Professional Documents
Culture Documents
Instruction Manual - PM6 24kV (S3) & 36kV (S4)
Instruction Manual - PM6 24kV (S3) & 36kV (S4)
PM6 S3-S4
SF6 load break switch-disconnector
MV Overhead distribution switchgear
51107195 M0
Sept 08
IND. F0
Date: 06/2016
1. INTRODUCTION
BEWARE
While high voltage systems are in operation, certain elements of the system are live, others
may be moving, and other parts may reach high temperatures. This means that there are
electrical, mechanical and heat-related risks in the use of these systems.
In order to provide an acceptable level of protection for both people and property and taking
into account the applicable environmental recommendations, the manufacturers that form part
of SERCOBE develop and construct their products according to the principle of integrated
security, based on the following criteria:
• When this is technically or economically unfeasible, build effective protection devices into
the systems.
• Inform users of any remaining risks so as to help them understand the operating
procedures that prevent these risks and help them with the training of the operating
personnel that carry out these information, and the use of the correct personal protection
INDEX: equipment.
• Use recyclable materials according to the state of the art and within applicable technical
1. INTRODUCTION and economic limits and establish procedures for the processing of the equipment and
2. DESIGN FEATURES AND APPLICATIONS
its component parts so that once they have come to the end of their useful lives, they
3. HANDLING, TRANSPORT AND STORAGE
can be dealt with in a way that complies as far as possible with the environmental
4. INSTALLATION
requirements established by the relevant bodies.
5. TORQUE SETTINGS
6. SETTING INTO SERVICE
As a result, when working on the system covered by this manual or in the vicinity thereof the
7. MAINTENANCE MANUAL
specifications of paragraph 11.2 of standard IEC-62271-1 must be taken into account. This
work can only be done by personnel who are suitably trained and supervised (in accordance
with the provisions of the EN50110-1 standard on safety in electrical installations and the
EN50110-2 standard which applies to all kinds of activity in, with or near an electrical
installation) and who are completely familiar with the instructions and warnings contained in
this manual and all others of a general nature that may be applicable under current legislation
on the prevention of risks, and all others that in the future may replace or modify them.
2 of 25
51107195M0
IND. F0
Date: 06/2016
The above instructions must be followed with great care, because the safe and correct
functioning of this system depends not only on its design, but also on circumstances which in
general are beyond the control of and not the responsibility of the manufacturer, in particular:
• The correct transport and handling of the equipment from the time it leaves the factory to
the place where it is to be installed.
• Any storage on the way must be carried out under conditions that do not alter or damage
the characteristics of the system as a whole or of its essential parts.
• The operating conditions must be compatible with the specifications of the system.
• The manoeuvres and operations carried out while using the equipment must be
performed in strict accordance with the instructions in the manual, and with a clear
understanding of the operating and safety principles that apply to it.
• Maintenance work must be carried out correctly, taking into account the real operating
and environmental conditions in the place where the system is installed.
• The disposal of the equipment once it has come to the end of its useful life must be
carried out according to the instructions in the manual and legislation in force at the time.
For this reason, the manufacturer will not be responsible for any direct or indirect damage
resulting from any breach of the guarantee or of the rules set out above under any jurisdiction,
including damage to people or assets, loss of profits, periods of idleness, costs of repair or
replacement of materials.
Guarantee
The manufacturer guarantees this product against any fault in the materials or the operation of
the system during the period covered by the contract. If any defect is detected, the
manufacturer may choose either to repair or to replace the equipment. Incorrect handling of
the equipment or the repair of the equipment by the user will be considered a breach of the
guarantee.
All the registered trademarks in this document are the property of their respective owners. The
intellectual property of this manual belongs to the manufacturer.
3 of 25
51107195M0
IND. F0
Date: 06/2016
2.1.- Description.
8
The aerial remote-controlled PM6 disconnector-switch is designed for use on public distribution
networks, at 10kV to 36 kV. Basic components are:
9
- Three-phase disconnector-switch in SF6
- Electrical control. 6
- Manual command. 7
- Control box, integrating a power source, electrical control management and the 1 3
necessary remote control interfaces
. 2
The set is prepared to be fixed onto the M. V. line support.
It may be operated:
This equipment contains the fluorinated greenhouse gas SF6 covered by the Kyoto Protocol and 5 10
with a global warming potential (GWP) 22 200. SF6 shall be recovered and not released into the
atmosphere.
