Professional Documents
Culture Documents
8.om. Chapter 8-Mrp-Jit
8.om. Chapter 8-Mrp-Jit
JUST-IN-TIME (JIT )
2
LEARNING OUTCOME
After completing this chapter, you should be able to:
• Introduce JIT
3
INTRODUCTION
Evolution of ERP
2000s
1990s Extended
Enterprise ERP
1980s resource
Manufacturing planning
resource (ERP)
1970s planning
Material (MRPII)
requirements
planning
1960s (MRP)
Inventory
Control
Packages
4
INTRODUCTION
• Resource
Planning for
Manufacturing
5
AN OVERVIEW OF MRP
• Material requirements planning (MRP) A methodology that translates master schedu
requirements for end items into time-phased requirements for subassemblie
components, and raw materials
6
AN OVERVIEW OF MRP
• MRP is designed to answer three questions:
✓ What is needed?
Production schedule
✓ How much is needed?
✓ And when is it needed? Inventory status
MRP
Purchasing
7
Independent and Dependent demand
• Dependent demand: Demand for items that are subassemblies or component parts
to be used in the production of finished goods.
8
AN OVERVIEW OF MRP
• MRP inputs, processing, and outputs
9
MRP INPUTS
• The Master Schedule
✓ Which end items are to be produced
✓ When these are needed
✓ What quantities
The master schedule cover the stacked or cumulative lead time necessary to produce
the end items
• Bill Of Materials (BOM)
✓ A listing of all of the raw materials, parts, subassemblies, and assemblies
needed to produce one unit of a product.
• Inventories
✓ Includes information on the status of each item by time period.
10
The Bill of Materials
• Bill Of Materials (BOM): A listing of
all of the raw materials, parts,
subassemblies, and assemblies
needed to produce one unit of a
product.
• Product Structure Tree: A visual
depiction of the requirements in a
bill of materials, where all
components are listed by levels.
11
The Bill of Materials
A product structure tree for item X
12
The Bill of Materials
A product structure tree for item X
Example 1
• Determine the quantities of B, C, D,
E, and F needed to assemble 10 Xs?
• Determine the quantities of these
components that will be required to
assemble 10 Xs, taking into account
the quantities on hand (i.e., in
inventory) of various components:
13
The Bill of Materials
Example 1
14
The Bill of Materials
Example 1
15
MRP PROCESSING
Assembly time chart
16
MRP PROCESSING
17
MRP PROCESSING
• Gross Requirements Total expected demand for an item or raw material in a time
period.
• Scheduled Receipts Open orders scheduled to arrive from vendors or elsewhere
in the pipeline.
• Projected On Hand Expected amount of inventory that will be on hand at the
beginning of each time period.
• Net Requirements The actual amount needed in each time period.
• Planned-order Receipts Quantity expected to be received by the beginning of the
period in which it is shown.
• Planned-order Releases Planned amount to order in each time period; planned
order receipts offset by lead time.
18
MRP PROCESSING
Project inventory on-hand for current period = Planned receipts for previous period −
Net requirements for previous period + Scheduled receipts for current period
Net requirements for current period = Gross requirements for current period −
Projected on-hand inventory for current period
19
MRP PROCESSING
Example 2
A firm that produces wood shutters and bookcases has received two orders for
shutters: one for 100 shutters and one for 150 shutters. The 100-unit order is due for
delivery at the start of week 4 of the current schedule, and the 150-unit order is due
for delivery at the start of week 8. Each shutter consists of two frames and four
slatted wood sections. The wood sections are made by the firm, and fabrication takes
one week. The frames are ordered, and lead time is two weeks. Assembly of the
shutters requires one week. There is a scheduled receipt of 70 wood sections in (i.e.,
at the beginning of) week 1. Determine the size and timing of planned-order releases
necessary to meet delivery requirements under each of these conditions:
1. Lot-for-lot ordering (i.e., planned-order release equal to net requirements).
2. Lot-size ordering with a lot size of 320 units for frames and 70 units for wood
sections
20
MRP PROCESSING
Example
21
MRP PROCESSING
Example 2
22
MRP PROCESSING
Example 2
MRP schedule with lot sizes for
components
23
MRP OUTPUTS
Primary Reports.
• Planned Orders Schedule indicating the amount and timing of future orders.
• Order Releases Authorization for the execution of planned orders.
• Changes Revisions of due dates or order quantities, or cancellations of orders
Secondary Reports.
• Performance-control Reports Evaluation of system operation, including deviations
from plans and cost information
• Planning Reports Data useful for assessing future material requirements.
• Exception Reports Data on any major discrepancies encountered.
24
OTHER CONSIDERATIONS
• Safety Stock
• Lot Sizing
✓ Lot-for-Lot Ordering.
✓ Economic Order Quantity Model.
