Professional Documents
Culture Documents
Sewer System Modeling V8 I
Sewer System Modeling V8 I
TRN014280-1/0005
Trademark Notice
Bentley and the "B" Bentley logo are either registered or unregistered trademarks or
service marks of Bentley Systems, Incorporated. All other marks are the property of their
respective owners.
AccuDraw, MDL, MicroStation, and SmartLine are registered trademarks; PopSet and
Raster Manager are trademarks.
Copyright Notice
Workshop
CSO Analysis
Designing a New System
Gravity and Pressure Length: 2-3 hours
Length: 2-3 hours
Length: 2 - 3 hours
Presentation:
Presentation • Model Calibration
Presentation • Design of Gravity Systems
• Force Mains and Pumps
Workshop
Workshop
Workshop
Nov-14 3 Agenda
Agenda ____________________________________________ 3
Module Prerequisites
• Modeling Basics
Module Objectives
After completing this module, you will be able to:
• Switch solvers within SewerGEMS
• Draw a schematic model
• Duplicate, edit and rename FlexTables
• Use the Sanitary Load Control Center to apply unit loads to manholes
• Setup extreme flows to apply peaking factors to unit loads
• Create and edit new scenarios, calculation options, and profiles
• Use the Unit Sanitary (Dry Weather) Loads manager to import unit loads
• Apply color coding and annotation to models
Problem Statement
In this exercise you will first analyze the performance of a proposed commercial
development, composed of predominantly 200 mm lines, for the initial average
dry weather loading conditions and review the results. Next, you will analyze the
performance of the system with a peaking factor by creating a new alternative
and scenario for this condition.
MH-4 32 31.09
Note: Real elevation data should be entered to at least 0.03 m precision. Initially all of
the conduits will be 200 mm with a user defined length of 121.92 m.
Getting Started
In the next few exercises, you will be setting up the SewerGEMS project
properties. You will set up the prototypes and import your Engineering Libraries.
Note: You may receive a warning message about the new database format in SS4 like
the one shown here. If so, please click OK to continue.
3 Once the new project is created, select File > Save As and name the
project GravityNetworkSteady.stsw and click Save.
kinematic wave solution and a uniform flow solution, which does not account
for any backwater effects. The Explicit dynamic solver simultaneously solves
for both flow and hydraulic grade and uses the same equations for gravity and
pressure portions of the system. It can be applied to storm, sanitary and
combined sewer, especially systems without a great deal of force mains or
pressure sewers.
• GVF - Convex (SewerCAD): Separates the hydraulic problem first into a set of
gravity subnetworks and pressure subnetworks. For the gravity subnetworks,
it divides the solution into a flow routing problem using convex routing (a
hydrologic routing method) and then solves for hydraulic grade (including
depth and velocity) using gradually varied flow (GVF) (backwater) equations.
For the pressure subnetworks, it uses a true pressure solver as found in
Bentley's WaterGEMS. It can perform extended period simulations and steady
state simulations and can base steady simulations on an extreme flow factor
method that reduces peaking factors as the flow increase moving
downstream. The solution method was developed for the SewerCAD model. It
can be applied to sanitary and combined sewers, especially those with a great
deal of pumping or pressure sewers, and those which only require a steady
state analysis.
• GVF - Rational (StormCAD): Uses flows developed by the rational method (plus
other additional flows). The solver routes values for CA downstream while
decreasing peaking factors due to longer time of concentration moving
downstream. Once flows are determined, hydraulic grade (including depth
and velocity) are determined using gradually varied flow (GVF) methods for
both gravity and pressure pipes. This solution method was originally
developed for the StormCAD model. It can be applied to stormwater systems.
Implicit solver is the default solver for a new project. We will now switch to GVF -
Convex solver.
3 Under the General section, find Active Numerical Solver and choose GVF -
Convex (SewerCAD).
Conduit Catalog
Next, you need to set up the default conduit properties that you will use in the
model. To do this, you will need to enter them in the Conduit Catalog.
5 Click in the check box in front of Circle - Concrete then click Select to select
that catalog.
Note: You should see all of the different circular concrete pipe sizes listed underneath
that category. All of these sizes are now available in your project's conduit
catalog.
6 Select Close.
7 You should save your file periodically by selecting the Save button or by
selecting File > Save.
8 Select Tools > Options.
Note: If you wish to use SI units for all new projects, select SI from the dropdown
menu for Default Unit System for New Project.
11 Click OK to close out of the Options dialog.
Project Properties
The first step is to enter the project properties. This step is not necessary, but it is
good to enter some notes and information about the project.
Drawing Options
Next, you will need to set some drawing options.
Note: Setting the drawing mode to schematic means that you will be manually
entering the pipe lengths instead of using scaled lengths.
Prototypes
The next step is to set up some prototypes to specify default and recurring values
for any new elements that you draw. All of the pipes in this project are concrete
and their inverts will be determined by their upstream and downstream
structures. Although different pipe sizes may be used in the project, the majority
of the pipes are 200 mm. You can use the Conduit Prototype to enter these values
and cut down on the amount of time dedicated to data entry.
Note: Your pointer should now change to have a triangle next to the cross-hairs.
3 Click in the bottom left area of the drawing to lay out the outfall OF-1.
Note: Notice that as you move your mouse around, there is a pipe that is connected
to your pointer.
The next element that you want to draw is manhole MH-1.
4 Right click in the empty area above and to the right of OF-1 and on the
right click menu, select Manhole.
5 After selecting Manhole from the right click menu, click in the drawing to
lay out MH-1.