For further information on use and handling of SF6 please refer to IEC 62271-303: High-voltage
switchgear and controlgear – Part 303 Use and handling of sulphur hexafluoride (SF6) 1-SF6 disconnector-switch.
2- Electrical or manual mechanism.
3- M.V links to line.
4- Manual command rod. Fig 1
5- Manual command.
6- Anchoring structure
7. Support chassis
8-.Surge arresters.
9- Voltage transformer
10-Control.box..
11-Current transformer.
4 of 25
51107195M0
IND. F0
Date: 06/2016
Fig 2
5 of 25
51107195M0
IND. F0
Date: 06/2016
Option 3:
Fault detection. This function is carried out by
the current transformer mounted on one side of
the disconnector-switch.
The transformer detect the following:
Phase and homopolar fault.
2nd level
• Phase fault: 100at 750A, 50 passes
• Homopolar fault: 3 at 25A, 1A passes
Fig 3
Fault information is displayed on an LED
display situated inside the control box, with a 1- Double-ceil.
signaling contact.
2- Electronics card (Power, control and remote card)
8 Antivandalism cap.
6 of 25
51107195M0
IND. F0
Date: 06/2016
2.2.-Technical features Any other use may affect the safe operation and correct performance of the unit, giving rise to
potential hazards for persons and plant equipment. It is therefore important to read thoroughly
2.2.1.-Electrical system characteristics and understand the manual before attempting any installation work or operation of the unit.
Ensure also that all staff employed to install or service the unit are properly trained.
See table 6
The operations described should be carried out in accordance with current safety legislation and
2.2.2.-Applicable standards. under the responsibility of a person qualified representing the user.
CEI 62271-103. CEI 62271-102. SCHNEIDER accepts no liability whatsoever for any consequences that may result from failure to
observe the instructions contained in this manual, or from any unauthorized use of the unit. For
CEI 62271-200. CEI 60694 CEI 60815 safety reasons, you are strongly advised to consult us before carrying out any operation not
included in the manual.
2.3.-Figures of Nameplate. As a result of improvements in materials technology, you may find that certain items on your unit
do not exactly match the information provided in this document. If this is the case, or if you have
The apparatus is identified by the nameplate on the disconnector-switch where the serial number any other query regarding the system, please contact us directly or via our commercial
appears. representatives or after-sales service.
Side
panel
2.4.-Operating conditions.
PM6-S3 and PM6-S4 disconnector-switches are designed to provide long-term safe and reliable Figure 5
functioning, provided the instructions in this manual are strictly observed and the devices are
used as stipulated and according to the conditions listed in I.E.C. 60694:
- Max. temperature 50º; min. temperature-25ºC
- Altitude less than 1.000 m.
- Other operating conditions by consultation
7 of 25
51107195M0
IND. F0
Date: 06/2016
3.2.- Lifting and transporting the unit. 3.3.- Checking at the arrival.
Please follow the instructions indicated on the crates: Please carry out a check immediately after delivery to ensure that the items supplied match the
The apparatus must be lifted in the packaging to the nearest possible point to the post. (figure 6- items listed in the delivery note and order documentation.
1) You are advised to carry out a visual check to ensure that the units have not suffered any
A forklift truck or crane is enough for moving and handling the unit. damage in transit.
Important: If you do find any damaged items, please contact the insurer and make the corresponding claim.
- Avoid any impacts or sudden movements that may damage components. Before carrying out this inspection, please unpack the unit following the instructions given in
- Do not leave the packing cases in any inadequate location such as on an unstable surface. section 3.4.
- Do not slide the units down sloping floor areas or stairways. Now inspect the delivery to ensure that each item is correctly identified, and check the following
items:
The details shown on the nameplate should match the order specifications.
All accessories included in the order should be present.
In the event of any anomaly, please make out a report in collaboration with the carrier. The report
should indicate the order number and give details of the damage and how it was caused.
All damage reports and compensation claims MUST be submitted to SCHNEIDER within the
guarantee period toclaim for responsibilities.
Fig 6-1
1. The apparatus, with its packing, must be deposited as close as possible to the post
and parallel to the line. The space between the post and the apparatus must be sufficient to allow
the assembly of surge arresters and the connectors and to allow operation of the lifting
Fig 6-2 equipment.
2. Remove top and side panels from upper section, from transverse supports onwards.
Loosen the screws fixing apparatus to packaging.
