25 F Condo MEP Design Work Plan May June

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

ID Task Task Name Duration Start Finish Resource Names May 2024 June 2024

Mode 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29
0 25 Floors Condo MEP Design 84 days? Thu 02/05/24 Fri 30/08/24
1 Initiating 4 days Thu 02/05/24 Tue 07/05/24
2 Contract sign off 1 day Thu 02/05/24 Thu 02/05/24 Project Manager Project Manager
3 Internal meeting 1 day Fri 03/05/24 Fri 03/05/24 Project Manager Project Manager
4 Assign task 1 day Mon 06/05/24 Tue 07/05/24 Manager Manager
5 Concept Design Phase 16 days? Wed 08/05/24 Fri 31/05/24
6 Develop concept design document 1 day? Wed 08/05/24 Wed 08/05/24 Project Manager Project Manager
7 Review archeticture plan 2 days Thu 09/05/24 Fri 10/05/24 Engineer Engineer
8 Prepare Xref Drawing 2 days Mon 13/05/24 Wed 15/05/24 Engineer Engineer
9 Prepare sheet set 1 day? Thu 16/05/24 Thu 16/05/24 Engineer Engineer
10 Draft calculation 1 day Fri 17/05/24 Fri 17/05/24 Engineer Engineer
11 Develop concept electrical design 4 days Mon 20/05/24 Fri 24/05/24 E Manager E Manager
12 Develop concept mechanical design 1 day? Mon 27/05/24 Mon 27/05/24 MVAC Manager MVAC Manager

13 Develop concept plumbing design 1 day? Tue 28/05/24 Tue 28/05/24 P Manager P Manager
14 Combine all MEP system 1 day? Wed 29/05/24 Wed 29/05/24 MEP Engineer MEP Engineer
15 Print out to PDF 1 day? Thu 30/05/24 Thu 30/05/24 Engineer Engineer
16 Submit document & drawing 1 day Fri 31/05/24 Fri 31/05/24 Project Manager Project Manager
17 Tender Design Phase 56 days? Mon 03/06/24 Tue 20/08/24
18 Prepare design 5 days? Mon 03/06/24 Fri 07/06/24
19 Internal meeting 1 day Mon 03/06/24 Mon 03/06/24 Project Manager Project Manager
20 Develop tender design document 1 day? Tue 04/06/24 Tue 04/06/24 Manager Manager

21 Review archeticture update 2 days Wed 05/06/24 Thu 06/06/24 Engineer Engineer
22 Prepare sheet set 1 day? Fri 07/06/24 Fri 07/06/24 Engineer Engineer
23 Low voltage system 43 days Mon 10/06/24 Thu 08/08/24
24 LV Calculation (Draft) 3 days Mon 10/06/24 Wed 12/06/24 Senior E Engineer Senior E Engineer
25 Develop lighting system 25 days Mon 10/06/24 Mon 15/07/24 E Engineer 1,E Engineer
2
26 BOQ lighting systm 5 days Tue 16/07/24 Mon 22/07/24 E Engineer 1,E Engineer
2
27 Develop socket system 25 days Mon 10/06/24 Mon 15/07/24 E Engineer 3,E Engineer
4
28 BOQ socket system 5 days Tue 16/07/24 Mon 22/07/24 E Engineer 3,E Engineer
4
29 Develop earthing and lightning 10 days Mon 10/06/24 Mon 24/06/24 E Engineer 5 E Enginee
system
30 Develop main network system 10 days Tue 25/06/24 Mon 08/07/24 E Engineer 5
31 BOQ earthing and lightning system 3 days Tue 09/07/24 Thu 11/07/24 E Engineer 5

32 BOQ main network system 3 days Fri 12/07/24 Tue 16/07/24 E Engineer 5
33 LV calculation (Detail) 3 days Fri 19/07/24 Tue 23/07/24 Senior E Engineer
34 Develop single line diagram 10 days Wed 24/07/24 Tue 06/08/24 Senior E Engineer

Task Project Summary Manual Task Start-only Deadline

Project: 25 Floors Condo MEP D Split Inactive Task Duration-only Finish-only Progress
Date: Wed 01/05/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Resource Names May 2024 June 2024
Mode 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29
35 Check & Review 2 days Wed 07/08/24 Thu 08/08/24 E Manager
36 Extra low voltage system 32 days Mon 10/06/24 Wed 24/07/24
37 Develop fire alarm system 25 days Mon 10/06/24 Mon 15/07/24 ELV Engineer 1
38 BOQ fire alarm system 5 days Tue 16/07/24 Mon 22/07/24 ELV Engineer 1
39 Develop telecommunication system 25 days Mon 10/06/24 Mon 15/07/24 ELV Engineer 2

