Proposed Sections for AMP 2022-23 (

Revised Cost as
Remaining Recommended Cost as per HDM-IV Cost per km Coring Thickness Cost as per Estiamte Engineer Cost
S. No. Team Year Zone Region Road name Section Work Description Location C/way Type Length Previous AMP's History Remaining Section
Length (km) Length (Km) Section (Millions)
Coring
(Millions)
per recommended Remarks Recheked Status Revised Work Description Stragy Applied Recommended Section Recommended Length
(Cm)
Unit Rate
recommended length (CSR-2022) AADT Remarks
length

KM 172 = 7 cm
KM 182 = 7cm
50 mm Mill & Fill Deep Patching 167+000-170+000
1 A 2023 North Zone Kpk N-45 N45-N Nowshera - Chitral - 06 (167+000 - 231+000) 50 mm Overlay with Deep Patching Dir- Chitral Single 65 - 167+000 - 231+000 64 64 754.668 11.32 724.48 50 mm Mill & Fill Deep Patching 41 KM 192 = 7cm 14.363 588.883 #REF! 14987
(25%) 173+000 - 211+000
KM 202 = 7cm
KM 209 = 7cm

3 A 2023 North Zone Kpk N-140 N140 Chitral - Shandur - 01 (01+000 - 76+000) 50 mm Overlay with Deep Patching Chitral - Booni Single 76 - 1+000 - 76+000 76 76 581.239 11.32 860.32 Under Project? No maintenance required No maintenance 0 - 0 0 4974
Rehabilitation of Bahrain -
Kalam Road N-95
Road in good condition, some repair
(Bahrain - Chimgarh) KM 54 = 15 cm
5 A 2023 North Zone Kpk N-95 N95 Chakdara - Kalam - 03 (49+000 - 83+000) 50 mm Overlay with Deep Patching Manglor - Madyan Single 35 - 49+000 - 83+000 34 34 488.508 11.32 384.88 works needed that can be handled in No maintenance 0 0 0 1190
(Chimgarh - Asrit)
Routine maintenance KM 64 = 16 cm
(Asrit - Pashmal )
(Pashmal - Kalam )
Balochistan KM 507 = 17 cm
6 A 2023 West Zone N-25 N25 Karachi - Chaman - 18 (501+000 - 529+000) 50 mm Overlay with Deep Patching Surab - Kalat Single 29 515+000 - 529+000 (AMP 2019-20) 501+000 - 515+000 14 14 449.93 11.32 158.48 Under Project? 50 mm Mill & Fill Deep Patching 50 mm Mill & Fill Deep (25%) 501+000 - 515+000 14 18.862 264.068 245.0034171 8563
south km 514 = 12 cm

KM 1190 = 21 cm
130 mm Mill & Fill Overlay with Deep 130 mm Mill & Fill Overlay with Deep KM 1200 = 14 cm
9 A 2023 North Zone Kpk N-55 N55-N Kotri - Peshawar - 26 (1176+000 - 1222+000) Lachi - Peshawar Dual 47 - 1176+000 - 1222+000 46 46 1214.881 23.73 1091.58 Status of dualization Rehabilitation 1187+000 - 1214+000 27 33.721 910.467 867.12647715 7440
Patching Patching KM 1210 = 15 cm
KM 1220 = 21 cm

Balochistan 130 mm Mill & Fill Overlay with Deep 450+000 - 460+000 130 mm Mill & Fill Overlay with Deep 130 mm Mill & Fill Overlay with 470+000 -471+000 KM 455 = 18 cm
11 A 2023 West Zone N-25 N25 Karachi - Chaman - 16 (450+000 - 480+000) Lakhorain - Nighar Single 31 460+000 - 470+000 (AMP 2020-21) 20 20 801.304 22.2 444 Under Project? 4 29.588 118.352 110.53541084 8563
south Patching 470+000 - 480+000 Patching Deep Patching (25%) 477+000 - 480+000 KM 475 = 14 cm

Balochistan 130 mm Mill & Fill Overlay with Deep 130 mm Mill & Fill Overlay with Deep 130 mm Mill & Fill Overlay with 430+000 - 431+000 KM 436 = 13 cm
12 A 2023 West Zone N-25 N25 Karachi - Chaman - 15 (430+000 - 449+000) -be - lakhorain Single 20 - 430+000 - 449+000 19 19 516.971 22.2 421.8 Under Project? 17 28.98 492.66 472.46523097 8563
south Patching Patching Deep Patching (20%) 433+000 - 449+000 KM 446 = 14 cm

KM 215 = 11 cm
215+000 - 217+000 KM 226 = 13 cm
Balochistan 211+000 - 215+000 (AMP 2019-20) 215+000 - 217+000 Under Project? 130 mm Mill & Fill Overlay with Deep 130 mm Mill & Fill Overlay with
13 A 2023 West Zone N-25 N25 Karachi - Chaman - 09 (211+000 - 261+000) 50 mm Overlay with Deep Patching Las Bela - Khuzdar Single 51 41 41 791.257 11.32 464.12 233+000 - 242+000 18 KM 236 = 7 cm 28.67 516.06 492.165055522 5719
south 217+000 - 222+000 (AMP 2019-20) 222+000 - 261+000 Re-alignment? Patching Deep Patching (15%)
253+000 - 261+000 KM 246 = 13 cm
KM 256 = 15 cm
Construction of Burhan-
Havelian Expressway E-35 No maintenance required, this road is
17 A 2023 North Zone Northern Areas N-35 N35 Hassanabdal - Khunjrab - 08 (298+000 - 350+000) TST (Surfacing) Dasu - Shangrila Chilas Single 106 298+000 - 350+000 52 52 671.228 0
(Sarai Saleh to Simlaila) under project
- TST (Surfacing) (35%) Under Project 0 - 0 0 3318
Package-III

No maintenance required, this road is


18 A 2023 North Zone Gilgit Baltistan N-35 N35 Hassanabdal - Khunjrab - 08 (350+000 - 403+000) TST (Surfacing) Dasu - Shangrila Chilas Single 360+000 - 404+000 (AMP 2018-19) 350+000 - 360+000 10 10 0 Need overlay?
under project - TST (Surfacing) (35%) Under Project 0 - 0 0 3318

KM 318 = 15 cm
KM 328 = 14 cm
KM 338 = 15 cm
KM 348 = 13 cm
Widening and Strengthening KM 358 = 13.5 cm
Balochistan 286+000 - 312+000 (AMP 2018-19) 312+000 - 361+000 of National Highway N-70 Strategy is changed as per project level analysis 130 mm Mill & Fill Overlay with Deep 130 mm Mill & Fill Overlay with 345+000 - 352+000 KM 370 = 13 cm
19 A 2023 West Zone N-70 N70-W Multan - Qillah Saifullah - 10 (286+000 - 433+000) 50 mm Overlay with Deep Patching Mekhtar - Qilla Safiullah Single 148 116.3 116.3 2296.196 11.32 1316.516
Rakhi-Gaaj-Bewata Section comments
74.3 28.67 2130.181 2063.1620554757 7555
North 361+000 - 365+700 (AMP 2018-19) 365+700 - 433+000 Patching Deep Patching (15%) 365+700 - 433+000 KM 380 = 13 cm
Package-IA KM 390 = 13.5 cm
KM 400 = 14.5 cm
KM 410 = 14 cm
KM 420 = 15 cm
KM 430 = 17 cm

Balochistan 97+000 - 114+000 Cannot take 1 km for


20 A 2023 West Zone N-25 N25 Karachi - Chaman - 06 (97+000 - 120+000) 50 mm Overlay with Deep Patching Sonmiani - uthal Single 24 114+000 - 119+000 (AMP 2019-20) 18 18 372.356 11.32 203.76 Cannot take 1 km for maintenance 50 mm Mill & Fill Deep Patching 0 KM 120 = 16 cm 0 0 5719
south 119+000 - 120+000 maintenance

Balochistan 50 mm Mill & Fill Deep Patching 283+000 - 285+000 KM 274 = 12 cm


21 A 2023 West Zone N-25 N25 Karachi - Chaman - 11 (271+000 - 285+000) 50 mm Overlay with Deep Patching Badari - Waheer Single 15 - 271+000 - 285+000 14 14 232.723 11.32 158.48 50 mm Mill & Fill Deep Patching 8 16.24 129.92 139.17405339 5719
south (25%) 276+000-282+000 KM 284 = 11 cm

Balochistan 50 mm Mill & Fill Deep Patching


22 A 2023 West Zone N-10 N10-MCH Liyari (Uthal) - Gwadar - 02 (07+000 - 15+000) 50 mm Overlay with Deep Patching Uthal - Kund Malir Single 9 - 7+000 - 15+000 8 8 149.634 11.32 90.56 Any SM Works? 50 mm Mill & Fill Deep Patching 07+000 - 15+000 8 5 Cm 14.363 114.904 81.85027454 1367
west (25%)

50 mm Mill & Fill Deep Patching


Balochistan (25%)
23 A 2023 West Zone
west
N-10 N10-MCH Liyari (Uthal) - Gwadar - 06 (42+000 - 61+000) 50 mm Overlay with Deep Patching Uthal - Kund Malir Single 20 42-50 (AMP 2020-21) 50+000 -61+000 11 11 310.297 11.32 124.52 NHA to meet decission to take 60+000 - 70+000 10 5 Cm 0 0 130.57970312 1367
(NHA Desison Required)

Balochistan 130 mm Mill & Fill Overlay with Deep Dhadar - Darazbent
24 A 2023 West Zone
North
N-65 N65-N Sukkur - Quetta - 05 (269+000 - 282+000)
Patching Recreation Bent
Single 14 280+000 - 282+000 (AMP 2017-18) 269+000 - 280+000 11 11 361.879 22.2 244.2 50 mm Mill & Fill Overlay 50 mm Mill & Fill Overlay 250+000 - 259+000 9 KM 275 = 20 cm 13.351 120.159 112.03166808 6041

404+000 - 407+000 (AMP 2018-19)


No maintenance required, this road is No maintenance required, this
26 A 2023 North Zone Gilgit Baltistan N-35 N35 Hassanabdal - Khunjrab - 09 (404+000 - 472+000) Structrual 130 mm Overlay Milling Basha - Gilgit Single 69 417+000 - 444+000 (AMP 17-19) 407+000 - 417+000 10 10 1700.236 21.67 216.7
under project - 0 - 0 0 3970
444+000 - 472+000 (AMP 2018-19) road is under project

33+000 - 35+000
Balochistan 32+000 - 39+000 50 mm Mill & Fill Deep Patching 36+000 - 39+000
28 A 2023 West Zone N-40 N40 Lakpass - Taftan - 02 (32+000 - 55+000) 50 mm Overlay with Deep Patching Abad Mustang - Kardagap Single 24 39+000 - 45+000 (AMP 2017-18) 17 17 372.356 11.32 192.44 50 mm Mill & Fill Deep Patching 13 Km 51+000 = 10 cm 16.244 211.172 183.20615905 4169
North 45+000 - 55+000 (25%) 45+000 - 51+000
53+000 - 55+000