Once the packaging is open as indicated, release low voltage cable leaving it tight so that the
centre of gravity of the apparatus is not affected. Never let the disconnector-switch rest on the
ground, as this could damage the disconnector-switch output shaft and the connecting cables.
8 of 25
51107195M0
IND. F0
Date: 06/2016
3. Remove post fixing clamp from packaging and screw onto post or metalic support. 3.5- Storage.
Mounting position. (figure 23) - The disconnector-switch will be stored in its original packing.
- It is not advisable to store the units in sealed seaworthy packing for more than a period of six
months,(standard) counted from the moment of dispatch from SCHNEIDER.
When lifting the disconnector-switch, special care must be taken to - Protect from corrosive atmospheres such as chemical agents: cement dust, acid emissions,
avoid damaging the ceramic parts, especially those of the smoke, saline.atmospheres, etc.
transformer, as these are located very near to the elevation point. - Store all items in a dry, well-ventilated place.
- Ensure that all components are stored carefully, stacked or grouped in a way corresponding to
their installed locations.
- Items stored for a long period should be cleaned and lubricated before being used, following the
NOTE. instructions given in the maintenance section (section 7) of this document.
It is extremely important not to damage the equipment. Do not remove the apparatus from - Check battery status and cable set (apparent shock, good connection and in working order)
the support supplied with the packaging. It will be sent to its destination along with this CAUTION
support, and must only be removed for lifting to the post. - The battery must not be stored for more than 3 years without being recharged.
- To help conserve the battery, do not use a car-type battery charger; use the T-200P unit
itself to recharge batteries.
4.- INSTALLATION.
4.-instalación.
4.1.- General conditions
The minimum conditions corresponding to the point of installation should conform to HV rules
Packaging support contained in the rules applicable in the destination country.
4.2.- Assembly
- When carrying out jobs under hight voltage, the transformer terminals must receive voltage
simultaneously in order to prevent induced overvoltage phenomena that might damage the
transformer. A proposal is outlined below for assembly procedure under voltage based on a
typical PM6 option.
Please consult for other options.
Fig 8 - Make a provisional by-pass in the line where the disconnector-switch is to be
installed.
9 of 25
51107195M0
IND. F0
Date: 06/2016
The surges arrester are usually supplied dismantled and are mounted on the structure in the zone
indicated in 11. For assembly, the screw set supplied has to be placed in the holes.
Screws must be tightened with a torque wrench or spanner. Torque setting 30N/m.
Fig 11
Figura 9
Torquing
4.2.3.-Connector Assembly.
OPPOSITE SIDE
Phaese
Figure 10
10 of 25
51107195M0
IND. F0
Date: 06/2016
4.2.3.1- Unpacking the Connectors. surface of the socket (Figure 17) and 1/3 to the connector zone indicated in figure 18. Special
The connectors must never all be unpacked at once. Unpack one at a time just before mounting care must
in order to avoid dirt and deterioration by bumps or scratches. be taken to avoid greasing the metallic zone in the socket indicated in figure 16.
4.2.3.2- Handling
To avoid dirt getting into the connectors during handling, the disposable gloves provided in the Area of grease Metallic area
assembly
Kit must always be used. Area of grease
4.2.3.3- Cleaning Connectors and Sockets
Before mounting the connector on the socket the connector and socket must be cleaned as
instructed in figures 15 and 16.
Area to be cleaned Metallic area
Figura 17 Figura 18
As indicated in section 4.2.2.1. connectors must be assembled one by one. After greasing, place
Figure15 Figure 16 the nylon thread in the connector as shown in figure 20 and proceed with assembly,
pressing strongly in the direction of the socket shaft, turning clockwise until firmly screwed onto
the socket.
Once the connector is screwed onto the socket and apply a torque setting of 70Nm to the outer
nut with a torque wrench ( figure 21).
4.2.3.3.1 -Cleaning the Connector.
Using the gloves supplied with the KIT at all times, insert the isopropyl alcohol-soaked paper
supplied in the KIT to the zones to be cleaned (figure 15) in a twisting motion inside the connector
until
clean. For less accessible areas, use wooden tool supplied with the KIT, twisting along with the
isopropyl
alcohol-impregnated paper.
CAUTION: Great care must always be taken in cleaning to avoid black rubber semiconductor
residues
(figure 15) in the contact zones between the connector and socket.
With the same paper used in the connector, proceed to clean the socket in the zone indicated in
figure 16.