40 BOQ telecommunication system 5 days Tue 16/07/24 Mon 22/07/24 ELV Engineer 2
41 Develop CCTV system 15 days Mon 10/06/24 Mon 01/07/24 ELV Engineer 3
42 BOQ CCTV System 3 days Tue 02/07/24 Thu 04/07/24 ELV Engineer 3
43 Check & Review 2 days Tue 23/07/24 Wed 24/07/24 ELV Manager
44 MVAC System 38 days Mon 10/06/24 Thu 01/08/24
45 Ventilation system calculation (Draft) 5 days Mon 10/06/24 Fri 14/06/24 Senior MVAC Engineer Senior MVAC Engineer

46 AC system calculation (Draft) 5 days Mon 17/06/24 Mon 24/06/24 Senior MVAC Engineer Senior M

47 Develop ventilation system 25 days Mon 10/06/24 Mon 15/07/24 MVAC Engineer 1,MVAC
Engineer 2
48 BOQ ventilation system 5 days Tue 16/07/24 Mon 22/07/24 MVAC Engineer 1,MVAC
Engineer 2
49 Develop AC system 25 days Mon 10/06/24 Mon 15/07/24 MVAC Engineer 3,MVAC
Engineer 4
50 BOQ AC System 5 days Tue 16/07/24 Mon 22/07/24 MVAC Engineer 3,MVAC
Engineer 4
51 Ventilation system calculation (Detail) 3 days Tue 23/07/24 Thu 25/07/24 Senior MVAC Engineer

52 AC system calculation (Detail) 3 days Fri 26/07/24 Tue 30/07/24 Senior MVAC Engineer

53 Check & Review 2 days Wed 31/07/24 Thu 01/08/24 MVAC Manager
54 Plumbing system 32 days Mon 10/06/24 Wed 24/07/24
55 Domestic system calculation 5 days Mon 10/06/24 Fri 14/06/24 Senior P Engineer Senior P Engineer
56 Fire fighting system calculation 5 days Mon 10/06/24 Fri 14/06/24 Senior FF Engineer Senior FF Engineer
57 Develop domestic system 15 days Mon 10/06/24 Mon 01/07/24 P engineer 1,P engineer
2
58 BOQ domestic system 3 days Tue 02/07/24 Thu 04/07/24 P engineer 1,P engineer
2
59 Develop soil and waste system 25 days Mon 10/06/24 Mon 15/07/24 P engineer 3,P engineer
4
60 BOQ soil and waste system 5 days Tue 16/07/24 Mon 22/07/24 P engineer 3,P engineer
4
61 Develop fire fighting system 25 days Mon 10/06/24 Mon 15/07/24 FF engineer
62 BOQ fire fighting system 5 days Tue 16/07/24 Mon 22/07/24 FF engineer
63 Check & Review 2 days Tue 23/07/24 Wed 24/07/24 P Manager
64 MEP system 26 days Tue 16/07/24 Tue 20/08/24

Task Project Summary Manual Task Start-only Deadline

Project: 25 Floors Condo MEP D Split Inactive Task Duration-only Finish-only Progress
Date: Wed 01/05/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
ID Task Task Name Duration Start Finish Resource Names May 2024 June 2024
Mode 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29
65 Combine all MEP system 20 days Tue 16/07/24 Mon 12/08/24 MEP Engineer

66 Check & Review 1 day Tue 13/08/24 Tue 13/08/24 E Manager,MVAC


Manager,P Manager

67 Revise electrical system 5 days Wed 14/08/24 Tue 20/08/24 Senior E Engineer
68 Revise MVAC system 5 days Wed 14/08/24 Tue 20/08/24 Senior MVAC Engineer
69 Revise plumbing system 5 days Wed 14/08/24 Tue 20/08/24 Senior P Engineer
70 Closing 8 days? Wed 21/08/24 Fri 30/08/24
71 Prepare submit 7 days? Wed 21/08/24 Thu 29/08/24
72 Prepare sheet set 2 days Wed 21/08/24 Thu 22/08/24 Engineer
73 Print out to PDF 1 day Fri 23/08/24 Fri 23/08/24 Engineer
74 Check & Review 2 days Mon 26/08/24 Tue 27/08/24 E Manager,ELV
Manager,MVAC
Manager,P Manager

75 Check & Review 1 day? Wed 28/08/24 Wed 28/08/24 Project Manager
76 Submit document & drawing 1 day Thu 29/08/24 Thu 29/08/24 Project Manager
77 Contract Closure 1 day? Fri 30/08/24 Fri 30/08/24
78 Close Contract 1 day? Fri 30/08/24 Fri 30/08/24 Project Manager

Task Project Summary Manual Task Start-only Deadline

Project: 25 Floors Condo MEP D Split Inactive Task Duration-only Finish-only Progress
Date: Wed 01/05/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3