29 A 2023 North Zone Kpk N-5 N5-N Karachi - Torkham - 29 (1716+000 - 1721+000) 50 mm Overlay with Deep Patching Jamrud - Salkani Dual 6 - 1716+000-1721+000 5 5 93.089 11.35 56.75 50 mm Mill & Fill Overlay 50 mm Mill & Fill Overlay 1718+000 - 1721+000 3 KM 1719 = 22 cm 13.351 40.053 46.1073495 12456
Proposed Sections for AMP 2022-23 (
Revised Cost as
Remaining Recommended Cost as per HDM-IV Cost per km Coring Thickness Cost as per Estiamte Engineer Cost
S. No. Team Year Zone Region Road name Section Work Description Location C/way Type Length Previous AMP's History Remaining Section
Length (km) Length (Km) Section (Millions)
Coring
(Millions)
per recommended Remarks Recheked Status Revised Work Description Stragy Applied Recommended Section Recommended Length
(Cm)
Unit Rate
recommended length (CSR-2022) AADT Remarks
length

KM 392 = 15 cm
KM 402 = 12 cm
KM 412 = 12 cm
30 A 2023 North Zone Kpk N-50 N50 Kuchlak - DI Khan - 07 (388+000 - 456+000) Structrual 130 mm Overlay Milling Dhana Sar - Daraban Single 69 - 388+000 - 456+000 68 68 2021.353 21.67 1473.56 130 mm Overlay Mill & Fill 130 mm Overlay Mill & Fill (30%) 428+000 - 441+000 15 KM 422 = 9 cm 29.588 443.82 622.98454912 5187
KM 432 = 6 cm
KM 442 = 8 cm
KM 452 = 11 cm

Balochistan 130 mm Mill & Fill Overlay with Deep 175+000 - 197+000 50 mm Mill & Fill Overlay with Deep 50 mm Mill & Fill Overlay with 175+000 - 189+000
31 A 2023 West Zone N-40 N40 Lakpass - Taftan - 07 (175+000 - 211+000) Nushkti - Dalbandin Single 37 197+000 - 200 (AMP 2020-21) 33 33 956.396 22.2 732.6 25 Km 199+000 = 5 Cm 14.363 359.075 314.25400514 4169
North Patching 200+000 - 211+000 Patching Deep Patching (25%) 200+000 - 211+000

56+000 - 58+000
56+000 - 72+000
Balochistan 130 mm Mill & Fill Overlay with Deep 72+000 - 77+000 (AMP 2020-21) 130 mm Mill & Fill Overlay with Deep 130 mm Mill & Fill Overlay with 109+000 - 112+000 51+000 = 10 Cm
32 A 2023 West Zone N-40 N40 Lakpass - Taftan - 03 (56+000 - 130+000) Mustag - Padag Single 75 77+000 - 101+000 67 67 1938.64 22.2 1487.4 23 29.588 680.524 586.65999918 4169
North Patching 101+000 - 103+000 (AMP 2018-19)
103+000 - 130+000 Patching Deep Patching (30%) 93+000 - 98+000 100+000 = 15 Cm
117+000 - 130+000

Rehabilitation of Bahrain - KM 6 = 13 cm
Road in good condition, some repair
Kalam Road N-95 KM 16 = 14 cm
35 A 2024 North Zone Kpk N-95 N95 Chakdara - Kalam - 01 (01+000 - 35+000) 50 mm Overlay with Deep Patching Paul Saokiae - Mingora Single 35 - 01+000 - 35+000 35 35 488.508 11.32 396.2 works needed that can be handled in -- -- -- 0 0 -- 31950
(Bahrain - Chimgarh) Routine maintenance KM 26 = 14 cm
(Chimgarh - Asrit) KM 34 = 12 cm
(Asrit - Pashmal )
(Pashmal - Kalam )

Rehabilitation of Bahrain - Road in good condition, some repair


KM 40 =14 cm
36 A 2024 North Zone Kpk N-95 N95 Chakdara - Kalam - 02 (36+000 - 48+000) 50 mm Overlay with Deep Patching Qambar - Charbagh Single 13 - 36+000 - 48+000 12 12 181.446 11.32 135.84 Kalam Road N-95 works needed that can be handled in -- -- -- 0 0 -- 43075
Routine maintenance KM 46 = 5cm
(Bahrain - Chimgarh)
(Chimgarh - Asrit)
(Asrit - Pashmal )
(Pashmal - Kalam )
KM 835 = 17 cm
831+000 - 840+000 KM 845 = 18 cm
840+000 - 855+000 (AMP 20-21)
855+000 - 868+000 KM 855 = 19 cm
45 A 2024 Central Zone Punjab South N-55 N55-N Kotri - Peshawar - 20 (831+000 - 886+000) 50 mm Overlay with Deep Patching Retra - Buzdar Single 56 868+000-872+000 (AMP 20-21) 831+000 - 886+000 55 55 868.831 11.32 622.6 Under Project? Rehabilitation Rehabilitation 29 33.721 977.909 1346.59558793 11082
875+000-882+000 (AMP 17-18) 872+000 - 875+000 KM 865 = 16 cm
882+000 - 886+000 KM 875 = 20 cm
KM 885 = 10 cm
KM 33 = 14 cm
0+000 - 16+000 (AMP 2017-18) 50 mm Mill & Fill with deep
46 A 2024 North Zone Kpk N-90 N90 Khuwazakhela - Besham - 02 (09+000 - 48+000) 50 mm Overlay with Deep Patching Khuwazakhela - Besham Single 40 31+000 - 48+000 17 17 620.593 11.32 192.44 50 mm Mill & Fill Overlay 31+000 - 48+000 17 KM 41 = 12 cm 18.862 320.654 242.41147763 1077
16+000 - 31+000 (AMP 2019-20) patch (20%)
KM 46 = 10 cm

Balochistan 400+000 - 410+000 (AMP 2019-20) 376+000 - 400+000 KNII No maintenance KM 382 = 14 cm
47 A 2024 West Zone N-25 N25 Karachi - Chaman - 14 (376+000 - 429+000) Structrual Overlay (150mm with Milling) Jinnah Can-nment - Anjira Single 54 24 24 1705.569 28.23 677.52
Shahid Take atleast 4-5 Km 50 mm Mill & Fill Overlay 130 mm Mill & Fill Overlay KM 395 - 400 5 27.755 138.775 129.01814805 9002
south 410+000 - 429+000 (AMP 2018-19) KM 396 = 13 cm

50 mm Mill & Fill Deep Patching


48 A 2024 North Zone Northern Areas N-35 N35 Hassanabdal - Khunjrab - 06 (166+000 - 184+000) 50 mm Overlay with Deep Patching Battagram - Thakot Single 19 - 166+000 - 184+000 18 18 228.863 11.32 203.76 50 mm Mill & Fill Deep Patching 166+000 - 169+000 3 KM 166 = 5 cm 14.49 43.47 30.54429283 3490
(40%)

50 mm Mill & Fill Deep Patching


50 A 2025 North Zone Kpk N-45 N45-N Nowshera - Chitral - 08 (240+000 - 249+000) 50 mm Overlay with Deep Patching Mirkhani - Darosh Single 10 - 240+000 - 249+000 9 9 114.718 11.32 101.88 50 mm Mill & Fill Deep Patching 240+000 - 249+000 9 5 Cm 14.36 129.24 99.58162914 16701
(25%)

KM 1001 = 15 cm
KM 1011 = 15 cm
KM 1021 = 15 cm
996+000 - 1048+645 KM 1031 = 15 cm
Masha Mansoor Lakki Marwat 1048+645 - 1058+000 (AMP 2019-20)
65 A 2025 North Zone Kpk N-55 N55-N Kotri - Peshawar - 23 (996+000 - 1084+000) 50 mm Overlay with Deep Patching
-Mitha Khel Karak
Dual 89
1080+000 - 1084+000 (AMP 2018-19)
1058+000 - 1080+000 74.645 74.645 1380.82 11.35 847.22075 Under Project? Rehabilitation Rehabilitation 996+000 - 1040+500 44.5 KM 1041 = 8 cm 33.721 1500.5845 1379.59092829 6348
KM 1045 = 15 cm
KM 1063 = 20 cm
KM 1073 = 20 cm
KM 1080 = 27cm
Road in good condition, some repair
KM 33 = 17 cm
66 A 2025 North Zone Kpk N-45 N45-N Nowshera - Chitral - 02 (30+000 - 45+000) 30cm GB + 13 cm AC REHAB Janday - Shergarh Dual 16 38+000 - 45+000 (AMP 2017-18) 30+000 - 38+000 8 8 510.508 32.66 261.28 works needed that can be handled in 0 27.592032915 0 20783
KM 37=17 cm
Routine maintenance

Cost based on HDM-IV


50 mm Mill & Fill Deep Patching
67 A 2025 North Zone Kpk N-45 N45-N Nowshera - Chitral - 09 (250+000 - 298+000) 50 mm Overlay with Deep Patching Naghar - Chitral Single 49 - 250+000 - 259+000 9 9 562.119 11.32 101.88 To be surveyed 50 mm Mill & Fill Deep Patching 250+000 - 259+000 9 - 14.363 129.267 106.31759634 8020 Tickness assumed 5
(25%)
cm.

286+000 - 291+000
KM 288 = 15 cm
294+000 - 295+000
KM 297 = 15 cm
296+000 - 297+000
286+000 - 291+000 KM 307 = 11 cm
Balochistan Ornach water fall - Jinnah 291+000 - 292+000 (AMP 2018-19) 130 mm Mill & Fill Overlay with Deep 130 mm Mill & Fill Overlay with 304+000 - 305+000
70 A 2025 West Zone N-25 N25 Karachi - Chaman - 12 (286+000 - 365+000) 30cm GB + 13 cm AC REHAB Single 80 292+000 - 330+000 63 63 2552.541 31.06 1956.78 Dualization project ? 40 KM 317 = 13 cm 29.588 1183.52 1127.99163663 6303
south cantonment 330+000 - 345+000 (AMP 2020-21)
345+000 - 365+000 Patching Deep Patching (30%) 314+000 - 330+000
KM 327 = 13 cm
345+000-349+000
KM 350 = 15 cm
351+000-354+000
KM 360 = 13 cm
357+000-364+000

Being realigned due to Naran Dam


72 A 2025 North Zone Northern Areas N-15 N15 Mansehra - Chilas - 03 (105+000 - 111+000) 30cm GB + 13 cm AC REHAB Kaghan - Naran Single 7 105+000 - 107+000 (AMP 2021-22) 107+000 - 111+000 4 4 223.347 31.06 124.24 No maintenance required 0 KM 30 = 8 cm 0 0 11015
(NO WORK RECOMMENDED)

74 A 2025 North Zone Kpk N-45 N45-N Nowshera - Chitral - 07 (232+000 - 239+000) 100 mm Asphaltic Overlay Ashret Gol - MirKhani Single 8 - 232+000 - 239+000 7 7 119.281 20.88 146.16 No work is required, Under project UNDER PROJECT 0 - 0 0 16701