11 of 25
51107195M0
IND. F0
Date: 06/2016
Once the assembly has been carried out, proceed with extraction of the nylon thread. After
extracting the thread, the connector must be turned gently in both directions to eliminate the
marks produced in the grease during extraction.
CAUTION.
Connector and surge arrestor assembly must be carried out WITHOUT VOLTAGE
After checking the torque setting of the connector, no torque pressure above 20Nm must
be appliedin anticlockwise direction to the connector or connections to be screwed onto
this connector.
Take into account the supporting face where the apparatus is to be installed, so that the voltage
transformer
remains supplied even although the disconnector-switch is open.
Fig 23
12 of 25
51107195M0
IND. F0
Date: 06/2016
Fig 24
A.- Attachment using metal bands, regardless of the diameter of the post (figure 25).
B.- Attachment using stud and bolts, of sufficient lenght to go through the metal clamps,
regardless of diameter.(figure 26)
C.- Fixing by brakets and screw rods. The diameter must be less than mid-axis of fixaton.(figure
27)
Figure 25 Figure 26
Figure 27
Metal band attachment : Screw bolt attachment: Bracket and rod attachment:
Whatever the diameter of Support for a regular Diameter must be less than the
the support. post. Distance between the attachment
centre axes.
13 of 25
51107195M0
IND. F0
Date: 06/2016
The user have to manufacture the metal fittings to anchor the to the post. Dimensions of manual
command support plate. (figure 30)
Figura 30
Figura 31
Take the following points into account before drilling into any part:
a)- Make sure that the functioning of the apparatus will not be affected.
b)- The anchoring base must provide solid support.
c)- Clean up rough edges and burrs.
d)- Protect the drilled holes:
1. Apply a thick coat of zinc chromate-based cold galvanising paint (96% min. 4.3.- Lifting, leveling and alignment.
of powdered zinc.) Wherever possible, lift the frames directly from their delivery packaging to the point of final
2. When dry, apply a topcoat of neutral varnish designed for outdoor use. installation on the structure.
14 of 25
51107195M0
IND. F0
Date: 06/2016
4.3.1.- Lifting the Disconnector-switch. Take into account the supporting face where the apparatus is to be installed, so that
the voltage transformer remains supplied even although the disconnector-switch is
open.
Assembly
In addition:
Lift the disconnector-switch with the aid of a hoist, introducing the cables through the suspension
SI OJO IMPORTANTE ring situated on the chassis (figure 6.2)
NO IZAR EL EQUIPO
SIRVIÉNDOSE DE LAS lift the disconnector-switch , avoiding the support shaft A.
CONEXIONES.
- Lower disconnector-switch carefully, checking that support is situated in the central groove
of the frame, B.
A B
SI
yes
Lower switch again for fixing.
Raise the apparatus, passing check that the gear is placed in the
support axle central groove of the chassis
Figure 32
15 of 25
51107195M0
IND. F0
Date: 06/2016
Figure 33
4.3.2.- Manual command.
The transmission pipes are supplied in a separate package. The lower part of the control, the
operating lever (figure 34) and the piece for joining the two pipes (figure 39) are located in the
same package as the switch.
The switch is supplied in the OPEN position which is shown on the bottom of the switch, see
figure 45.
The assembly is done with the switch in the open position. Check its state in the position indicator • Take the other transmission pipe that goes to the command and place it in the
of the switch-disconnector. command support (Fig. 35).
Once the switch-disconnector is installed to the post as well as the support of the manual control, • In case that the pipes are too long and cannot be fitted together, make a mark on
the operations to be carried out are as follows: the pipe that needs to be cut (Fig. 36), remove it and cut it at the mark.
• Check the length needed for the transmission verifying that it is less than 8 metres • Place the switch shaft in the command position as shown in Fig. 37 and the
(normal transmission supply); if it is longer than 8 metres, a supplementary pipe or linkage according to Fig. 35.
another additional support will be necessary.
• Take the pipe that has a 10 mm drilled hole and another slot in one end of the pipe
(the other end does not have holes drilled) and hang it from the switch shaft by
means of a 10-mm-diameter pin. The slotted hole remains free and through it one
must see the other hole of the switch shaft (Fig. 34)
Fig. 37
16 of 25
51107195M0
IND. F0
Date: 06/2016
Place the joining clamp, fastening it tightly (Fig. 38). 4.3.3 Low-voltage cables from the switch-disconnector.
General considerations:
• The downward direction of these cables must be done on the side opposite that of
the earthing circuit, or with a minimum distance of 200 mm between them.
