Vikash Sharma
Designation
Field Quality Control Engineer
Region Name
Bharatpur, Block: Deeg, Location: Kaman-Pahari
Project Name
Various OTMP Works under Jal Jeevan Mission, Rajasthan
Name of the Month
April
S. No. Date Description
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
on.
Day-1 1-Apr-2024
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Work is completed upto 3rd lift of column above 3rd brace
beam. Shuttering work is going on for 3 rd brace beam.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
on.
Day-2 2-Apr-2024
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Work is completed upto 3rd lift of column above 3rd brace
beam. Shuttering work is going on for 3 rd brace beam.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
on.
Day-3 3-Apr-2024
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Work is completed upto 3rd lift of column above 3rd brace
beam. No work at site due to some issue from labour side.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is
stopped due to some issue from contractor side.
Day-4 4-Apr-2024
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Steel cutting work is going on for 3rd brace beam.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
on.
Day-5 5-Apr-2024
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Work is completed upto 3rd lift of column above 3rd brace
beam. Steel laying work is going on for 3 rd brace beam.
Site 1: Rising Main Pipeline, Gangora, Chapra,Tehsil – Pahari
Detail: Excavation & Laying Work of 125mm hdpe pipe is going
on.
Day-6 6-Apr-2024
Site 2: Dheemri 300KL ESR, Staging 18Mtr, Tehsil – Pahari
Detail: Work is completed upto 3rd lift of column above 3rd brace
beam. Steel laying work is going on for 3 rd brace beam