KM 288 = 10 cm
Balochistan 50 mm Mill & Fill Deep Patching 290+000-302+000 KM 298 = 5 cm
75 A 2025 West Zone N-65 N65-N Sukkur - Quetta - 06 (283+000 - 324+000) 30cm GB + 13 cm AC REHAB Dhadar - Mach Single 42 - 283+000 - 324+000 41 41 1340.084 31.06 1273.46 50 mm Mill & Fill Deep Patching 21 15.138 317.898 326.96775741 6651
North (20%) 322+000 - 315+000 KM 308 = 7 cm
KM 318 = 7 cm
KM 1725 = 8cm
KM 1734 = 26 cm
77 A 2025 North Zone Kpk N-5 N5-N Karachi - Torkham - 30 (1722+000 - 1755+000) 30cm GB + 13 cm AC REHAB Jamrud - -rkham Dual 34 - 1722+000 - 1755+000 33 33 1084.83 32.66 1077.78 50 mm Mill & Fill Overlay 50 mm Mill & Fill Overlay 1721+000 -1724+000 3 13.351 40.053 45.84405589 13893
KM 1744 = 16 cm
KM 1751 = 16 cm

Balochistan
78 A 2025 West Zone
west
N-10 N10-MCH Jiwani - Iran Border - 01 (01+000 - 30+000) 50 mm Overlay with Deep Patching Uthal - Kund Malir Single 30 - 01+000 - 30+000 30 30 465.445 11.32 339.6 No maintenance required No maintenance required 0 5 Cm 0 0 1509

0+000 - 16+900 (AMP 2019-20) 16+900


50 mm Mill & Fill Deep Patching KM 28+00 to KM KM
79 A 2026 North Zone Northern Areas N-15 N15 Mansehra - Chilas - 01 (01+000 - 33+000) 30cm GB + 13 cm AC REHAB Mansehra - Tarana Single 33 - 28+700 (AMP 2018-19) 34+000 - 28+700 - 33+000 4.3 4.3 1052.923 31.06 133.558 To be analised 50 mm Mill & Fill Deep Patching 5 Km 30+00 =8 Cm 15.138 75.69 67.95465613 17592
40+000 (AMP 2020-21) (20%) 33+00

210+000 - 213+000 (AMP 2020-21)


213+000 - 218+000 (AMP 2018-19)
218+000 - 228+000 (AMP 2018-19)
228+000 - 238+000 (AMP 2018-19)
Balochistan 50 mm Mill & Fill Deep Patching
80 A 2026 West Zone N-10 N10-MCH Liyari (Uthal) - Gwadar - 09 (202+000 - 256+000) 50 mm Overlay with Deep Patching Kund Malir - Chil-i-Dif Single 55 238+000 - 242+000 (AMP 2020-21) 202+000 - 209+000 7 7 853.316 11.32 79.24 To be analiyed 50 mm Mill & Fill Deep Patching 202+000 to 209+000 7 5 Cm 14.363 100.541 97.32599785 1585
west
242+000 - 244+000 (AMP 2017-18) (25%)
244+000 - 247+000 (AMP 2020-21)
247+000 - 250+000 (AMP 2020-21)
250+000 - 260+000 (AMP 2019-20)

501.8 12,077.90 #REF!


a
-
T
a
Proposed Sections For Periodic Maintenance of AMP 2022-23 c
k
%
NDM-IV Project Level Analysis M
iC
o
d
n
a
Effective Treated

Direction
t
rL
Road C/ Work Description Based Effective Estiamte Engineer ea
Sr. S Existing Ashpalt Length (Chainage)
Name/ way Region HDM-IV Section Location Cost (Rs. Million) on Existing Section and Treated Cost Remarks n
m
No. No. Thickness (cm) e
a
No. Type Construction History Length (km) (CSR-2022) r
From To k
s
1- Strategy is fine
2- Three lane carriageway (only outer
two lanes are included)

Functional Overlay: 50 mm Mill &


Fill Asphalt Overlay with deep
62 1 LEBP Dual Punjab North NB LEBP-W Lahore Eastern Bypass - 01 (01+000 - 17+000) Lahore - sheikhapura 397.435 Patch on outer two lanes only. (For 19cm to 18cm 01+000 17+000 16 286.23 286,228,059.73
deep patch, Mill & Fill 80mm ACBC
on 10% area)

###
1- Strategy is fine
2- Three lane carriageway (only outer
two lanes are included)

Functional Overlay: 50 mm Mill &


Fill Asphalt Overlay with deep
68 2 LEBP Dual Punjab North SB LEBP-E Lahore Eastern Bypass - 01 (17+000 - 01+000) Lahore - sheikhapura 397.435 Patch on outer two lanes only. (For 20cm to 18cm 17+000 01+000 16 286.23 286,228,059.73
deep patch, Mill & Fill 80mm ACBC
on 10% area)

###
KM (0.6-1): 1- Strategy is fine.
Structural Overlay:
120mm Mill & Fill Asphat Overlay 2- KM 0+600 to KM 1+000 has been
with deep patch in 100% area (Item added due to poor condition and
207a). connection with N-55.
KM (1-9): 3- KM 7+100, Canal Bridge Deck is
15 3 LKBP Single Sindh North NB LKBP Larkana - Khairpur - 01 (01+000 - 15+000) Larkana - mohenju dar 232.723 50 mm Direct 12cm 01+000 15+000 14.4 137.36 137,355,227.03 damaged which need repair.
Asphalt Overlay
KM (9-15):
50 mm
Direct Asphalt Overlay with deep
patch (For deep patch, Mill & Fill
70mm ACBC on 15% area) ###
1- Strategy is fine.

2- Actual measured length is 38.5


Functional Overlay: 50 mm Mill & kilometers instead 37.0 kilometer.
Fill Asphalt Overlay with deep 3- KM 384+000 to KM 386+000 & KM
Thailan Interchange - 387+000 to KM 388+000, shoulder
69 4 M-1 Dual M-1 NB M1-N Islamabad - Peshawar - 01 (351+000 - 388+000) 880.308 Patch on outer two lanes only. (For 24cm 351+000 388+000 37 599.63 599,629,111.68
Burhan treatment was in progress. 4- KM
deep patch, Mill & Fill 80mm ACBC
on 20% area) 351+000 to KM 384+000 & KM 386+000
to KM 387+000 shoulder treatment is
required.
###
1- Strategy is fine.

2- KM 263+000 to KM 369+500, Mill &


Fill Overlay has already been placed and
work was in progress during site visit
Functional Overlay: 50 mm Mill & (outer lane).
Sahian Wala Interchange Fill Asphalt Overlay with deep 3-KM 264+100 to KM 264+400,
10 5 M-4 Dual M-4 NB M4-N Multan - Pindi Bhattian - 05 (263+000 - 290+000) - Pindi Bhattian Multan 820.259 Patch on inner lane only. (For deep 13cm 263+000 290+000 27 236.61 236,608,719.30 Mill & Fill Overlay has already been
Interchange patch, Mill & Fill 80mm ACBC on placed (inner lane).
25% area) 4- The
overlay start location is KM 263+000 and
likely to be continue up to KM 290+000.

###
1- Strategy is fine.
Functional Overlay: 50 mm Mill &
Ratedero - khuzadr Can- Fill Asphalt Overlay with deep 7cm, 18cm, 19cm, 20cm
34 6 M-8 Single Sindh North NB M8 Khuzdar - Ratodero - 05 (203+000 - 250+000) 744.712 203+000 250+000 47 757.70 757,696,405.67
nment Patch (For deep patch, Mill & Fill & 15cm
80mm ACBC on 25% area)
###
1- Strategy is fine.
Structural Overlay: 50mm Mill & 2- Existing Asphalt Concrete
130mm Fill Asphalt Overlay with Thickness is only 5cm, so milling can be
25 7 N-120 Single Sindh south NB N120 Mirpur Khas - Khokhrapar - 02 (40+000 - 70+000) Mirpur Khas - Umarkot 856.079 5cm 40+000 65+000 25 584.21 -
deep patch in 25% area (Item done up to 50mm .
207a).
###
1- Strategy is fine except 30cm ABC.
2- Existing
Structural Overlay: 80mm Mill & Asphalt Concrete Thickness is only 8cm,
130mm Fill Asphalt Overlay with so milling can be done up to 80mm .
71 8 N-120 Single Sindh South NB N120 Mirpur Khas - Khokhrapar - 01 (01+000 - 39+000) Mirpur Khas - Sufi Faqir 1244.364 8cm 01+000 39+000 38 1,028.76 1,028,755,094.92 3- Provision of 30cm
deep patch in 25% area (Item
207a). ABC is not required as the embankment
is already raised.
###
KM (1345-1348): 1- Strategy is fine except KM 1345+000 to
Functional Overlay: KM 1350+000, where structural overlay is
50 mm Mill & Fill Asphalt Overlay required. 2-
with deep patch (For deep patch, KM 1346+000 to km 1348+000,
Mill & Fill 80mm ACBC on 25% longitudnal side drain is required (Rs
area) 4500/Rmtr).
KM (1348-1350):

Structural Overlay: 130mm Mill &


2 9 N-5 Dual Punjab North SB N5-S Karachi - Torkham - 11 (1383+000 - 1345+000) Wazirabad - Ghakhar 605.079 26cm 1359+000 1345+000 14 267.71 267,712,649.26
Fill Asphat Overlay with deep patch
in 25% area (Item 207a).
KM
(1350-1359):
Functional Overlay: 50
mm Mill & Fill Asphalt Overlay with
deep patch (For deep patch, Mill &
Fill 80mm ACBC on 25% area)
###
a
-
T
a
Proposed Sections For Periodic Maintenance of AMP 2022-23 c
k
%
NDM-IV Project Level Analysis M
iC
o
d
n
a
Effective Treated

Direction
t
rL
Road C/ Work Description Based Effective Estiamte Engineer ea
Sr. S Existing Ashpalt Length (Chainage)
Name/ way Region HDM-IV Section Location Cost (Rs. Million) on Existing Section and Treated Cost Remarks n
m
No. No. Thickness (cm) e
a
No. Type Construction History Length (km) (CSR-2022) r
From To k
s
1- KM 1564+250 to KM 1568, three lane
rigid pavemen is provided. No action is
required.
2- KM 1567+800 to KM
KM (1564+250-1568): 1568+000, longitudnal side drain is
Three lane required. 3- KM 1568+000 to KM
rigid pavement is provided. No 1569+500, 1.5 kilometer length may be
action is needed. KM (1568- included for structural overlay on Taxila
4 10 N-5 Dual Punjab North SB N5-S Karachi - Torkham - 04 (1568+000 - 1554+000) Wah - tarnol 439.425 1569+500): Rigid 1568+000 1564+250 1.5 42.36 42,360,720.78 Bypass Service Road due to very poor
Structural Overlay: condition.
130mm Mill & Fill Asphat Overlay 4- The proposed section is a part of new
with deep patch in 20% area (Item design from Tarnol to Hassanabdal. NHA
207a). intends to widen and rehabilitate to make
4+4 lanes on each direction.