• The cables will go down from the PM6 attached to the post with flanges or similar
devices valid for outdoors, with an approximate distance between them of 1 metre,
avoiding that the weight of the cable hangs directly from the PM6·
• Fig.5 Fig.6 Fig.7 Fig.8 • Cut the cables to the required measurement in order to avoid coils of excess
Fig 38 Fig 39 Fig 40 Fig 41 cable.
•
• Do not leave loose cables, which due to the wind could cause their uncontrolled
• Perform the operations with the command lever, opening and closing. Check that movement, leading to disconnections or even to contacts with the high-voltage
after the switch has made the opening or closing operation, the distance from the areas.
mobile piece and the mechanical stop is equal in both operations(Fig. 39 and 40);
if not, loosen the joining clamp of the pipes, move the pipes in the direction 4.3.4 Assembly of the control box.
needed and again tighten the joining clamp, then check the correct operation.
• Once the switch is adjusted both in closed and open position, change the place of
The control box will be located at the chosen height, on the anchors.
the bolt which is in the shaft of the switch (Fig. 41).
Assemble the control cabinet on the ironwork of the post provided for such purpose.
• The operating lever has three positions that coincide in the slots of the lower pipe Assemble them with the battery outside the control cabinet in order to facilitate the assembly.
of the transmission. Depending on how it is placed in each of these positions or
The cabinet can be mounted with the door closed.
slots, the operation will be the following:
In the installation, take care not to cover the air holes so that air can circulate in the interior.
A) OPEN: the remote control is blocked.
Once mounted, leave it with the door closed.
B) REMOTE CONTROL: possibility of opening or closing the switch by the
remote control.
C) CLOSED: the remote control is blocked. 4.3.5 Connection to the control box.
• The operating lever, positioned in the lower pipe at its lower part, operates the
three positions A), B), C) and remains set by one, two or three padlocks.
These tasks have to be performed prior to the connection of the PM6 to the line; therefore, there
is no voltage in these cables. Keep this situation during the entire connection of the cables. In
case of carrying out maintenance work, bear in mind that the supply cable is directly connected to
the secondary of the voltage transformer, thus it has alternate current. Be careful when handling
and follow the specific INFORMATION from the electric company for this kind of situations. Not
short circuiting the supply cables causes the destruction of the voltage transformer.
To connect the cables of the switch, follow the diagram supplied with each set of equipment.
The feeding hose is connected on the circuit-breaker input of the control cabinet.
Always connect the feeding hose to the circuit-breaker of the control box in order to avoid
accidental short circuits of these cables, which in operation cause the destruction of the voltage
transformer. Bear in mind the colour code according to the diagram supplied with this cable, since
one of the cables is joined to the earth in the transformer itself.
The battery must be connected to the control box when the equipment has voltage, in order to
avoid its unnecessary discharge.
17 of 25
51107195M0
IND. F0
Date: 06/2016
After installation or servicing work of any type carry out the following checks before connecting
the power supply:
a) Installation should comply with all points indicated in the manual.
b) Check the operation of the disconnector-switch. The disconnector-switch is delivered in the
OPEN position (position indicated in figure 45) and check that the indicator turns to ( I ) by
carrying out a closing operation.(figure 46)
c) Operating direction for opening and closing, as well as the remote control position are both
indicated on the solid front control panel (figure 42)
Fig 43
d) Check that the apparatus closes 5º before the end of run (5 mm on front control panel).
Proceed in the same way when opening. (figure 43)
e) Check all nuts and bolts for tightness (attachment to structure, transmission units, etc.).
c) Do not paint the hinge points or the articulations of the different set components.
d) Check the control unit for correct functioning, paying special attention to correct visual signal
display.
e) Lubricate all articulations and hinge points on the controls. After checking for free movement
several times, wipe off any surplus grease. (See list of lubricants in table 5, section 7). Figure 45 Figure 46
f) Operate disconnector-switch to check for correct functioning.
- Perform several manual opening and closing operations and check disconnector-switch
signalling: - O open (figure 45) - I closed (figure 46)
g) General cleaning of the stainless steel casing with non-abrasive cloth, applying a domestic
cleaner for stainless steel in order to remove pollutants; dust; moisture; oils etc. that may have
adhered to the equipment during assembly and restore passivation within the steel casing.
