DAILY SITE PROGRESS REPORT


CRK-MIT-ELV-DSPR-
EFFECTIVE DATE: 05-Dec -2023 REPORT ID: 23-0290

CONTRACTOR: MILLENNIUMIT ESP DISCIPLINE: ELV

WORK START TIME: 8.00 am WORK FINISH TIME: 18.00 pm

01 | STAFF 03 | ACTIVITY PERFORMED ON YESTERDAY


CATEGORY NOS ACTIVITY / OUTCOME WORK DONE MANPOWER
Project Manager 1 SE# LEV CATEGORY NOS
PLANNED ACTUAL
ACTIVITY
Engineer 1
Draftsman 1 L02 GI Conduiting 50% 30%
QS HO
Engineering Intern 2 L-14 Guest Rooms cabling 90% 90%
(balance work)

TOTAL 5

02 | MANPOWER (ALL) 04 | ACTIVITY PLAN TO BE PERFORMED ON TODAY


CATEGORY NOS ACTIVITY / OUTCOME OUTPUT MANPOWER
TECHNICIAN 6 SE# LEV ACTIVI UNIT QTY CATEGORY NOS
ELV | HELPER 3 TY

ELV Technician 2
L02- L03 GI Conduiting
1 1
ELV Helper 1
L-14 Cable tray installation 1 1 ELV Helper 1
ELV Technician 2

Guest Rooms TV and WiFi ELV Helper 1


TOTAL 9 L-06 1 1
Sunk box installation ELV Technician 2

(PM / DEPARTMENT HEAD)

PREPARED BY CHECKED BY CONFIRMED BY


(NCC TEAM)

Sanjeewa Liyanage Amila Gamage

Engineer - Network Project Manager - ELV

SIGNATURE