Project Page 1
Location
BILL OF MATERIALS
Unit Total
Description of Material Quantity | Unit | cose coal
1. FOUNDATION, CONCRETE COLUMNS, BEAMS
‘AND CONCRETE HOLLOW BLOCKS WALLS
Portland Cement, ATLAS brand 450 | Bag | 6500
‘Washed Sand 30 | cum | 250.00
Gravel or Crushed Stones 45 | cum | 350.00
Ezrth Fil 15 | cum | 9000
‘Cone. Holl. Giks., 100 x 200 x 400mm, JACKBILT 1,350 | Piece | 4.00
Do, | 150%x200x 400mm, JACKBILT 2900 | Piece | 450
‘Steel Reinforcing Bars, Deformed: (PAG-ASA brand)
‘10mm x 6.00 meters 350 | Piece | 45.00
‘12mm 6.00 meters 120 | Piece | 95.00
16mm x 6,00 meters 65 | Piece | 150.00
‘We No. 16 for Tying 30 | Kio | 3000
(Common Wire Nails: 50mm (2°) 30 | Ko | 2500
75men (3°) 25 | Ko | 2500
‘100mm (4°) 20 | Kilo | 2500
125mm (5°) 15 | Kio | 2500
Finishing Nails: 3tmm (1-114) 10 | Kio | 2500 250.00
50mm (2') 9 | Kio | 25.00 225.00
63mm (2-1/2') 8 | Kio | 2500 200.00
Concrete Nails, 75mm (3°) 3 | Kio | 3500 1105.00
Form Lumber, Rough Tanquile:
'50 Pes, - SOmm.x 75mm x 3,60mm (23% 12’) 300 | eon | 1250 3,750.00
90 Pes. = 50mm_x $0mm x 3.60mm (2%2%12) 360 | Bat | 1250 4,500.00,
Waterproof Plywood, 6mm x 1.20mx 2.40m 15 | Sheet | 200.00 3,000.00
2. FLOOR FRAMING ....... . se sense P.
Floor Beams, Guijo-Rough
2 Pes. - SOmmx 200mm x 3.00m (2"x8°% 10) 26 | Ben
3 Pes, - 50mmx 250mm x 4.20m (2x10%14") 7o | Ban
5 Pes, - 50mm x 250mm x 3,60m (210 12) 100 | Bat.
Floor Joists and Bridgings, Apitong Rough:
30 Pes, - 50mm x 150mm x 3.00m (2%6°x10) 300 | Bar
40 Pes, - 50mm x 150mm x 4.20m (26X14) 560 | Bd
Prepared by: Approved:
"ARCHITECTIENGINEER ‘OWNER
DATE DATE
ASS ESTIMATING BILL OF MATERIALS - TagayunProject
Owners 71
Location
BILL OF MATERIALS
: Unit Total
Description of Material Quantity | unit | gat a
IMC Botts w/ Washers, 16mm fa x 200mm (51 da x 8")
Common Wire Naiis. 100mm (4°)
Common Wire Nais, 125mm (5°)
SOLIGNUM Wood Preservative
3, ROOF FRAMINGS P.
Roof Beams. Guijo-Rough:
6 Pes. - SOm x 200mm x 3.00m (2x 8x 10) 80 | Bon
8 Pes. - SOmm x 250mm x 4.20m (2"x8"x 14} 10 | Bon
‘Truss Top Chord, Apitong Rough:
{8 Pes. - SOmm x 200mm x 5.40m (2'x 8"x 18} 12 | ban
2 Pes. - 80mm x 200mm x 480m (2'x 8x 16) 42 | Bat
Bottom Chords, Apitong Rough:
8 Pes, -SOmm x 125mm x 420m (2'x 5'x 14) 93 | Ban
Pes, - SOmmx 125mm x 480m (2"x 5" 16) 2 | Bat
Truss Collars, Aritong Rough:
