PBSCE 025

CONSTRUCTION METHODS AND PROJECT MANAGEMENT


NETWORK DIAGRAM

ACTIVITY:
Short Bond Paper
Handwritten

From the following information:


a. Construct a network diagram.
b. Identify all paths and their corresponding duration.
c. Identify the critical path.

I.
Activity Precedes Estimated Time (weeks)
A B 15
B C, D 13
C E 8
D END 5
E END 3

II.
Activity Precedes Estimated Time (weeks)
F G,H 10
G I,J 10
H J 8
I END 6
J K 12
K END 7