共Caner and Zia 1998兲; however, it was left visible for the purpose
the top of the deck over the course of a year. Only one location is of this research program.
shown because the other thermocouple locations produced similar
results. From Fig. 14, the temperature at the bottom of the steel
girders was typically cooler than the top of the deck, which is as Design and Analysis Recommendations for Limit
expected. There are some exceptions to this, and these readings States Design
were likely a result of momentary increases in temperature due to
truck traffic under the bridge passing at the time of the recordings. The actual design criteria for the link slab in the Plott Creek
The thermocouples are very sensitive, and those on the underside bridge was a limit to the crack width of less than 0.33 mm. The
of the bridge were exposed to the atmosphere and subject to pass- width of the crack at the joint was approximately 1.6 mm. While
ing variations in temperature, while those in the top of the bridge still very small, it is still much larger than the design criteria. It is
were embedded in the deck thus giving a more reliable indication believed that the crack initiated as a result of localized debonding

Table 13. Yearly Temperature Ranges 共Celsius兲 for Thermocouples on the Girders
Value Bottom Steel Mid B4 Bottom Steel Mid B5 Bottom Steel Mid A5 Bottom Steel Mid A4
Maximum 33.00 29.51 29.95 29.43
Minimum −9.65 −10.01 −10.47 −10.10

JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005 / 341


Fig. 14. Daily temperature change for a thermocouple over the
course of a year
Fig. 17. Girder B4 comparison

of the concrete. As previously stated, the crack, which was al-


ready present before the testing was conducted, did not change
during any of the live load testing.
The 0.33 mm crack width limit comes from the AASHTO
crack control criteria 共1996兲 under exposed conditions. This crack
width is based on the fact that the cracks are going to be spaced
out over the length of the link slab. However, a saw cut was made
along the link slab to concentrate the cracks in one location. The
result of the saw cut is that the entire deformation is concentrated
at one location. One advantage of this is that instead of many
smaller cracks, the one large crack can more readily be repaired.
The disadvantage is that the deformation is concentrated at one
location, although by debonding, the strain in the reinforcement
may be kept to acceptable levels. It is clear that a larger limit for
crack width should be investigated for link slabs in which a saw
cut is present; however, that is beyond the scope of this research.

Limit States Design


Fig. 15. Girder A4 comparison
In a limit-states design approach, the engineer selects a series of
performance levels that the structural system must achieve. Each
performance level consists of two components: 共1兲 a performance
limit state, and 共2兲 a load under which the performance limit state

Fig. 16. Girder A5 comparison Fig. 18. Girder B5 comparison

342 / JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005


Fig. 19. Crack located at link slab

is to be achieved. With regards to the design of link slabs, the f rM a


performance limit states are defined by residual crack widths, fs = 共3兲
6M cr␳␥ 兵1 + ␩␳/3 − 0.333关共␩␳兲2 + 2␩␳兴0.5其
2
while the loads are defined on the basis of girder end rotations
that are induced due to thermal or service loading. where f s⫽stress in the reinforcing steel, ␳⫽ratio of tension
Several design charts were developed for different steel ratios steel reinforcement, ␩⫽modular ratio 共Es / Ec兲, and
based on the geometry of the bridge specific to the Plott Creek ␥⫽distance to tension steel divided by overall section depth.
bridge. The process for developing these design charts is as fol- 3. Using the Gergely–Lutz expression 共McCormac 1998兲
lows. shown in Eq. 共4兲, solve for the effective tension area of con-
1. Compute the negative moment 共M a兲 induced in the link slab crete around the main reinforcement 共A兲, having the same
due to the applied end rotation using Eq. 共1兲 and the cracking centroid as the reinforcement, using different crack widths.
moment 共M cr兲 of the link slab using Eq. 共2兲.
␻ = 0.076␤f s冑dcA
3
共4兲
2EcId␪ where ␻⫽estimated cracking width in units of 0.03 mm,
Ma = 共1兲
L ␤⫽ratio of the distance to the neutral axis from the extreme
tension fiber and from centroid of main reinforcement,
dc⫽concrete cover measured from extreme tension fiber to
f rI d centroid of nearest reinforcement level in units of mm, and
M cr = 共2兲
y A⫽the effective tension area of concrete around the main
reinforcing divided by the number of bars in mm2.
where M a⫽negative moment induced in the link slab due to 4. Solve for the spacing, s, of reinforcement using Eq. 共5兲
applied end rotations, Id⫽moment of inertia of the link slab, 共Caner and Zia 1998兲.
␪⫽end rotation of the girder, L⫽length of the link slab,
M cr⫽cracking moment of the link slab, f r⫽flexural modulus A
for the deck concrete, and Ec⫽elastic modulus of the con- s= 共5兲
2dc
crete.
2. Compute the stress in the steel using Eq. 共3兲 共Caner and Zia
1998兲
Table 15. Steel Ratio of 0.010
␳ = 0.010 w 共mm兲

Table 14. Steel Ratio of 0.005 ␪ 0.25 0.5 0.75 1.00

␳ = 0.005 w 共mm兲 0.0005 No. 29 at 482


0.00075 No. 16 at 143
␪ 0.25 0.5 0.75 1.00 0.001 No. 10 at 60 No. 29 at 482
0.00025 No. 22 at 530 0.00125 No. 19 at 247
0.0005 No. 22 at 530 0.0015 No. 16 at 143 No. 29 at 482
0.00075 No. 13 at 157 No. 22 at 530 No. 32 at 1257 0.00175 No. 13 at 90 No. 22 at 304 No. 36 at 720
0.001 No. 13 at 224 No. 22 at 530 0.002 No. 10 at 60 No. 19 at 204 No. 29 at 482

JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005 / 343


Table 16. Steel Ratio of 0.015 were generally greater. In each case, the demands were much
␳ = 0.015 w 共mm兲 lower than the assumed design rotational demand. As a result, the
assumption of simply supported spans is acceptable although con-
␪ 0.25 0.5 0.75 1.00 servative. 共2兲 While the size of the crack in the link slab exceeded
0.00075 No. 32 at 451 the design criteria, it thus far has not impaired service of the
0.001 No. 22 at 190 bridge. Furthermore, the large size of the crack 共1.6 mm兲 is due to
0.00125 No. 16 at 98 the saw cut which forced all the deformation into one crack. Re-
0.0015 No. 13 at 56 No. 32 at 451 vised crack control criteria should be investigated for link slabs
0.00175 No. 25 at 284 that contain saw cuts to control crack location. 共3兲 A limit-states
0.002 No. 22 at 190 design approach where reinforcement is sized based on a rota-
0.00225 No. 19 at 134 No. 32 at 451 tional demand and crack control criteria is proposed which allows
0.0025 No. 16 at 98 No. 29 at 329 the engineer to quickly develop design charts for use for a variety
0.00275 No. 13 at 73 No. 25 at 247 of structural configurations.
0.003 No. 13 at 56 No. 22 at 190 No. 32 at 451

5. Compute the number of bars, N, needed using Eq. 共6兲.


Acknowledgments
b
N= 共6兲
s The research described in this paper was supported by the North
where b⫽width of link slab in units of mm. Carolina Department of Transportation under research grant
6. Calculate the area of the reinforcing bars needed, Ab, to ob- HWY-2001-01. In addition, several NCDOT engineers were very
tain the crack width with the specified girder end rotation helpful during the project period including Tim Rountree, Rodger
using Eq. 共7兲. Rochelle, Moy Biswas, Rob Woodruff, and Tom Koch. The writ-
ers would also like to thank Paul Zia, Matt Wagner, Bruce War-
␳b␥h
Ab = 共7兲 ren, Jerry Atkinson, and Bill Dunleavy for their various contribu-
N tions to the large instrumentation effort.
where h⫽overall section depth.
7. Eliminate nonfeasible solutions from the charts such as small
spacing and large reinforcement bar diameters. References
This procedure is then repeated as many times as necessary to
develop the desired design charts. By changing the crack width, American Association of State Highway and Transportation Officials
girder end rotation, and reinforcement ratio, different steel quan- 共AASHTO兲. 共1996兲. sStandard specifications for highway bridges,
tities will be calculated to produce the desired results. Tables 16th Ed., Highway Subcommittee on Bridges and Structure,
14–16 are the design charts that were produced for a link slab AASHTO, Washington, D.C.
having the same geometry as the link slab at the Plott Creek AM25T solid state multiplexer instruction manual. 共1998a兲. Campbell
bridge. These charts can only be used for link slabs having the Scientific Inc., Edmonton, Alberta, Canada.
same depth and length as the link slab in the Plott Creek Bridge AM416 relay multiplexer instruction manual. 共1996兲. Campbell Scientific
since the above-mentioned procedure is dependent on those two Inc., Edmonton, Alberta, Canada.
variables. Charts were developed for steel ratios of 0.005 to COM200 instruction manual. 共1998b兲. Campbell Scientific Inc., Edmon-
0.015. For each of the different steel ratios, different crack widths, ton, Alberta, Canada.
specifically 0.25, 0.5, 0.75, and 1.0 mm, were used for each of the CR23X micrologger operator’s manual. 共1998c兲. Campbell Scientific
different girder end rotations to obtain the different steel quanti- Inc., Edmonton, Alberta, Canada.
ties. Notice that in Tables 14–16, steel quantities are missing for MSX10, MSX10R, and MSX20R solar panels instruction manual. 共1994兲.
certain combinations because the results are not feasible. These Campbell Scientific Inc., Edmonton, Alberta, Canada.
charts are only examples of the different charts that could be PC208W datalogger support software instruction manual. 共1998d兲.
produced using this procedure. Design charts could be developed Campbell Scientific Inc., Edmonton, Alberta, Canada.
for any steel ratio, crack width, and girder end rotation desired by Caner, A., and Zia, P. 共1998兲. “Behavior and design of link slabs for
using the above procedure as long as the results are feasible. jointless bridge decks.” PCI J., 43共3兲, 68–80.
To use these charts, an engineer would chose a crack width El-Safty, A. K. 共1994兲. “Analysis of jointless bridge decks with partially
and girder end rotation based on thermal or service load condi- debonded simple span beams.” PhD dissertation, North Carolina State
tions. The intersection of the two would be the amount of rein- University, Raleigh, NC.
forcing steel required in the link slab to achieve the prescribed McCormac, J. C. 共1998兲. Design of reinforced concrete, Addison-Wesley,
limit state. Menlo Park, Calif.
Visual Analysis; software manual. 共2000兲. http://www.iesweb.com/.
Wagner, M. 共2001兲. “The behavior of prestressed high performance con-
Conclusions crete bridge girders for US Highway 401 over the Neuse River in
Raleigh, NC.” MSCE thesis, North Carolina State University, Raleigh,
Following over a year of monitoring of the bridge structure and N.C.
controlled live load testing, the following conclusions are pre- Warren, B. 共2000兲. “Development of a data acquisition system for an
sented: 共1兲 The link slab within the bridge was subjected to very instrumented highway structure.” MSCE thesis, North Carolina State
low rotations due to traffic loads, while thermal induced rotations University.

344 / JOURNAL OF BRIDGE ENGINEERING © ASCE / MAY/JUNE 2005

View publication stats

You might also like