40 Pes, - 50mm x 125mm x2.40m (2"x 5" 8) 66 | Ban
Diagonal and Vertical Truss Members Guijo-Rough
10 Pes. - 0mm x 100mm x 3.6m (Z"x 4°x 12) 2 | Ban.
Rafters, Antong Rough
114 Pes, - 50mm x 150mm x 2.40m (2"x6"x 8) | Bon,
7 Pes, - 50mm x 150mm x 360m (2'x6"x 12) ea | Ban
Cleats. Aptong/Tanqule, Rough:
14 Pes, - 50mm x 50mm x 3,00m (2'x2"x 101 46 | Ban
Putin, Apitong Rough
£80 Pos, 50mm x 7Smmx 360m (2'x3'x 12) as | eat
Fascia Boards, KD Tangule, $25:
410 Pes, - 25mm x 300mm x 4 80m (1"x 12"x 16) te | eat
[MC Bolts with washers, 16mm la x 250mm 5/8" cia x 10) 25 | Piece
Do, ‘amm ax 175mm 1/2" dax 7”) 50 | Piece
‘Common Wre Nails 75mm (3") 5 | Kio
Do 100mm(4’) 7 | ko
Do 125mm(s) 10 | Kilo
Wood Preservative, SOUGNUM 12. | titer
Prepared by Approved
“ARCHITECTIENGINEER OWNER
DATE DATE
AS6Project
Owners
Location
Page 3
BILL OF MATERIALS
: Unit Total
Description of Material Quantity | unit | One ee
4, ROOFING MATERIALS :
YACINTO colorsheet pre-coated galvanized sheets:
(0.4mm x 0.81mm x 244m 34 | Sheet
0.4mm x 0.8mm x 3.05m 48 | Sheet
04mm x 0.8mm x 3.665 37 | Sheet
Plain Gl ridge roll and hip rolls, Ga. 0.4mm
450mm x 2.44 (18" x 8) 35 | Piece
Plain Gl fascia flashing, Ga, 25,
450mm x 2.44m (18° x 8) 11 | Piece
Plain Gi wall lashing and straps, Ga. 0.4mm 6 | Sheet
810mm x 2.44m (32 x 8) 7 | Kio
Sef-diling rooting screws 12mm x 6.00 meters 10 | Kilo
VULCASEAL sealant 3 | +Can
PVC Pipes downspout, Schedule 40, MOLDEX Gray
75mrm dia x 3.00m (3" dia x 10) 20 | Piece
PVC Elbows, 75mm dia (3° dia), Sched. 40 32 | Piece
PVC Tees, 75mm dia (3" dia), Sched. 40 4 | Piece
PVC Solvent Cement 20 | oe
5. PLUMBING PIPES AND FITTINGS
Sanitary pipes and fitings. MOLDEX SANIMOLD
Pipes - 100mm dia x.3.00m (4° dia x 10°) 5 | Piece
Pipes - 75mm dia x 3.00m(3" dia x 10}) 4 | Piece
Pipes - SOrmm dia x 3,00m(2" dia x 10} 7 | Piece
Sanitary Tee - 100mm dia (4" aia) 5 | Piece
Sanitary Tee- 75mm dia (3" aia) 3. | Piece
Sanitary Tee- SOmm dia (2" dia) 4 | Piece
Elbow, 90 deg - 100rrm dia (4° dia) 6 | Piece
Elbow, 90 deg- 76mm dia (3° dia) 8 | Piece
Elbow, 90 deg- 50mm dia (2° dia) 2 | Piece
Sanitary Wye - 100mm dia (4” da) 3. | Piece
Reducer Wye- 50mm cia x 100mm dia (2" dia x 4" dia) 2 | Piece
Prepared by. Approved:
"ARCHITECTIENGINEER ‘OWNER,
DATE DATE
AS?