###
1- Strategy is changed from structural
overlay to functional overlay.
Functional Overlay: 50 mm Mill &
Fill Asphalt Overlay with deep
7 11 N-5 Dual Punjab South NB N5-N Karachi - Torkham - 09 (747+000 - 768+000) Janpur - Chani Goth 568.668 Patch on inner lane only. (For deep 13cm 756+000 765+000 9 97.27 97,265,400.69
patch, Mill & Fill 80mm ACBC on
25% area)

###
a
-
T
a
Proposed Sections For Periodic Maintenance of AMP 2022-23 c
k
%
NDM-IV Project Level Analysis M
iC
o
d
n
a
Effective Treated

Direction
t
rL
Road C/ Work Description Based Effective Estiamte Engineer ea
Sr. S Existing Ashpalt Length (Chainage)
Name/ way Region HDM-IV Section Location Cost (Rs. Million) on Existing Section and Treated Cost Remarks n
m
No. No. Thickness (cm) e
a
No. Type Construction History Length (km) (CSR-2022) r
From To k
s
1- Strategy is fine.
KM (1303-1318+500): 2- KM 1318+500 to KM 1320+500
Functional is excluded as new overlay was in
Overlay: 50 mm Mill & Fill Asphalt progress.
Overlay with deep patch (For deep 3- KM 1344+000 to KM 1345+000
patch, Mill & Fill 80mm ACBC on is included due to poor condition.
25% area) 4- KM 1337+000 to KM 1341+000
KM(1318+500- & 1341+700 to KM 1342+200, longitudnal
1320+500) side drain is required due to poor sufrace
No action required. drainage.
KM
(1320+500-1344): 17cm, 14cm, 12cm &
37 12 N-5 Dual Punjab North SB N5-S Karachi - Torkham - 12 (1344+000 - 1303+000) Ghakhar - Sadhoke 651.623 1344+000 1303+000 40 778.06 778,061,801.38
Functional Overlay: 15cm
50 mm Mill & Fill Asphalt Overlay
with deep patch (For deep patch,
Mill & Fill 80mm ACBC on 25%
area) KM
(1344-1345):
Additional length &
Functional Overlay: 50 mm Mill &
Fill Asphalt Overlay with deep patch
(For deep patch, Mill & Fill 80mm
ACBC on 25% area)
###
1- Strategy is fine.
2- KM 1344+000 to KM 1345+000
KM (1344-1345): is included due to poor condition.
Additional length &
Functional Overlay: 50 mm Mill &
Fill Asphalt Overlay with deep patch
(For deep patch, Mill & Fill 80mm
ACBC on 25% area)
N-5 NB 12cm 1345+000 1359+000 15 269.53
KM (1345-1359):

Functional Overlay: 50 mm Mill &


Fill Asphalt Overlay with deep patch 269,526,961.92
(For deep patch, Mill & Fill 80mm
ACBC on 25% area)

###
1- Strategy is fine.
38 13 Dual Punjab North N5-N Karachi - Torkham - 23 (1345+000 - 1452+000) Rahwali - Dina 1675.602 Functional Overlay: 50 mm Mill &
Fill Asphalt Overlay with deep patch
N-5 NB 13cm 1410+000 1411+000 1 -
(For deep patch, Mill & Fill 80mm
ACBC on 10% area)
###
1- Strategy is fine.
2- KM 1429+250 to KM 1429+750
longitudnal side drain is required.

Functional Overlay: 50 mm Mill &


Fill Asphalt Overlay with deep patch
N-5 NB 19cm, 16cm & 16cm 1425+000 1452+000 27 416.00 415,999,076.68
(For deep patch, Mill & Fill 120mm
ACBC on 10% area)

###
a
-
T
a
Proposed Sections For Periodic Maintenance of AMP 2022-23 c
k
%
NDM-IV Project Level Analysis M
iC
o
d
n
a
Effective Treated

Direction
t
rL
Road C/ Work Description Based Effective Estiamte Engineer ea
Sr. S Existing Ashpalt Length (Chainage)
Name/ way Region HDM-IV Section Location Cost (Rs. Million) on Existing Section and Treated Cost Remarks n
m
No. No. Thickness (cm) e
a
No. Type Construction History Length (km) (CSR-2022) r
From To k
s
KM (1071-1071+575): 1- Strategy is fine.
Additional 2- KM 1071+000 to KM 1071+575 &
length & Structural Overlay: 120mm KM 1073+845 to KM 1074+000 is
Mill & Fill Asphalt Overlay with deep included.
patch in 25% area (Item 207a). 3- 300 longitudnal side drain is
required on inner side for superelevation
KM(1071+575-1073+845) drainage.
Functional Overlay: 50 mm Mill &
Fill Asphalt Overlay with deep patch
N-5 NB (For deep patch, Mill & Fill 70mm 12cm 1071+575 1073+845 3 59.89 59,885,164.12
ACBC on 25% area)
KM(1073+845-1074)
Additional length;
Functional Overlay: 50 mm Mill &
Fill Asphalt Overlay with deep patch
(For deep patch, Mill & Fill 70mm
ACBC on 25% area)
39 14 Dual Punjab North N5-N Karachi - Torkham - 19 (1065+000 - 1146+000) Kassowal - Renala Khurd 1272.217
###
1- Strategy is fine.
2- KM 1085+000 (Intersection) &
KM 1100+000 (roundabout), drain is
Functional Overlay: 50 mm Mill & required in 400 meter length.
Fill Asphalt Overlay with deep patch 3- KM
N-5 NB 10cm 1085+000 1100+000 15 249.54 249,540,282.76 1086+600, superelevation drain is
(For deep patch, Mill & Fill 50mm
ACBC on 25% area) required in 250 meter length.

###
1- Strategy is fine.
Functional Overlay: 50 mm Mill &
2- KM 1133+000 to KM 1140+000,
Fill Asphalt Overlay with deep patch
N-5 NB 11cm 1133+000 1140+000 7 130.82 130,821,096.18 treatment of outer shoulder is required.
(For deep patch, Mill & Fill 60mm
ACBC on 40% area)
###
a
-
T
a
Proposed Sections For Periodic Maintenance of AMP 2022-23 c
k
%
NDM-IV Project Level Analysis M
iC
o
d
n
a
Effective Treated

Direction
t
rL
Road C/ Work Description Based Effective Estiamte Engineer ea
Sr. S Existing Ashpalt Length (Chainage)
Name/ way Region HDM-IV Section Location Cost (Rs. Million) on Existing Section and Treated Cost Remarks n
m
No. No. Thickness (cm) e
a
No. Type Construction History Length (km) (CSR-2022) r
From To k
s
1- Strategy is fine.
KM(1053-1053+271)
2- KM 1053+800, superelevation
Additional length; Functional
drain is required in 150 meter length.
Overlay: 55 mm Mill & Fill Asphalt
Overlay with deep patch in 25%
area (Item 207a).
40 15 N-5 Dual Punjab South SB N5-S Karachi - Torkham - 18 (1062+000 - 1048+000) Chichawatni - Kassowal 232.723 KM(1053+271- 5.5cm 1058+000 1053+271 5 71.29 71,286,107.27
1058)
Functional Overlay: 55 mm Mill &
Fill Asphalt Overlay with deep patch
in 25% area (Item 207a).
###
1- Strategy is changed from functional
overlay to structural overlay.
Structural Overlay: 130mm Mill &
41 16 N-5 Dual Punjab North SB N5-S Karachi - Torkham - 13 (1302+000 - 1268+000) Kamoke - Shadara 814.529 Fill Asphat Overlay with deep patch 13cm 1302+000 1295+000 7 275.02 275,017,882.62
in 25% (Item 207a).

###
1- Strategy is fine.
2- KM 1395+000 to KM 1396+000,
longitudnal side drain is required.
Functional Overlay: 50 mm Mill &
Fill Asphalt Overlay with deep patch
42 17 N-5 Dual Punjab North SB N5-S Karachi - Torkham - 10 (1403+000 - 1384+000) Kharian - Gujraat 310.297 12cm 1398+000 1395+000 3 51.62 51,618,208.72
(For deep patch, Mill & Fill 70mm
ACBC on 25% area)

###
1- To be excluded from annual
maintenace plan as new construction of
No action required (New project start km 870 to km NB is in progress.
43 18 N-5 Dual Punjab South NB N5-N Karachi - Torkham - 13 (870+000 - 886+000) Lodhran - Basti Malook 263.752 870+000 885+000 0 -
Construction is in Progress) 885

1- Strategy is fine except 30cm ABC.


KM(1534-1535) 3-lanes 2- KM 1534+000 to KM 1535+000, only
Functional Overlay: 50 mm Mill functional overlay is required.
& Fill Asphalt Overlay with deep
patch (For deep patch, Mill & Fill
110mm ACBC on 25% area)
N-5 NB 16cm 1534+000 1536+000 2 66.05 66,045,730.76
KM(1535+1536) 3-lanes
Structural Overlay:
160mm Mill & Fill Asphat Overlay
with deep patch in 25% area (Item
207a).
51 19 Dual Punjab North N5-N Karachi - Torkham - 25 (1508+000 - 1551+000) Mandra - Tarnnol 1403.898 KM(1537-1538) 3-lanes ###
Additional length: Functional 1- Strategy is changed form rehabilitation
Overlay: 50 mm Mill & Fill Asphalt to functional overlay.
Overlay with deep patch (For deep
patch, Mill & Fill 120mm ACBC on
25% area)
N-5 NB KM(1538+1540) 3-lanes 17cm 1538+000 1540+000 3 87.17 87,168,875.15
Functional
Overlay: 50 mm Mill & Fill Asphalt
Overlay with deep patch (For deep
patch, Mill & Fill 120mm ACBC on
25% area) ###
1- Strategy is fine.
2- KM 1440+500 to KM 1447+000,
rigid pavement in outer lane is excluded.