✓ Fixed-Period Ordering
25
MRP II
• Manufacturing Resources Planning (MRP II)
Expanded approach to production resource
planning, involving other areas of a firm in the
planning process and enabling capacity
requirements planning.
26
CAPACITY REQUIREMENTS PLANNING
• Capacity Requirements Planning The process of determining short-range capacity
requirements.
• Time Fences Series of time intervals during which order changes are allowed or
restricted; the nearest fence is most restrictive to change, the farthest is least
restrictive.
27
REMIND
28
REMIND
29
REMIND
Example: Given the following information, compute the efficiency and the utilization
of the vehicle repair department:
• Design capacity = 50 trucks per day
• Effective capacity = 40 trucks per day
• Actual output = 36 trucks per day
30
CAPACITY REQUIREMENTS PLANNING
• Example 3:
• Production schedule of Minh Thanh company with 1.5 liter bottles in the next 5
months:
Month
1 2 3 4 5
Number of 100.000 125.000 100.000 175.000 150.000
bottles
• Capacity of company:
✓ Labor: 150.000 bottles/month
✓ Machine: 200.000 bottles/month
31
CAPACITY REQUIREMENTS PLANNING
• Example 3:
Month Labor utilization Machine utilization
32
CAPACITY REQUIREMENTS PLANNING
• Example 3:
• Option 1: April: overtime to make 25,000 more bottles
Month
1 2 3 4 5
Number of 100.000 125.000 125.000 150.000 150.000
bottles
33
JUST – IN – TIME
(JIT)
JIT AND LEAN OPERATIONS
• Lean operation A flexible system that uses minimal resources and produces high
quality goods or services.
• Lean systems are sometimes referred to as just-in-time (JIT) systems owing to
their highly coordinated activities and delivery of goods that occur just as they are
needed
35
JIT SYSTEM
• Flexible resources- Tài nguyên (nguồn lực) linh động-
• Cellular layout- Mặt bằng theo ô – nhóm -
• Pull Systems- Hệ thống kéo
• Kanban Control system- Hệ thống kiểm soát - Kanban
• Small batch production- Sản xuất loạt nhỏ
• Single-Minute Exchange of Die- Điều chỉnh nhanh - SMED
• Sản xuất đều đặn
• Quality Improvement- Cải tiến chất lượng
• Close Vendor Relationships - Quan hệ với nhà cung cấp
• Continuous Improvement- Cải tiến liên tục
36
JIT SYSTEM
37
JIT SYSTEM
HM
Ghi chú: CN 2
G
S = Máy cưa (Saw)
L = máy tiện (Lathe) L
HM = Máy Bào trục ngang
(Horizontal milling Final
inspectio
machine) n
VM = Máy bào trục đứng
(Vertical milling Finishe
machine) S CN 1 d part
38
JIT SYSTEM
3.Pull Systems- Hệ thống kéo
39
JIT SYSTEM
3.Pull Systems- Hệ thống kéo
40
JIT SYSTEM
4.Kanban Control system- Hệ thống kiểm soát – Kanban
41
JIT SYSTEM
5. Small batch production- Sản xuất loạt nhỏ
• Ưu điểm
✓ Di chuyển quá trình lại gần nhau
✓ Đơn giản việc vận chuyển
✓ Dễ phát hiện các vấn đề chất lượng
✓ Tồn kho thấp
42
JIT SYSTEM
6. Single-Minute Exchange of Die- Điều chỉnh nhanh - SMED
• Điều chỉnh trong: tiến hành khi máy ngừng
• Điều chỉnh ngoài: tiến hành khi máy đang chạy
• Nguyên tắc:
• Tách riêng điều chỉnh trong và điều chỉnh ngoài
• Chuyển điều chỉnh trong thành điều chỉnh ngoài
• Sắp xếp hợp lý công việc điều chỉnh
• Hiệu chỉnh song song hoặc loại bỏ hoàn toàn (chuẩn hóa)
43
JIT SYSTEM
6. Single-Minute Exchange of Die- Điều chỉnh nhanh - SMED
44
JIT SYSTEM
7. Sản xuất đều đặn
• Giảm biến động sản xuất thông qua dự báo
• San bằng nhu cầu
45
JIT SYSTEM
8.Quality Improvement- Cải tiến chất lượng
• Sai hỏng = 0
46
JIT SYSTEM
9. Close Vendor Relationships - Quan hệ với nhà cung cấp
• Có 1 mạng lưới nhà cung cấp đáng tin cậy
47
JIT SYSTEM
10. Continuous Improvement- Cải tiến liên tục
• Luôn quyết tâm cải tiến, không nên thỏa mãn với hiện trạng
48
JIT SYSTEM
Các lợi ích của JIT
• Tăng tính linh hoạt, đáp ứng kịp thời nhu cầu KH
• Đơn giản việc lập kế hoạch và kiểm tra các hoạt động