ESTIMATING BILL OF MATERIALS - TagayunProject Page 4
Owmerts =
Location
BILL OF MATERIALS
5 Unit Total
Description of Material Quantity | unt | ont et
Reducer Viye -7Smm fa x 100mm ca (3 bax ba) 4 | Plece
Reducer Tee - 50mm da x 100mm da (2' ca x 4a) 5 | Piece
Reducer Tee - 75mm da x 100mm da (3" ax 4" da) 3 | rece
Reducer Coupling - 75mm cfax 100mm cia
(3 dax4' da) 2 | Pee
‘Coupting- 100mm cia (a" ea) 5 | Pee
Coupling - 75mm da (3" da) 3 | Plece
Coupling - 50mm da (2" da) 4 | Piece
Floor Drain Trap - 50mm cba (Z" cia) 5 | Piece
Clean-out wptug- 100mm da (4° da) 2 | Pece
Glean-out wiplug 50mm da (2" da) 2 | Pece
Concrete Drainage pipes:
‘00mm cha x 1,00 meter 8 | Piece
450mm ca x 1.00 meter 12 | Piece
‘Water meter, GREAT VOLUME brand 1 | Plece
Gate valve, Bronze frish, GREAT VOLUME brand 1 | Set
Faucet, Bronze frish, GREAT VOLUME brand 5 | Prece
Hose bibbs, chrome frish, GREAT VOLUME brand 2 | Pece
Gi pipes andifiting heduie 40,
Pipe - 12mm cia x 6.00m (1/2" ba x 20)
Pipe - 19mm cla x 6:00m (3/4" da x 20)
‘bow, 80 deg 198mm da (3/4 ca)
bow, 90 deg - 12mm da (1/2" da)
‘Street Bl- 12mm da (172" da)
Tapped Tee - 19mm cha (3/4" da)
Tapped Tee - 12mm da (1Z" da)
Reducer Tee - 18mm da x Tamm da (3/4 da x 12" da)
Reducer Ell- 19mm da x 12mm da (3/4" bax 172" da)
Reducer Bll - 12mm da x 10mm ca (1/2' a x 38" da)
‘Nipple - 12mm fa x 150mm (1/2" ha x 6°)
Courling - 19mm a (34 ca)
Coupling - 12mm da (172' a)
Union - 19mm da (3/4" da)
ONNSvOURHaNNAROD
2
8
Union - 12mm da (1/2" da) Piece
‘Teflon Tape, Big Rall
Prepared by: Approved:
"ARCHITECTIENGINEER OWNER
DATE DATE
ASBProject Pages
Owners
Location
BILL OF MATERIALS
7 Unit Total
Description of Material Quantity | Unit | cos Pair
6 PLUMBING FIXTURES AND ACCESSORIES P.
‘Water closet, SANIWARES Ventura PF 2400 2 Set
Lavatory, SANIWARES Ventura PF 1002 2 Set
Kitchen sink, NORTHERN HILL Lavelle 4221 RA 1 Set
Laundry tray, NORTHERN HILL Lawndale -244RA, 1 Set
‘Soap holder, C.W. Tan Mfg. Model ACOO4 3 Set
Toilet paper holder, C.W. Tan Mig, Model ACOO1 2 Set
Towel holder, SANIWARES PF 3800 3 Set
‘Shower head, valve and faucet 2 Set
Floor Drain, Chrome-plated, 100mm x 100mm 5 | Piece
7. CEILINGS, PARTITIONS, FLOORS IP.
AND OTHER INTERIOR WORKS:
Wood flooring, KD Tanguile, T&S
165 Pes, 25mm.x 100mm x 4.80m (1"x 4" x 161) 347 | Batt
Baseboards, KD Tanquile, S45
25 Pes, 25mm x 100mm x 3,60m (1"x 4" x 12') 100 | Bde
Celling joists, hangers and studs, Tanquile, Rough
200 Pes. 50mm x 60mm x 4.80m (2"x 2"x 16°) 1067 | Bd
Ceiling and partition boards:
‘mmx 1.20mx 2.40m Class A plywood 80 | Sheet
Sem x 1.20m x 2.40m plywood 10 | Sheet
419mm x 1.20m x 2.40m Plyboard for Cabinets 15 | Sheet
Shelves for cabinets and closets, KD Tanquile, S4S,
12 Pes.25mmx 300m x 3:60m (1"x 12" x 12) 144 | Bat
‘Quarter, “C" mouldings, KD Tanquile, 360m (12) 95 | Piece
Marble floor tiles, 300mm x 600mm (12" x 24") 120 | Piece
KENT Vinyl floor tiles, 300mm x 300mm (12"x 12") 750 | Piece
RUGBY glue for vinyl tiles 4 | aLcan
Toilet-Bathroom tiles and mouldings, MARIWASA.