KM(1425-1440+500) KM 3- KM 1447+000 to KM 1448+000 & KM


(1447-1452) 1440+500 to KM 1441+000, longitudinal
Functional Overlay: 50 mm Mill & drain is required. 4-
Fill Asphalt Overlay with deep patch Shoulder treatment is required throughout
(For deep patch, Mill & Fill 110mm the length.
ACBC on 25% area)
KM(1440+500-1447)
Chak mehun - Bawali Functional
52 20 N-5 Dual Punjab North SB N5-S Karachi - Torkham - 08 (1452+000 - 1425+000) 434.415 15cm, 20cm & 13cm 1452+000 1425+000 27 397.55 397,548,359.92
Khurd Overlay: 50 mm Mill & Fill Asphalt
Overlay with deep patch on inner
lane only (For deep patch, Mill & Fill
110mm ACBC on 25% area)

###
1- Strategy is fine.
2- Rigid pavement in outer lane is
KM(1453+200-1463+600) excluded.
KM (1466-1470+500)
KM (1471-1473+800) KM
(1478+900-1481)
Functional Overlay: 50 mm Mill &
Fill Asphalt Overlay with deep patch
on inner lane only (For deep patch,
Mill & Fill 110mm ACBC on 25%
area)
N-5 NB 16cm 1453+000 1481+000 28
KM(1463+600-1466)
KM (1470+500-1471) KM
(1473-800+1478+900)
53 21 Dual Punjab North N5-N Karachi - Torkham - 24 (1453+000 - 1507+000) Dina - Rawat 853.316 Functional 329.86 329,856,790.48
Overlay: 50 mm Mill & Fill Asphalt
Overlay with deep patch on both
lanes (For deep patch, Mill & Fill
110mm ACBC on 25% area)

###
a
-
T
a
Proposed Sections For Periodic Maintenance of AMP 2022-23 c
k
%
NDM-IV Project Level Analysis M
iC
o
d
n
53 21 Dual Punjab North N5-N Karachi - Torkham - 24 (1453+000 - 1507+000) Dina - Rawat 853.316 329.86 329,856,790.48 a
Effective Treated

Direction
t
rL
Road C/ Work Description Based Effective Estiamte Engineer ea
Sr. S Existing Ashpalt Length (Chainage)
Name/ way Region HDM-IV Section Location Cost (Rs. Million) on Existing Section and Treated Cost Remarks n
m
No. No. Thickness (cm) e
a
No. Type Construction History Length (km) (CSR-2022) r
From To k
s
KM (1481-1482) 1- Strategy is fine.
Functional Overlay: 50 mm Mill & 2- Rigid pavement in outer lane is
Fill Asphalt Overlay with deep patch excluded.
N-5 NB 1481+000 1482+000 1
on inner lane only (For deep patch,
Mill & Fill 110mm ACBC on 25%
area)
1- Strategy is fine.
2- At KM 847+800 (roundabout),
longitudnal drain is required in 200 meter
length.
Functional Overlay: 50 mm Mill & 3- In superelevation reach, longitudnal
Fill Asphalt Overlay with deep patch 14cm, 15cm, 11cm,
54 22 N-5 Dual Punjab South SB N5-S Karachi - Torkham - 22 (851+000 - 790+000) Gharibabad - Basti wahni 961.92 851+000 790+000 61 1,182.38 1,182,378,731.66 drain is also required in overall 5.0
(For deep patch, Mill & Fill 100mm 13cm, 12cm & 13cm kilometers.
ACBC on 25% area)

###
KM (190-205+680): 1- Strategy is fine except 30cm ABC.
Structural Overlay: 140mm Mill & 2- KM 205+680 to KM 206+000, length is
Fill Asphat Overlay with deep patch added.
in 30% area (Item 207a).

N-5 NB KM 14cm 190+000 205+680 16 500.27 500,274,387.78


(205+680-206):
Additional length: Structural
Overlay: 140mm Mill & Fill Asphat
Overlay with deep patch in 30%
area (Item 207a). ###
1- Strategy is fine except 30cm ABC.
2- KM 205+000
to KM 208+000 & KM 209+640 to KM
Structural Overlay: 260mm Mill & 210+000, also need to be included.
55 23 Dual Sindh South N5-N Karachi - Torkham - 02 (185+000 - 250+000) Hyderabad - Sakrand 2105.847
N-5 NB Fill Asphat Overlay with deep patch 26cm 208+000 209+640 5 205.13 205,131,754.51 3- KM 205+000 to
in 25% area (Item 207a). 210+000, shoulder treatment is also
required.
###
1- Strategy is fine.
2- KM 220+000 to KM 221+000 also
need to be included.
3- KM 218+000 to 221+000,
Rehabilitation: 30cm ABC & 13cm shoulder treatment is also required.
N-5 NB 15cm 218+000 220+000 3 101.31 101,311,556.41
Asphalt Concrete Overlay

KM (1534-1535): 4-lane ###


Functional Overlay: 50 1- Strategy is changed from structural
mm Mill & Fill Asphalt Overlay with overlay to functional overlay.
deep patch (For deep patch, Mill & 2- KM
Fill 40mm ACBC on 15% area) 1535+000 to KM 1540+000 need to be
KM (1535- excluded due to Satisfactory condition.
1540): No action
N-5 SB Tarnol - Dera Khalsa required. 9cm 1540+000 1534+000 2
KM (1540-1541): 3 -lane
Additional length:
Functional Overlay: 50 mm Mill &
Fill Asphalt Overlay with deep patch
(For deep patch, Mill & Fill 40mm
ACBC on 15% area)
KM (1495-1501): ###
Additional length: Functional 1- Strategy is changed from structural
Overlay: 50 mm Mill & Fill Asphalt overlay to functional overlay to include the
Overlay with deep patch (For deep additional length which is also in poor
patch, Mill & Fill 40mm ACBC on condition.
15% area) 2- KM 1495+000 to KM 1510+000
KM (1501-1504): (Mandra Toll Plaza), total 15 km length
Functional need to be included in AMP 2021-22.
56 24 Dual Punjab North N5-S Karachi - Torkham - 05 (1553+000 - 1501+000) 1552.634 Overlay: 50 mm Mill & Fill Asphalt 237.14 237,141,608.51 3-
Overlay with deep patch (For deep KM 1504+000 to KM 1505+500 rigid
patch, Mill & Fill 40mm ACBC on pavement is provided in outer lane.
25% area) KM (1504-
1505+500):
Functional Overlay: 50 mm Mill &
Fill Asphalt Overlay with deep
N-5 SB Tarnol - Dera Khalsa patch on inner lane (For deep 9cm 1506+000 1501+000 15
patch, Mill & Fill 40mm ACBC on
25% area)
KM (1505+500-1506):
Functional Overlay: 50 mm
Mill & Fill Asphalt Overlay with
deep (For deep patch, Mill & Fill
40mm ACBC on 25% area)
KM (1506-
1510):
Additional length: Functional
Overlay: 50 mm Mill & Fill Asphalt
Overlay with deep (For deep patch,
Mill & Fill 40mm ACBC on 25%
area) ###
1- To be excluded from annual
No action required (New maintenace plan as new construction of
57 25 N-5 Dual Punjab South NB N5-N Karachi - Torkham - 15 (897+000 - 920+000) Basti Malook - Multan 372.356 4cm & 5cm 898+000 920+000 0 - NB is in progress.
Construction is in Progress)

1- Strategy is fine.
2- KM 1036+200 to KM 1037+600,
longitudnal drain is required.
3- 500 meter drain is also required at
inner side for superelevation drainage.

Functional Overlay: 50mm Mill &


N-5 SB Fill Asphat Overlay with deep patch 5cm 1047+000 1030+000 17 260.41 260,409,126.33
in 25% area (Item 207a)
54 26 Dual Punjab South N5-S Karachi - Torkham - 19 (1047+000 - 982+000) Chichawatni - Khanewal 1023.979

###
a
-
T
a
Proposed Sections For Periodic Maintenance of AMP 2022-23 c
k
%
NDM-IV Project Level Analysis M
iC
o
d
n
a
Effective Treated

Direction
t
rL
Road Dual
C/ Punjab South Work Description Based Effective Estiamte Engineer ea
Sr.
54 S
26 N5-S Karachi - Torkham - 19 (1047+000 - 982+000) Chichawatni - Khanewal 1023.979 Existing Ashpalt Length (Chainage)
Name/ way Region HDM-IV Section Location Cost (Rs. Million) on Existing Section and Treated Cost Remarks n
m
No. No. Thickness (cm) e
a
No. Type Construction History Length (km) (CSR-2022) r
From To k
s
1- Strategy is fine.
Functional Overlay: 70mm Mill &
N-5 SB Fill Asphat Overlay with deep patch 7cm 1021+000 1019+000 2 32.89 32,885,950.53
in 25% area (Item 207a)
###
1- Strategy is changed from rehabilitation
to functional overlay because: (i) Raising
is not possible due to existance of NJB as
a median barrier and (ii) On the opposite
Functional Overlay: 50 mm Mill & carriageway only functional overlay is
Fill Asphalt Overlay with deep (For proposed.
59 27 N-5 Dual Punjab North NB N5-N Karachi - Torkham - 22 (1320+000 - 1344+000) Attwa - Ghakhar 797.669 19cm & 21cm 1320+000 1344+000 24 594.31 594,308,925.94 2- KM 1320+000 to KM 1344+000,
deep patch, Mill & Fill 150mm
ACBC on 40% area) longitudnal side drain is required in the
remaining length (Half length 12 km is
taken for side drain)

###
1- Strategy is changed as follows:
2- KM 921+000 to 929+000
KM (921-929): 50 mm 50 mm Direct Asphalt
50 mm Direct Asphalt Overlay with Overlay with deep patch
deep patch (For deep patch, Mill & 3- KM 929+000 to
Fill 130mm ACBC on 10% area) 931+700 130mm
Mill & Fill Asphat Overlay with deep patch
KM (929+931+700): 4-
Structural Overlay: 130mm KM 931+700 to 937+000
Mill & Fill Asphat Overlay with deep no action required (Multan Metwro
patch in 25% area (Item 207a).
N-5 NB 12cm & 14cm 921+000 940+000 13.7 330.10 330,096,419.76 Bus Section)
KM 5- KM 937+000 to 940+000
(931+700-937): 50 mm Mill & Fill Asphalt
No action required. Overlay with deep patch
KM (937-940): 6- 300 meter
Funtional Overlay: 50 mm longitudnal drain is required.
Mill & Fill Asphalt Overlay with deep
patch (For deep patch, Mill & Fill
80mm ACBC on 25% area)
60 28 Dual Punjab South N5-N Karachi - Torkham - 16 (921+000 - 988+000) Shahkot - Khanewal 1055.009

###
a
-
T
a
Proposed Sections For Periodic Maintenance of AMP 2022-23 c
k
%
NDM-IV Project Level Analysis M
iC
o
d
n
a
Effective Treated

Direction
t
rL
Road C/ Work Description Based Effective Estiamte Engineer ea
Sr. S Existing Ashpalt Length (Chainage)
Name/ way Region HDM-IV Section Location Cost (Rs. Million) on Existing Section and Treated Cost Remarks n
m
No. No. Thickness (cm) e
a
60 28 No. Type
Dual Punjab South N5-N Karachi - Torkham - 16 (921+000 - 988+000) Shahkot - Khanewal 1055.009 Construction History Length (km) (CSR-2022) r
From To k
s
1- Strategy is fine.
Funtional Overlay: 50 mm Mill & Fill
Asphalt Overlay with deep patch
N-5 NB 5cm & 13cm 944+200 970+000 25.8 474.79 474,787,109.64
(For deep patch, Mill & Fill 80mm
ACBC on 25% area)
KM (980-984+500): ###
Funtional Overlay: 60 mm Mill 1- Strategy is fine.
& Fill Asphalt Overlay with deep 2- KM 984+500 to KM 986+000, is
patch in 25% area (Item 207a). excluded fue to fair condition.

