25 F Condo MEP Design Work Plan

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID Task Task Name Duration Start Finish Resource Names 05 May '24 12 May '24

Mode W T F S S M T W T F S S M T W T
0 25 Floors Condo MEP Design 84 days? Thu 02/05/24 Fri 30/08/24
1 Initiating 4 days Thu 02/05/24 Tue 07/05/24
2 Contract sign off 1 day Thu 02/05/24 Thu 02/05/24 Project Manager Project Manager
3 Internal meeting 1 day Fri 03/05/24 Fri 03/05/24 Project Manager Project Manager
4 Assign task 1 day Mon 06/05/24 Tue 07/05/24 Manager Manager
5 Concept Design Phase 16 days? Wed 08/05/24 Fri 31/05/24
6 Develop concept design document 1 day? Wed 08/05/24 Wed 08/05/24 Project Manager Project Manager
7 Review archeticture plan 2 days Thu 09/05/24 Fri 10/05/24 Engineer Engineer
8 Prepare Xref Drawing 2 days Mon 13/05/24 Wed 15/05/24 Engineer Engin
9 Prepare sheet set 1 day? Thu 16/05/24 Thu 16/05/24 Engineer
10 Draft calculation 1 day Fri 17/05/24 Fri 17/05/24 Engineer
11 Develop concept electrical design 4 days Mon 20/05/24 Fri 24/05/24 E Manager
12 Develop concept mechanical design 1 day? Mon 27/05/24 Mon 27/05/24 MVAC Manager

13 Develop concept plumbing design 1 day? Tue 28/05/24 Tue 28/05/24 P Manager
14 Combine all MEP system 1 day? Wed 29/05/24 Wed 29/05/24 MEP Engineer
15 Print out to PDF 1 day? Thu 30/05/24 Thu 30/05/24 Engineer
16 Submit document & drawing 1 day Fri 31/05/24 Fri 31/05/24 Project Manager
17 Tender Design Phase 56 days? Mon 03/06/24 Tue 20/08/24
18 Prepare design 5 days? Mon 03/06/24 Fri 07/06/24
19 Internal meeting 1 day Mon 03/06/24 Mon 03/06/24 Project Manager
20 Develop tender design document 1 day? Tue 04/06/24 Tue 04/06/24 Manager

21 Review archeticture update 2 days Wed 05/06/24 Thu 06/06/24 Engineer


22 Prepare sheet set 1 day? Fri 07/06/24 Fri 07/06/24 Engineer
23 Low voltage system 43 days Mon 10/06/24 Thu 08/08/24
24 LV Calculation (Draft) 3 days Mon 10/06/24 Wed 12/06/24 Senior E Engineer
25 Develop lighting system 25 days Mon 10/06/24 Mon 15/07/24 E Engineer 1,E Engineer
2
26 BOQ lighting systm 5 days Tue 16/07/24 Mon 22/07/24 E Engineer 1,E Engineer
2
27 Develop socket system 25 days Mon 10/06/24 Mon 15/07/24 E Engineer 3,E Engineer
4
28 BOQ socket system 5 days Tue 16/07/24 Mon 22/07/24 E Engineer 3,E Engineer
4
29 Develop earthing and lightning 10 days Mon 10/06/24 Mon 24/06/24 E Engineer 5
system
30 Develop main network system 10 days Tue 25/06/24 Mon 08/07/24 E Engineer 5
31 BOQ earthing and lightning system 3 days Tue 09/07/24 Thu 11/07/24 E Engineer 5

32 BOQ main network system 3 days Fri 12/07/24 Tue 16/07/24 E Engineer 5
33 LV calculation (Detail) 3 days Fri 19/07/24 Tue 23/07/24 Senior E Engineer
34 Develop single line diagram 10 days Wed 24/07/24 Tue 06/08/24 Senior E Engineer

Task Project Summary Manual Task Start-only Deadline

Project: 25 Floors Condo MEP D Split Inactive Task Duration-only Finish-only Progress
Date: Wed 01/05/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1