Unglazed floor tiles, 108 x 108mm 750 | Piece
Glazed wall tiles, 108 x 108mm (4-1/4" x 4-1/4") 2500 | Peice
Tile mouldings (Assorted) 150 | Peice
PRIME white cement 3 | Bag
Prepared by: Approved:
ARCHITECTIENGINEER. ‘OWNER
DATE DATE
Aso
ESTIMATING BILL OF MATERIALS - TagayunProject Page 6
Owners
Location
BILL OF MATERIALS
4
: Unit Total
Description of Material Quantity | unit | ont paar
8. ELECTRICAL MATERIALS P.
Entrance Cap - 25mm da (1" da) 1 | Piece
Rigid steel conduit - 25mm cia x 3.00%,
‘Schedule 40 4 | Piece
Conduit lamp for 25mm RSC 5 | Piece
‘Metal locknut with bushing - 25mm dia 3 | Pair
‘Automatic circuit breaker, 100A main switch,
with 6 branch circuits, EVER brand 1 | set
RSC elbow - 90° long bend, 25mm dia 5 | Piece
RSC coupling - 25mm da 3. | Piece
NELTEX Power Guard electric wire protection, Orange:
UPVC Pipe, 20mm céax 300m, Schedule 40 90 | Piece
UPVC Coupling - 20mm cia 70 | Piece
UPVC Adaptor wilocknut and bushing, 20mm da 40 | Piece
UPVC Range pipe, 25mm dia x 3.00m 2 | Piece
UPVC Adaptor wflocknut and bushing, 025mm dia 4 | Par
UPVC Utility boxes, 38mm x 100mm x 54mm 55 | Piece
‘UPVC Junction boxes, 100mm x 100mm x 54mm 40 | Piece
‘Solvent cement 100 | cc
Electric Wre, PHELPS-DODGE, THW.
Electric wire, (3.5mm) 2 Box
We for range, (5.5mm?) 5 | Meter
Wr for range, (8 mm?) S| Meter
Wire for service entrance, (22mm?) 15 | Meter
‘We for service entrance, (14mm?) 30 | Meter
Porcelain lamp receptacle - 10mm da 45 | Piece
‘Whing Devices, EAGLE brand,
Pate assembly for single-gang switch 12 | set
Plate assembly for two-gang switch 8 | set
Piate assembly for three-gang switch 2 | se
Wal switch module, 5A, 250V, AC 30 | Piece
Three-way switch module, 54, 250V, AC 8 | Piece
Duplex convenience outlets 10 | Piece
Range outlet with cover pate, prongs 1 | set
Fricton/Ptastic tape, Big size 12 | Rol
Prepared by Approved:
ARCHITECTENGINEER OWNER
DATE DATE
A60Ast
Project
Owners
Page 7
BILL OF MATERIALS
5 a unit Total
Description of Material Quantity | Unit | Coup et
9 DOORS, WINDOWS AND ACCESSIRIESS P.
(0-1) ENTRANCE DOOR
Tene x 200mm (3" x
YAKAL door head and
jambs 1 | Piece
§ <4mnm (1-3/4) thick
S NARRA panel door 1 | Piece
WEISER Entrance lock
sat, colonial design 1 | set
9-172" x 4" BF ball bearing
template hinges 3. | Piece
{0-2} SEAVICE DOORS
ene x 150mm (3" x6")
YAKAL door head and
jambs 2 | Piece
g ‘4enm (1-3/4) thick
“ Kilndried TANGUILE
panel door 2 | Piece
WEISER Service entrance
oor lookset 2 | se
BF ball bear
template hinges 6 | Piece
Prepared by: Approved:
"ARCHITECTENGINEER OWNER
DATE DATE
ESTIMATING BILL OF MATERIALS - TagayunPage 8
ae
Brie
mer
BILL OF MATERIALS
a re
Description of Material Quantity Unit Cost Cost
saree a tee
:
|| FASEB @
8| S 7
i
(345) (SqFt)
Tal dallelceactint an
oe
Alumiqum jalousie hardware, single control 6 Pair
‘Smm x 100mm x 50m Smoked glass slats 6 Piece
poet le
ARCHITECT/ENGINEER ‘OWNER
DATE DATE
A62Project Page 9
Owneris
Location
BILL OF MATERIALS
: a) unit Total
Description of Material Quantity | Unit
10. PAINTING MATERIALS P
(DUTCH BOY or BOYSEN Products)
Flatwall Ename! Paint, White 2 | 16LCan
Quick Drying Enamel, Vite 2 | 16LCan
Exterior Wood Primer and Sealer 1 | 16.Can
Interior Wood Primer and Sealer 1 | 46. can
Oi Tinting Colors: Green’ 2 | 1Lcan
Yellow 2 | 1Lcan
Brown 2 | ALcan
Black 2 | tLcan
Primer Thinner 2 | can
Acrylic Serr-gloss Latex Paint 2 | t6Lcan
Concrete Neutralizer 2 | t6LCan
‘Actylic Concrete Primer Sealer 3. | can
Latex Putty 4 | 46.can
Acrylic Tinting Colors : Brown 2 | atcan
Yellow 1 | aLcan
Clear Gloss Lacquer 2 | aLcan
Dead Fiat Lacquer 2 | acan
Lacquer Primer Surfacer 1 | aUcan
Wood Filler Paste 2 | Alcan
Lacquer Thinner 3 | Alcan
Red Lead Primer 3 | acan
Portland Cement Roof Paint 3 | aLcen
Sandpapers (Assorted) 2 Doz.
Cleaning Rags 2 ‘elo
41, MISCELLANEOUS MATERIALS ( Lump Sum Estimates) P
(Cabinet door hardware, wrought
iron giles, screens, star materials, etc.)
Prepared by Approved:
ARCHITECTIENGINEER OWNER
DATE DATE
A63
ESTIMATING BILL OF MATERIALS - TagayunPage 10
‘SUMMARY COST ESTIMATES FOR MATERIALS, LABOR
AND OTHER CONSTRUCTION EXPENSES:
‘A ESTIMATED COST OF MATERIALS (Fromthe Bill of Materials) .... P
1, FOUNDATION, CONCRETE COLUMNS, BEAMS
AND CONCRETE HOLLOW BLOCKS WALLS P 121,680.00
FLOOR FRAMING Pp
ROOF FRAMINGS. Pp
ROOFING MATERIALS P
PLUMBING PIPES AND FITTINGS Pp
PLUMBING FIXTURES AND ACCESSORIES P
CEILINGS, PARTITIONS, FLOORS
AND OTHER INTERIOR WORKS.
ELECTRICAL MATERIALS
DOORS, WINDOWS AND ACCESSORIES
PAINTING MATERIALS
(DUTCH BOY or BOYSEN Products) Pp
11, MISCELLANEOUS MATERIALS P
NOwaen
vv
B. ESTIMATED COST OF LABOR (Including Supervision Fees)
C. ESTIMATED EXPENSES FOR CONTINGENCIES Pp
ESTIMATED TOTAL DIRECT COST Pp
The above items comprise the estimated expenses for materials and labor applied
directly in the construction of the building. If the work would be undertaken by a contractor,
the indirect costs shown below should also be taken into account in projecting the total
funding required for the completion of the project.
D. CONTRACTOR'S PROFIT (Including Overhead) Pp
E. CONTRACTOR'S TAX P
ESTIMATED TOTAL DIRECT COST P
ESTIMATED TOTAL DIRECT COST
Prepared by. Approved:
"ARCHITECTIENGINEER OWNER
DATE DATE
A64