KM (984+500-986):
N-5 NB No action required due to rigid 6cm 980+000 988+000 6.5 113.27 113,272,415.64
pavement
KM (986-988):
Functional Overlay: 60 mm
Mill & Fill Asphalt Overlay with deep
patch in 25% area (Item 207a). ###
1- Strategy is changed from structural
overlay to functional overlay.
2- 300
Funtional Overlay: 50 mm Mill & Fill meter longitudnal drain is required.
Asphalt Overlay with deep patch
N-5 NB 25cm 381+000 382+000 1 23.07 23,074,970.42
(For deep patch, Mill & Fill 200mm
ACBC on 25% area)

###
KM (383-412): 1- Strategy is changed from structural
Noushahro Feroze - Funtional Overlay: 50 mm Mill & overlay to functional overlay.
29 N5-N Karachi - Torkham - 04 (321+000 - 469+000) 4115.973
Babarloi Fill Asphalt Overlay with deep patch 2- KM
(For deep patch, Mill & Fill 180mm 421+000 to KM 414+000, rigid pavement
ACBC on 25% area) is provided on both lanes. 3- KM
61 Dual Sindh North 414+000 to KM 469+000, rigid lane is
KM (412-414):
23cm, 19cm, 20cm, provide in outer lane.
No action
N-5 NB 20cm, 19cm, 26cm & 383+000 469+000 84 1,854.44 1,854,439,013.24
required due to rigid pavement
19cm
KM
(414-469):
Funtional Overlay: 50 mm Mill & Fill
Asphalt Overlay with deep patch
(For deep patch, Mill & Fill 180mm
ACBC on 25% area) ###
a
-
T
a
Proposed Sections For Periodic Maintenance of AMP 2022-23 c
k
%

61 Dual Sindh North


NDM-IV Project Level Analysis M
iC
o
d
n
a
Effective Treated

Direction
t
rL
Road C/ Work Description Based Effective Estiamte Engineer ea
Sr. S Existing Ashpalt Length (Chainage)
Name/ way Region HDM-IV Section Location Cost (Rs. Million) on Existing Section and Treated Cost Remarks n
m
No. No. Thickness (cm) e
a
No. Type Construction History Length (km) (CSR-2022) r
From To k
s
1- Strategy is fine.

Rehabilitation: 30cm ABC & 13cm


30 N-5 NB 1 not found in data 321+000 339+000 18 611.38 611,377,628.28
Asphalt Concrete Overlay

###

Funtional Overlay: 50 mm Mill & Fill


Asphalt Overlay with deep patch
63 31 N-5 Dual Punjab North SB N5-S Karachi - Torkham - 15 (1140+000 - 1130+000) Okara Bypass - Panditpur 170.653 12cm 1140+000 1133+000 7 213.72 213,719,724.99
(For deep patch, Mill & Fill 70mm
ACBC on 50% area)
###
KM (354-363): 1- Strategy is fine.
Structural Overlay: 130mm Mill & 2- KM 363+000 to KM 368+000,
Fill Asphat Overlay with deep patch structural overlay is replaced with
in 30% area (Item 207a). functional overlay.
KM (363- 3- Outer shoulder treatment is
N-5 SB 15cm & 14 cm 368+000 354+000 14 1,075.61 1,075,607,193.79 required in full length.
368):
Funtional Overlay: 50 mm Mill & Fill
Asphalt Overlay with deep patch
(For deep patch, Mill & Fill 100mm
ACBC on 25% area) ###
1- Strategy is fine.
2- At KM 317+000 (inner side) &
Halani - Nawab Wali KM 320+000 (outer side), overall 1
64 32 Dual Sindh North N5-S Karachi - Torkham - 33 (368+000 - 296+000) 2138.533
Muhammad kilometer side drain may be provided to
Structural Overlay: 130mm Mill & improve road surface drainage.
N-5 SB Fill Asphat Overlay with deep patch 13cm 320+000 310+000 10 297.72 297,716,215.36
in 30% area (Item 207a).

###
1- Strategy is changed from structural
Funtional Overlay: 50 mm Mill & Fill overlay to functional overlay.
Asphalt Overlay with deep patch
N-5 SB 15cm 300+000 296+000 4 75.10 75,101,593.43
(For deep patch, Mill & Fill 100mm
ACBC on 25% area)
###
1- Strategy is changed from functional
Structural Overlay: 130mm Mill &
overlay to structural overlay.
N-55 NB Fill Asphat Overlay with deep patch 13cm & 12cm 473+000 487+000 14 353.62 353,616,681.92
in 30% area (Item 207a).
###
1- KM 487+700 to KM 489+000, Rigis
pavement is provided. 2-
KM 487+700 to KM 489+000, longitudnal
side drain is required in urban area of
Kashmore.
14 33 Single Sindh North N55-N Kotri - Peshawar - 10 (473+000 - 495+000) Kandh kot - Kashmore 356.841
KM (487+700-489):
N-55 NB No action required except 20cm 488+000 490+000 2 - -
provision of side drain

###
1- Strategy is fine.
2- KM 135+000 to KM 137+000,
longitudnal side drain is required.
Funtional Overlay: 50 mm Mill & Fill
Asphalt Overlay with deep patch
N-55 NB 20cm 135+000 140+000 5 103.28 103,276,526.37
(For deep patch, Mill & Fill 150mm
ACBC on 20% area)
Lakki Shah Saddar -
33 34 Dual Sindh south N55-N Kotri - Peshawar - 04 (135+000 - 240+000) 1479.482
Sehwan ###
a
-
T
a
Proposed Sections For Periodic Maintenance of AMP 2022-23 c
k
%
NDM-IV Project Level Analysis M
iC
o
d
n
a
Effective Treated

Direction
t
rL
Road C/ Work Description Based Effective Estiamte Engineer ea
Sr. S Existing Ashpalt Length (Chainage)
Name/ way Region HDM-IV Section Location Cost (Rs. Million) on Existing Section and Treated Cost Remarks n
m
No. No. Thickness (cm) e
a
No. Type Construction History Length (km) (CSR-2022) r
33 34 Dual Sindh south N55-N Kotri - Peshawar - 04 (135+000 - 240+000)
Lakki Shah Saddar -
1479.482 From To k
Sehwan s
1- Strategy is fine however, only overlay
Funtional Overlay: 50 mm Mill & Fill is required on inner lane. 2-
Asphalt Overlay with deep patch on Shoulder treatmnet is required throughout
N-55 NB outer lane only (For deep patch, 15cm & 19cm 220+000 240+000 20 227.95 227,947,834.28 the length.
Mill & Fill 120mm ACBC on 20%
area)
###
KM (430-463+500): 1- Strategy is fine.
Rehabilitation: 2- KM 463+000 to KM 469+000 is
30cm ABC & 13cm Asphalt excluded as new overlay has already
Concrete Overlay been placed.
KM 3- KM 463+000 to KM 469+000,
73 35 N-55 Single Sindh North NB N55-N Kotri - Peshawar - 09 (406+000 - 472+000) Larkana - Shikarpur 2137.753 (463+500-469): 15cm, 11cm & 13cm 430+000 472+000 36.5 1,086.52 1,086,522,573.07 only shoulder treatment is required.
No action required 4- At some urban locations drain is
KM required. Overall 4.2 kilometer lebgth of
(469+472): longitudnal side drain may be included.
Rehabilitation:30cm ABC &
13cm Asphalt Concrete Overlay ###
1- Strategy is fine except: KM 81+000 to
KM (1-81): KM 91+700 where structural overlay is
Funtional Overlay: 50 mm required & KM 91+700 to KM 92+000
Mill & Fill Asphalt Overlay with deep where 30cm ABC with 13cm Asphalt
patch (For deep patch, Mill & Fill Concrete Overlay is required (Raising).
110mm ACBC on 20% area)

KM (81-91+700):
13cm, 14cm, 15cm &
8 36 N-5A Dual Punjab South SB N5A-S Lodrhran - Khanewal - 01 (92+000 - 01+000) Lodrhran - Khanewal 1427.365 Structural 92+000 01+000 91 1,732.32 1,732,322,905.59
16cm
Overlay: 130mm Mill & Fill Asphat
Overlay with deep patch in 30%
area (Item 207a).
KM (91+700-92):

Rehabilitation: 30cm ABC & 13cm


Asphalt Concrete Overlay
###
Functional overlay with deep patch on 8%
KM (12-45): area as both sections contain same
Funtional Overlay: 50 mm straitagy except for deep patching, To
Mill & Fill Asphalt Overlay with deep achive our percent patch area over total
patch (For deep patch, Mill & Fill length , divide % area by 2 to deep patch
11cm, 12cm, 13cm &
49 37 N-65 Dual Sindh North SB N65-S Sukkur - Quetta - 01 (80+000 - 12+000) Jacobabad - Sukkar 1070.524 80mm ACBC on 15% area) 80+000 12+000 68 962.06 962,057,423.60 on just required percentage.
15cm
(i.e 15% area in 33 km
KM (45-80): 8% area in 68 km)
Funtional Overlay: 50
mm Mill & Fill Asphalt Overlay
###
1- Strategy is fine.
2- KM 90+000 to KM 92+000,
widening of the existing road is in
Structural Overlay: 100mm Mill & progress.
N-70 NB Fill Asphat Overlay with deep patch 10cm 90+000 112+000 22 455.73 455,733,098.90 3- Existing Asphalt Concrete
in 30% area (Item 207a). Thickness is only 10cm, so milling can be
done up to 100mm .
###
1- Strategy is fine.
2- Existing Asphalt Concrete
Thickness is only 11cm, so milling can be
Structural Overlay: 110mm Mill & done up to 110mm .
N-70 NB Fill Asphat Overlay with deep patch 11cm 118+000 128+000 10 227.53 227,534,108.00
in 30% area (Item 207a).
16 38 Single Punjab South N70-W Multan - Qillah Saifullah - 04 (90+000 - 154+000) D G Khan - Fort Monroe 1680.155

###
KM (138-142+675): Average of patching area (i.e 25%)
Additional length:
Structural Overlay: 110mm Mill &
Fill Asphat Overlay with deep patch
in 30% area (Item 207a).
N-70 NB KM 11cm 142+675 154+000 16 375.47 375,469,283.40
(142+675-154):
Structural Overlay:
110mm Mill & Fill Asphat Overlay
with deep patch in 20% area (Item
207a). ###
KM (38-40):
Funtional Overlay: 50 mm 1- Strategy is fine.
Mill & Fill Asphalt Overlay with deep 2- KM 40+000 to KM 71+000,
patch (For deep patch, Mill & Fill length is reduced due to Satisfactory
110mm ACBC on 25% area) pavement condition.
KM (40-71):
No action required. 16cm, 13.5cm, 12cm,
27 39 N-70 Dual Punjab South SB N70-E Multan - Qillah Saifullah - 01 (92+000 - 38+000) D G khan - Muzafargarh 853.316 92+000 38+000 23 335.21 335,209,699.89
KM (71-92): 15cm, 11cm & 12cm
Funtional
Overlay: 50 mm Mill & Fill Asphalt
Overlay with deep patch on outer
lane (For deep patch, Mill & Fill
110mm ACBC on 15% area) ###
1- Strategy is fine.
Funtional Overlay: 50 mm Mill & Fill
Asphalt Overlay with deep patch 20cm, 20cm, 13cm &
44 N-70 Dual Punjab South SB N70-E Multan - Qillah Saifullah - 02 (37+000 - 01+000) Muzafargarh - Multan 574.049 37+000 01+000 36 640.53 640,530,766.04
(For deep patch, Mill & Fill 150mm 15cm
ACBC on 20% area)
40 ###
KM (40-62): 1- Strategy is fine however, KM 40+000 to
Funtional Overlay: 50 mm KM 62+000, 50mm Mill & Fill Asphalt
Mill & Fill Asphalt Overlay with deep Overlay with deep patch is only required
patch on outer lane (For deep on outer lane. Inner lane condition is Fair.
patch, Mill & Fill 130mm ACBC on
20% area)
76 N-70 Dual Punjab South NB N70-W Multan - Qillah Saifullah - 02 (40+000 - 69+000) Muzafargarh - D G khan 465.445 13cm, 16cm & 18cm 40+000 69+000 29 293.17 293,167,479.88
KM (62-69):
Funtional Overlay: 50 mm
Mill & Fill Asphalt Overlay with deep
patch (For deep patch, Mill & Fill
130mm ACBC on 15% area)
41 ###
Previous Non Executed Schemes
Cost as per HDM- Revised Cost per
NHA Cost Recommended Cost Per Km
S.N Year Regions Road Name Sections Work Description Previous Amps Stragies Locations C/way Type Applied Strategy Recommended Section Core Info (Cm) IV Section recommended
(Millions) Length (millions)
(Millions) Length (millions)

