Name of Employee

Vikash Sharma
Designation
Field Quality Control Engineer
Region Name
Bharatpur, Block: Deeg, Location: Kaman-Pahari
Project Name
Various OTMP Works under Jal Jeevan Mission, Rajasthan
Name of the Month
April
S. No. Date Description
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
on.
Day-1 1-Apr-2024
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Work is completed upto 3rd lift of column above 3rd brace
beam. Shuttering work is going on for 3 rd brace beam.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
on.
Day-2 2-Apr-2024
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Work is completed upto 3rd lift of column above 3rd brace
beam. Shuttering work is going on for 3 rd brace beam.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
on.
Day-3 3-Apr-2024
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Work is completed upto 3rd lift of column above 3rd brace
beam. No work at site due to some issue from labour side.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is
stopped due to some issue from contractor side.
Day-4 4-Apr-2024
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Steel cutting work is going on for 3rd brace beam.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
on.
Day-5 5-Apr-2024
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Work is completed upto 3rd lift of column above 3rd brace
beam. Steel laying work is going on for 3 rd brace beam.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
on.
Day-6 6-Apr-2024
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Work is completed upto 3rd lift of column above 3rd brace
beam. Steel laying work is going on for 3 rd brace beam

Day-7 7-Apr-2024 Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari


Detail: Excavation & Laying Work of 125mm hdpe pipe is going
on.
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Steel laying shuttering work is completed for 3 rd brace
beam
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
Day-8 8-Apr-2024 on.
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Concrete work is completed for 3rd brace beam.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
Day-9 9-Apr-2024 on.
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Deshuttering work is going on for 3 rd brace beam.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
Day-10 10-Apr-2024 on.
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: No work at site due to some issue from labour side.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
Day-11 11-Apr-2024 on.
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: No work at site due to some issue from labour side.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
Day-12 12-Apr-2024 on.
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: No work at site due to some issue from labour side.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
Day-13 13-Apr-2024 on.
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: No work at site due to some issue from labour side.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: No work at site due to some issue.
Day-14 14-Apr-2024
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: No work at site due to some issue from labour side.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: No work at site due to some issue.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Day-15 15-Apr-2024 Detail: Steel binding & Shuttering work of 1 st lift of column
above 2nd brace beam is completed.

Site 3: Rising Main Pipeline, Nogawan,Tehsil – Kaman


Detail: Excavation & Laying Work of 90mm hdpe pipe is Started
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying of 125mm HDPE pipeline work.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Detail: Concrete work of 1st lift of column above 2nd brace beam
Day-16 16-Apr-2024
is completed.

Site 3: Rising Main Pipeline, Nogawan,Tehsil – Kaman


Detail: Excavation & Laying Work of 90mm hdpe pipe is going
on
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of remaining 1000mtr of
125mm hdpe pipeline work.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Day-17 17-Apr-2024
Detail: Steel binding & Shuttering work of 2nd lift of column
above 2nd brace beam.

Site 3: Rising Main Pipeline, Nogawan,Tehsil – Kaman


Detail: Excavation & Laying Work of 90mm hdpe pipeline work.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Length measurement of 125mm hdpe pipe from TW1,
TW2 to CWR is completed.Total length measured 6436mtr

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Day-18 18-Apr-2024 Detail: Concrete work of 2nd lift of column above 2 nd brace
beam is completed.

Site 2: Distribution Pipeline, Nogawan,Tehsil – Kaman


Detail: Excavation & Laying Work of 75mm, 110mm, 160mm
HDPE pipeline work.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: No work at site.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Day-19 19-Apr-2024 Detail: Steel binding & Shuttering work of 3rd lift of column
above 2nd brace beam.

Site 3: Distribution Pipeline, Nogawan,Tehsil – Kaman


Detail: No work at site.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: No work at site.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Day-20 20-Apr-2024 Detail: Shuttering work of 3rd lift of column above 2 nd brace
beam.

Site 3: Distribution Pipeline, Nogawan,Tehsil – Kaman


Detail: No work at site.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: No work at site.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Day-21 21-Apr-2024 Detail: No work at site.

Site 3: Distribution Pipeline, Nogawan,Tehsil – Kaman


Detail: Excavation & Laying Work of 75mm HDPE pipeline
work.
Site 1: Gangora, Chapra,Tehsil – Pahari
Detail: No work at site.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Day-22 22-Apr-2024 Detail: No work at site.

Site 3: Distribution Pipeline, Nogawan,Tehsil – Kaman


Detail: Excavation & Laying Work of 75mm HDPE pipeline
work.
Site 1: Rising main pipeline,Gangora, Chapra,Tehsil – Pahari
Detail: 235mtr length of 90mm HDPE pipeline connection from
TW3 to main rising line of 125mm HDPE pipeline.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Day-23 23-Apr-2024 Detail: shuttering work of 3rd lift of column above 2nd brace
beam.

Site 3: Distribution Pipeline, Nogawan,Tehsil – Kaman


Detail: Excavation & Laying Work of 75mm HDPE pipeline
work.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: No work at site.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Detail: Casting work of 3rd lift of column above 2nd brace
Day-24 24-Apr-2024
beam.

Site 3: Distribution Pipeline, Nogawan,Tehsil – Kaman


Detail: Excavation & Laying Work of 75mm HDPE pipeline
work.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: No work at site.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Detail: Scaffolding work of 1st brace beam.
Day-25 25-Apr-2024
Site 3: Distribution Pipeline, Nogawan,Tehsil – Kaman
Detail: Excavation & Laying Work of 75mm HDPE pipeline
work. Excavation of 100KL CWR is completed withoult approved
drawing.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: No work at site.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Detail: Steel work of 1st brace beam & deshutteting of 3rd lift
Day-26 26-Apr-2024
column below 1st brace beam.

Site 3: Distribution Pipeline, Nogawan,Tehsil – Kaman


Detail: Excavation & Laying Work of 75mm HDPE pipeline
work.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: No work at site.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Day-27 27-Apr-2024
Detail: Centring & Scaffolding work of 1st brace beam.

Site 3: Distribution Pipeline, Nogawan,Tehsil – Kaman


Detail: Excavation & Laying Work of 75mm HDPE pipeline work.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: No work at site.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Day-28 28-Apr-2024
Detail: Centring & Scaffolding work of 1st brace beam.

Site 3: Distribution Pipeline, Nogawan,Tehsil – Kaman


Detail: No work at site.
Site 1: Kherli Gumani, Kaman 250KL ESR, 18mtr staging
Detail: Finishing work of whole structure.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Day-29 29-Apr-2024
Detail: Steel work of 1st brace beam.

Site 3: Distribution Pipeline, Nogawan,Tehsil – Kaman


Detail: No work at site.
Site 1: Sablana,Kaman 350KL ESR, 18mtr staging.
Detail: Pipes (outlet, inlet, overflow, washout) installa work.

Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari


Detail: Steel work is completed. Shuttering work of 1st brace
Day-30 30-Apr-2024
beam.

Site 3: Kanwara, Kaman 250KL ESR, 18mtr staging


Detail: All DI pipes & accessories for outlet, inlet, overflow,
washout are received today.
Signature