18 of 25
51107195M0
IND. F0
Date: 06/2016
Table 3
Figure 49
L.V wiring
19 of 25
51107195M0
IND. F0
Date: 06/2016
Figura 50
CLOSE
OPEN
Figure 51
Figure 50
2.- Manual emergency operation.
To open manually: Turn the right control lever clockwise from the remote control
position.
To close manually: Turn the left control lever anticlockwise from the remote control
position.
Disconnector-switch open: The position indicator below the control is black. (figure 45)
Disconnector-switch closed: The position indicator below the control is white. (figure 46)
Lock in open position (lever on the right) or in closed position (lever on the left) to block
allelectrical controls (local or remote control).
Locking is possible in the 3 positions: remote controlled, open or closed.
20 of 25
51107195M0
IND. F0
Date: 06/2016
Table 4
Paint
Required
Application characteristics Method of application Example
21 of 25
51107195M0
IND. F0
Date: 06/2016
The guarantee is limited to the supply, in the shortest time possible and free of charge, of a part The main characteristics of the disconnector-switches are as follows:
with the some characteristics as the defective component. In accordance with I.E.C standards
Rated voltage S3 S4
24 kV 36 kV
Rated Insulation level
Effective kV, 50HZ, 1min. In relation to mass 50 70
To sectioning distance 60 80
Rated lightning impulse withstand voltageI common value 125 170____
1,2/50 µs Across the insulating distance 145 195___
Other features
Operating
Temperatura(C) maximum +40 +40
minimum -25 -25
Mechanical endurance (cycles C-O)*. 5000 5000
Protection level IP degree IP67 IP67
Control box IP55 IP55
Motor reducer Maximum operating time (s) 8 8
Table 6
22 of 25
51107195M0
IND. F0
Date: 06/2016
Device ID:
Disconnector switch Serial Nº:
T-200P Serial Nº:
Voltage transformer Serial Nº:
Reception
1 Check that the equipment is on its original packing.
2 Check the condition of the packing
3 Open the box to check the contents
4 Check the general conditions of the switch and that the enclosure has no shocks.
5 Check absence of impacts over the cover of the mechanism.
6 Check the medium voltage silicon terminals.
7 Check the voltage transformer terminals.
8 Check the battery status.
9 Check the set of cables (apparent shock, good connection and in working order)
10 Check that the minimum conditions for the installation are in conformity with the MV rules applicable in the destination
country.
23 of 25
51107195M0
IND. F0
Date: 06/2016
17 Apply a closing torque of 70 Nm clockwise to verify that the silicon connections are not loose.
18 The connection terminals of the voltage transformer are in good conditions: absence of fissures.
19 The connection terminals of the voltage transformer do not have traces of oil.
20 The carriage of the voltage transformer does not have any fissures or traces of oil.
21 Check the continuity of the current transformers.
22 Check that none of the wires descending from the switch is grounded, or cut (with the aid of a polymeter)
24 of 25
51107195M0
IND. F0
Date: 06/2016
42 Check that the operation lever is in remote control position, when using the remote controlled option.
43 General cleansing of the stainless steal cover, with non abrasive cloth and domestic stainless steal cleansing product, to
wipe away dust, humidity, oil, etc. that could have been deposed over the equipment while mounting it, and to make it
recover the original characteristics of stainless steal.
44 The operation lever is on the inside of the rod system.
45 Interlocking of the operation lever with padlocks
46 Check that it is not possible to perform any electrical operation when the control box is in LOCKED position.
47 Check that the remote control functions are WORKING / OUT OF SERVICE, according to the operating system criteria.
48 Verify the values configured in the control box for the remote controlled function option through PC.
49 The line and the earthing wires are connected according to the minimum distance required by the voltage level.
50 The auxiliary circuits are correctly connected:
51 Voltage transformer’s secondary circuit is connected to the control box.
52 Battery connected.
53 Once the equipment is under voltage supply:
54 Check the input voltage in the control unit with a voltmeter.
55 If the voltage is right, close the arrival fuse to the magnetothermal switch and verify the rest of the signals.
56 Set time and date in the control unit through PC.
Observations:
25 of 25
ART. 9602518 © Schneider Eletric - All rights reserved
Schneider Electric Industries SAS As standards, specifications and designs change from time to time, please
89, boulevard Franklin Roosevelt ask for confirmation of the informatión given in this publication.
F-92505 Rueil-Malmaison Cedex
Tel: +33 (0)1 41 29 85 00
This document has been printed
www.schneider-electric.com on ecological paper