388+000 - 421+000
1 2023 M-1 & E35 M-1 M1-N Islamabad - Peshawar - 02 (389+000 - 458+000) 50 mm Overlay with Deep Patching 120 mm Structural Overlay with Cold milling Brahma -Rashakai Dual 50 mm Mill & Fill Deep Patching (25%) 421+000 - 432+000 71 1621.6192 13.749 976.20
433+000 - 460+000

2 2025 M-1 & E35 M-1 M1-N Islamabad - Peshawar - 01 (351+000 - 388+000) 50 mm Overlay with Deep Patching 120 mm Structural Overlay with Cold milling Brahma -Rashakai Dual 50 mm Mill & Fill Deep Patching (25%) 377+000 - 388+000 11 880.308 13.749 151.24

575

120 mm Structural Overlay with Cold milling 460+000 - 433+000


3 2026 M-1 & E35 M-1 M1-S Islamabad - Peshawar - 01 (503+000 - 422+000) 50 mm Overlay with Deep Patching Brahma -Rashakai Dual 50 mm Mill & Fill Deep Patching (25%) 38 1,899.611 13.749 522.47
432+000 - 421+000

4 2026 M-1 & E35 M-1 M1-S Islamabad - Peshawar - 02 (421+000 - 351+000) 50 mm Overlay with Deep Patching 120 mm Structural Overlay with Cold milling Brahma -Rashakai Dual 50 mm Mill & Fill Deep Patching (25%) 421+000 - 377+000 44 1,644.785 13.749 604.97

120 mm Structural Overlay with cold milling &


2 2023 Punjab South N-55 N55-N Kotri - Peshawar - 13 (538+000 - 609+000) 50 mm Overlay with Deep Patching DST as Crack Relief layer 232.41 Rajanpur - Fazilpur Single 50 mm Mill & Fill Deep Patching (25%) 606+000 - 610+000 4 1117.068288 14.363 57.45

127+500 -130+000
3 2023 Northen Areas N-35 N35 Hassanabdal - Khunjrab - 05 (122+000 - 165+000) TST (Surfacing) 120 mm structural overlay with cold milling 232.42 Abbotabad to Mansehra Single TST 140+000 - 145+500 9.09999999999997 292.554112 4.927 44.84
158+800 - 160+200

4 2023 Sindh North N-65 N65-N Sukkur - Quetta - 01 (01+000 - 120+000) 50 mm Overlay with Deep Patching WBM,ABC, ACWC,DST at Shoulders 125.473 Shikarpur - Sultan Kot Dual 50 mm Mill & Fill Deep Patching (25%) 33+000 - 40+000 7 1861.780352 13.749 96.24

Cold Milling (130mm),WBM, DST,CRL ABC, ACWC,


5 2025 Sindh North N-5 N5-S Karachi - Torkham - 32 (399+000 - 369+000) 50 mm Overlay with Deep Patching Shoulders 303.133 Rajanpur - Kotri Kabir Dual 50 mm Mill & Fill Deep Patching (25%) 400+000 - 383+000 17 480.959936 13.749 233.74

Cold Milling (130mm), WBM, DST,CRL ABC, ACWC, Moro -Naushero Feroz 330+000 - 320+000
6 Shoulders Dual 130 mm Mill & Fill Overlay Km 315 = 13 cm

2025 Sindh North N-5 N5-S Karachi - Torkham - 33 (368+000 - 296+000) Structrual 130 mm Overlay Milling 380.979 20 2138.532992 28.242 564.85
50 mm Asphaltic Overlay with Cold milling & DST
as Crack Relief Layer Moro - Shahpur Dual 130 mm Mill & Fill Overlay 310+000 - 300+000

475+000 - 460+000
460+000 - 445+000
Cold Milling (150mm), DST, ACBC, ACWC, 445+000 - 430+000
7 2025 Sindh North N-5 N5-S Karachi - Torkham - 31 (477+000 - 400+000) 30cm GB + 13 cm AC REHAB Shoulders 1775.659 Sukkar Bypass - Kotri Kabir Dual Rehabilitation 73 2488.727808 33.369 2,435.92
430+000 - 414+000
412+000 - 400+000

8 2026 Northen Areas N-15 N15 Mansehra - Chilas - 01 (01+000 - 33+000) 30cm GB + 13 cm AC REHAB Structural overlay 262.944 Attarshisha - Bissian Single Rehabilitation 16+900 - 28+700 11.8 1052.923328 33.721 397.90

120 mm Structural Overlay with cold milling & 610+000 - 615+000


Rajanpur - Muhammad Pur Divan
9 2034 Punjab South N-55 N55-N Kotri - Peshawar - 14 (610+000 - 638+000) 30cm GB + 13 cm AC REHAB DST as Crack Relief layer Single Rehabilitation 617+000 - 627+000 18 925.296256 33.721 606.98
630+000 - 633+000
339.81
120 mm Structural Overlay with cold milling & Rajanpur - Muhammad Pur Divan
2036 Punjab South N-55 N55-N Kotri - Peshawar - 17 (700+000 - 768+000) 50 mm Overlay with Deep Patching DST as Crack Relief layer Single 50 mm Mill & Fill Deep Patching (25%) 709+000 - 711+000 2 963.059 14.363 28.73

Ratodero-Shdadkot
10 2036 Sindh North M-8 M8 Khuzdar - Ratodero - 02 (36+000 - 84+000) 50 mm Overlay with Deep Patching 150 Single 50 mm Mill & Fill Deep Patching (25%) 56+000 - 64+000 8 760.227008 14.36 114.88

Cold Milling (150mm), DST, ACBC, ACWC,


11 2036 Sindh North N-5 N5-N Karachi - Torkham - 06 (488+000 - 608+000) 30cm GB + 13 cm AC REHAB Shoulders 231.079 Ghotki - Sarhad Dual Rehabilitation 544+000 - 552+000 8 3860.718848 33.369 266.95

Cold Milling (150mm), DST, ACBC, ACWC,


12 2037 Sindh North LKBP-2 LKBP Larkana - Khairpur - 02 (16+000 - 56+000) Structrual Overlay (150mm with Milling) Shoulders 286.383 Larkana Khairpur Bypass Single Structrual Overlay (150mm with Milling) 45+100 - 55+300 10.4 1294.969344 27.755 288.65

4895.29 Total 352.3 23283.140608 7,392.00


HDM-IV NHA List
Proposed Sections for AMP 2022-23
Revised Cost
Recommend NHA Proposed
Road Cost per km as per
S. No. Year Region Section Work Description Cost (Million) C/way Type Recommended Section ed Length Location Work Description Coring Budget Remarks
name (Millions) recommended
(Km) (Million)
length

130 mm Mill & Fill Overlay with Deep Rehabilition 30 cm Base course/ 13 cm Asphalt
0 2023 KPK N-55 N55-S Kotri - Peshawar - 03 (1204+000 - 1021+000) 4756.130 Dual 1118+000-1124+000 6 jatta, ismail khel-krapa 169.11 33.369 200.21
Patching concrete.

130 mm Mill & Fill Overlay with Deep Rehabilition 30 cm Base course/ 13 cm Asphalt
2 2023 KPK N-55 N55-S Kotri - Peshawar - 03 (1204+000 - 1021+000) 4756.130 Dual 1104+000-1111+000 7 jandri - Shaheedan Band 212.50 33.369 233.58
Patching concrete.

130 mm Mill & Fill Overlay with Deep Rehabilition 30 cm Base course/ 13 cm Asphalt
3 2023 KPK N-55 N55-S Kotri - Peshawar - 03 (1204+000 - 1021+000) 4756.130 Dual 1040+000-1048+000 8 Marmandi azim - mash m 254.96 33.369 266.95
Patching concrete.

Rehabilition 30 cm Base course/ 13 cm Asphalt


4 2025 KPK N-55 N55-N Kotri - Peshawar - 23 (996+000 - 1084+000) 50 mm Overlay with Deep Patching 1380.820 Dual 1009+000-1013+500 4.5 kakka khel - masha manso Km 1011 = 15 cm - 33.369 150.16
concrete.

Rehabilition 30 cm Base course/ 13 cm Asphalt


5 2022 KPK N-55 N55-S Kotri - Peshawar - 04 (1020+000 - 997+000) 50 mm Asphaltic Overlay 269.381 Dual 1013+500-1009+000 4.5 masha mansoor - kakka kh - 33.369 150.16
concrete.
1+000-4+000 3 50 mm Mill & Fill Deep Patching 14.36 14.36 43.09
130 mm Mill & Fill Overlay with Deep
6 2023 Punjab N-125 N125 Taxila - Haripur - 01 (01+000 - 43+000) 1111.487 Single Taxila zero point - UET T
Patching
4+000-6+000 2 Rehabilitation 33.72 33.72 67.44

7 2036 Sindh North N-55 N55-N Kotri - Peshawar - 09 (406+000 - 472+000) 30cm GB + 13 cm AC REHAB 2,137.753 single 398+000 - 413+000 15 Higorja-ranipur Functional overlay 53.25 14.363 215.4471792

8 2035 Punjab South N-5 N5-N Karachi - Torkham - 18 (1033+000 - 1064+000) 30cm GB + 13 cm AC REHAB 1,021.017 Dual 1042+300 - 1044+500 2.2 Chichawatni -Kassowal Structural overlay 60.16 27.755 61.062084908001

20188.847 30.0 636.57 1,388.10


Direction
HDM-IV
Length Length Recommended Revised Cost
Year Section Road Class AADT Work Description From To Work Discription Location Cost Unit cost Remarks
(km) (km) Length (Km) (Million Rs.)
(Million Rs.)
Jamia masjid No shoulders.
ghussai to
2028 N75-N Islamabad - Lower Topa - 03 (30+000 - 54+000) NB Primary or trunk 25.0 2958 50 mm Overlay 29+000 44+000 15 50 mm mill & Fill with Deep Patch (20%) 15 Secrit sky
375.000 12.600 189.005 Core thickness is
murree supposed 10 cm
Lower topa No shoulders.
which is
2029 N75-S Islamabad - Lower Topa - 01 (54+000 - 13+000) SB Primary or trunk 42 2636 50 mm Overlay with Deep Patching 55+000 43+000 12 130 mm Mill & Fill 12 54+800 to
651.623 20.169 242.032 Core thickness is
tourist dera supposed 10 cm

27 1,026.623 431.036
Unit rate Cost
S. No. Road name NHA Desired section Year HDM-IV Section Work Description as per HDM-IV Length (Km) Core info Site Visit Notes Remarks Previous AMP's
(Million) (Million)

This section is already Surveyed for AMP 2022-23, Rehabilitation is proposed to the following sections
855+000 - 868+000 855+000 - 868+000
1 N-55 (Direction not mentioned) 0

831+000-886+000 (AMP 2022-


23)
700+000 - 703+000
707+000 - 709+000 Km 715 = 6 Cm
726+000 - 730+000
2 N-55 2036 N55-N Kotri - Peshawar - 17 (700+000 - 768+000) 50 mm Overlay with Deep Patching 19.5 Km 620 = 15 cm 19.29343899 376.222060305
744+000 - 748+000
Km 668 = 14 cm
763+000 - 769+000
(Direction not mentioned) AMP 2018-19
700+000 - 707+000

615+000 - 617+000
3 N-55 627+000 - 630+000 2034 N55-N Kotri - Peshawar - 14 (610+000 - 638+000) 30cm GB + 13 cm AC REHAB 10.7 33.72057464 360.810148648
633+625 - 639+325
(Direction not mentioned)

4 N-5 1047+000 - 1053+000 (NB) 2035 N5-N Karachi - Torkham - 18 (1033+000 - 1064+000) 30cm GB + 13 cm AC REHAB 6 33.72057464 202.32344784

5 N-5 2035 N5-S Karachi - Torkham - 21 (949+000 - 852+000) 30cm GB + 13 cm AC REHAB 4.8 33.72057464 161.858758272
847+400 - 852+200 (SB)
6 N-5 858+000 - 862+000 (SB/NB) 2025 N5-S Karachi - Torkham - 22 (851+000 - 790+000) 50 mm Overlay with Deep Patching 16 229.81032448 Core assumed 5 cm
835+000 - 847+000 (SB) 14.36314528
7 N-5 2030 N5-N Karachi - Torkham - 12 (851+000 - 869+000) 50 mm Overlay with Deep Patching 4 57.45258112 Core assumed 5 cm
14.36314528
765+000 - 784+000 (SB)
Km 767 = 18 cm In previous AMP
8 N-5 765+000 - 785+500 (SB) 2035 N5-S Karachi - Torkham - 23 (789+000 - 754+000) 30cm GB + 13 cm AC REHAB 20.5 Km 775 = 20 cm 33.72057464 691.27178012 Only 1.5 Km length need
maintenance

2035 N5-S Karachi - Torkham - 24 (753+000 - 714+000) 30cm GB + 13 cm AC REHAB 23 33.72057464 775.57321672
9 N-5 680+000 - 736+000 (SB)

2033 N5-S Karachi - Torkham - 25 (713+000 - 648+000) 30cm GB + 13 cm AC REHAB 33 33.72057464 1112.77896312
660+000 - 662+000
10 N-55 662+000 - 670+000 2022 N55-N Kotri - Peshawar - 16 (649+000 - 699+000) 130 mm Mill & Fill Overlay with Deep Patching 16 29.587519682 473.400314912 Core assumed 15 cm
685+000 - 691+000
635+000 - 685+000 (NB) 608+000 - 635+000
11 N-5 608+000 - 635+000 2025 N5-N Karachi - Torkham - 07 (609+000 - 713+000) 30cm GB + 13 cm AC REHAB 77 Km 623 = 17 cm 33.72057464 2596.48424728 635+000 - 685+000 (AMP
(NB) Km 615 = 4 cm 2017-18)
1- At km 322+000, Moro Toll Plaza is situated. 1- Section coordinates are corrected
2- Two lane cariageway with 0.8m inner and as per actual mile stone locations.
2.0m outer shoulder. 2- Major rehabilitation is
12 N-5 321+000 - 329+000 2025 N5-N Karachi - Torkham - 03 (251+000 - 340+000) Structrual 130 mm Overlay Milling 8 29.587519682 236.700157456 3- The pavement condition is very poor. Severe recommended in this section with
cracking, rutting and patch work is observed in 30cm WBM/ABC and 13cm Overlay
outer and inner lanes. with Milling.

7274.686000273
Proposed Sindh North Section
Recommended Section
Cost As per
Road Length Cost as per Sindh Unit rate Cost
S. No. NHA Desired section Year HDM-IV Section Work Description as per HDM-IV HDM-IV Work Description as per Sind North Proposel Direction Location Location Core info Site Visit Notes Remarks Previous AMP's
name (Km) North (Million) (Million) (Million)
(Million) From To

1 N-5 381+000-370+000 2025 N5-S Karachi - Torkham - 32 (399+000 - 369+000) 50 mm Overlay with Deep Patching 480.959936 130 mm Mill & Fill Overlay with Asphalt Deep Patching SB 381+000 370+000 9 Halani to Kandiaro 270.64
29.282
263.540
Muhib shah Rahim Yarkhan To Village sain Dino
2 N-5 607+000-603+000 2022 N5-S Karachi - Torkham - 28 (608+000 - 584+000) 130 mm Mill & Fill Overlay with Deep Patching 646.21328345 130 mm Mill & Fill Overlay with Asphalt Deep Patching SB 607+000 603+000 11 Malik Ghotki Sindh
291.1
29.282
322.104

3 N-5 490+000-486+000 2022 N5-S Karachi - Torkham - 29 (583+000 - 488+000) 130 mm Mill & Fill Overlay with Deep Patching 2481.459008448 130 mm Mill & Fill Overlay with Asphalt Deep Patching SB 490+000 486+000 4 Rohri Bypass To Kundi Form 105.84
29.282
117.129

4 N-55 430+000-436+000 2025 N55-N Kotri - Peshawar - 09 (406+000 - 472+000) 30cm GB + 13 cm AC REHAB 2137.753472 130 mm Mill & Fill Overlay NB 430+000 436+000 6 Ratodero Khanpur Shikarpur
Km 435= 15 cm
119.17
27.755
166.533
Km 11+000-45+061
5 LKBP 21+000-33+000 2022 LKBP Larkana - Khairpur - 02 (16+000 - 56+000) Structrual Overlay (130mm with Milling) 1132.233359718 130 mm Mill & Fill Overlay 21+000 33+000 12 Larkana Khairpur Bridge 294.164
27.755
333.066 AMP 18-19

As per Larkana maintenance unit M-8


starts from Rato Dero and as per
Khuzdar Maintenance unit, M-8 starts
from Khuzdar

230+000-212+000 230+000 212+000 Km 218= 18 cm As per our data collected M-8 starts from
6 M8 2023 M8 Khuzdar - Ratodero - 05 (203+000 - 250+000) 50 mm Overlay with Deep Patching 744.712128 130 mm Mill & Fill Overlay (with treated Hard Shoulder) 12 Sajawal To Shahdad Kot
Km 228= 19 cm
503.747 29.282 351.386 khuzdar and ends at Rato dero
212+000-213+000 212+000 213+000
Larkana maintenance unit also suggested
that there should be one start point
thus as per requirements on site Km 19
is 230 & Km 37 is 212 in our data base

Not Included in Unconstraion Program


7 N-55 281+000-335+000 281+000-335+000 130 mm Mill & Fill Overlay 130 mm Mill & Fill Overlay NB 281+000 335+000 15 Wagan Larkan To Ratodero 367.705
27.755
416.332 (HDM-IV work Program)
69 1952.366 1970.090
Team A budget Summery

Approved Cost HMD-IV Cost

Team - A - 30916.89336
Team - B - 39438.372
Previously non executed 23283.140608
NHA Desired Sections 20188.84718611
N-75 - 1026.623104
Sindh North Required section - -
Punjab South Required Section - -
Total 114853.9
dget Summery
Revised Cost in millions
Estiamte Engineer Cost
(After deducting sections of
(CSR-2022)
provious AMP's)
19077.10 #REF!
22000.30 25000.3
7392.00 7392.003674832
1388.10 1388.104010028
431.04 431.03617491
1970.09 1970.08982292
7274.69 7274.686000273
59533.32 #REF!
Roads for AMP 2022-23
Road C/way
S. No. Location Remarks NHA Response
name Type

Any SM Works? (if yes, chainages


1 N-35 Hassanab dal Khunjrab Single
information required)

Under Project or any SM works


2 N-140 Chitral- Shandur Single
(chainages required) ?

Rehabilitation of Bahrain - Kalam Road N-


95
(Bahrain - Chimgarh)
3 N-95 Chakdara - Kalam Single (Chimgarh - Asrit)
(Asrit - Pashmal )
(Pashmal - Kalam )
(Chainages required)

Under Project?
4 N-5A Lodhran - Khanewal Dual
(If yes chainages are required

Status of dualization also any SM Works?


5 N-55 Kotri - Peshawar Dual
(Chainages required)

Construction of Faisalabad-Khanewal
Motorway M-4 (Dinpur - Khanewal
6 M-4 Multan - Pindi Bhattian Dual Section) Package-IIIB
Or any other SM Works or Project
(Chainages information required)

Consultancy services for Design review


and construction supervision of
dualization of Khuzdar -kuchlak section N-
7 N-25 Karachi - Chaman Single
25, Length =320.52 Km

(chaianges information required)

Any SM Works?
8 LKBP Larkana - Khairpur Single
(If yes, Chaianges information required)

Widening and Strengthening of National


9 N-70 Multan - Qillah Saifullah Single Highway N-70 Rakhi-Gaaj-Bewata
Section Package-IA

Any SM Works?
10 N-10 Uthal - Gawadar Single
(If yes, Chaianges information required)

Any SM Works?
11 N-65 Sukkur - Quetta Single
(If yes, Chaianges information required)
Roads for AMP 2022-23
Road C/way
S. No. Location Remarks NHA Response
name Type

Under Project or any SM works


12 N-120 Mirpur Khas - Khokhrapar Single
(chainages required) ?

Any SM Works? (if yes, chainages


13 N-40 Lakpass - Taftan Single
information required)

Any SM Works? (if yes, chainages


14 N-5 Karachi Torkham Dual
information required)

Any SM Works? (if yes, chainages


15 N-50 Kuchlak - DI Khan Single
information required)

Construction of Khuzdar-Shadadkot
Section of Gawadar - Ratodero Road M-8
16 M-8 Khuzdar - Rattodero Single
Section-IV, Package-III
( Chainages information required )

Any SM Works?
17 N-90 Khwuwazakhela - Besham Single
(If yes, Chaianges information required)

Any SM Works?
18 N-45 Nowshera - Chitral Single
(If yes, Chaianges information required)

Lahore Eastern Bypass Project (LEBP)


19 LEBP Lahore Eastern Bypass Dual Package-I Status?
(chainages required)

Any SM Works?
20 M-1 Islamabad - Peshawar Dual
(If yes, Chaianges information required)

Any SM Works ?
21 N-15 Mansehra - Chilas Single
(If yes chainages information required)