6 Move the pointer to the right of MH-1.
7 Lay out MH-2 to the right of MH-1.
8 Continue and lay out MH-3 to the right of MH-2.
9 Then right click on an empty area of the drawing and select Done.
10 In the drawing click on MH-1 to begin drawing the next pipe run from MH-
1.
11 Move straight up from MH-1 and draw MH-4.
12 Move to the right of MH-4 and draw MH-5 and then MH-6.
13 Right click and select Done.
The drawing should look like this now:
14 In the drawing, click on MH-4 to begin the next section of the model.
15 Draw MH-7 above MH-4 and then drag the mouse to the right of MH-7
and draw MH-8 and MH-9.
16 Right click and select Done after that.
You could continue clicking on each element one by one and entering the
data in the Properties manager. However, a quicker way to enter data is
using the FlexTables.
Note: The reason why you did not want to create the new table under Tables - Shared
is because this new table would then be available for use in future projects in
addition to this project. By creating this table in the Tables – Project category,
the table will only been available in this single project.
3 Double click on the Copy of Manhole Table.
4 Enter the invert elevations and ground elevations from the Manhole Data
Table listed in the Problem Statement section.
Once you have entered the elevations, the table should look like this:
4 Under the Available Columns section, find Has User Defined Length? in
the list and double click on it to add it to the Selected Columns section.
5 Repeat step 4 for Length (User Defined).
6 Click OK to go back to the FlexTable.
7 Scroll all the way to the right so you can see these new columns.
8 Make sure that all of the boxes are checked for the Has User Defined
Length? field.
9 Right click on the Length (User Defined) column heading and select Global
Edit.
10 On the Global Edit dialog set the following:
Operation: Set
Value: 121.9
11 Click OK.
12 Close the FlexTable: Copy of Conduit Table dialog and the FlexTables
manager.
Exercise: Importing Unit Sanitary (Dry Weather) Loads from the Engineering
Libraries
1 Select Components > Unit Sanitary (Dry Weather) Loads.
2 On the Unit Sanitary (Dry Weather) Loads dialog, click the Synchronization
Options button and select Import from Library.
This will open the Unit Loads Engineering Libraries.
4 Check the box next to Office and see that it will use 55.0 L/day/employee.
5 Repeat this for Hotel Per Customer and see that it uses 190.0 L/day/guest.
This will add a line for every node into the Sanitary Load Control Center.
3 The data for the sanitary loading is contained in the following table:
Note: Notice that all of the manholes have Office for the Unit Sanitary Load except
for manhole MH-6 which has Hotel Per Customer.
You can use the Global Edit feature to quickly enter this data.
4 In the Sanitary Load Control Center on the Manhole tab, scroll the table to
the right until you see the column for Unit Sanitary Load and Loading Unit
Count.
5 Right click on the Unit Sanitary Load column heading and select Global
Edit.
6 On the Global Edit dialog, set the following options and then click OK.
Operation: Set
Value: Office
All of the lines should now have Office for the Unit Sanitary Load.
7 Manually change MH-6 to Hotel per Customer.
8 Right click on the Loading Unit Count heading and select Global Edit.
9 On the Global Edit dialog this time, set the following options and click OK:
Operation: Set
Value: 200
10 Change MH-6 to 500 and change MH-13 to 1200.
Note: It is unnecessary to have unit loads displayed for many decimal places.
11 Change the precision by right clicking on the Loading Unit Count column
heading and choose Units and Formatting.
12 Set the Display Precision to 0.
The Sanitary Load Control Center should now look like this and have both
the Unit Sanitary Load and Loading Unit Count columns filled in:
13 Close the dialog and save the file when you are done.
Peaking Factors
Next, you need to assign peaking factor methods to the two loading types you are
utilizing in this project. For the first scenario, you will not need to enter peaking
factors because it is for average load conditions but you will need to enter values
other than one for subsequent runs.
3 In the Properties manager, select Avg Day Setup for the Extreme Flow
Setup.
Computing
Exercise: Calculating the model
1 Run the scenario by selecting the Compute button or by selecting Analysis
> Compute.
2 Review the results on the different tabs listed on the Detailed Calculation
Summary dialog that comes up.
Note: Many of the results you need to complete the Results Table at the end of the
workshop are found here. You may find the other results by double clicking on
the element and viewing the results section of the Properties manager for that
element.
Annotation
Exercise: Setting up annotation for conduits
1 Select View > Element Symbology.
2 Right click on Conduit and select New > Annotation.
3 In the Annotation Properties dialog, select Flow for the Field Name.
4 Delete any text under Suffix set the Y Offset to -2.4 and select Apply.
Color Coding
Next, we are going to color code the conduit velocity.
Profiles
Next you will draw a profile from MH-6 to the outfall.
4 Click on the Done button on the Select tool bar to get back to the Profile
Setup dialog.
This will close the Engineering Libraries dialog and populate the Extreme
Flows dialog with the Peaking Factor (SI) method.
5 Click Close.
Next, you need to assign the Extreme Flows to our sanitary loads.
4 Check the Use box for each unit load and then select Peaking Factor (SI) as
the Extreme Flow Method for each.
5 Click Close.
Now that you are done entering data, we have to duplicate the Calculation
Options to create the peak flow run.
2 To run the model, click on the Compute button or select Analysis >
Compute.
3 Review the results and complete the Results Table.
Results Table
Workshop Review
Now that you have completed this workshop, let’s measure what you have
learned.
Questions
1 Does this system appear to have adequate capacity?
2 Usually pipes are designed for a velocity of 0.6 m/s. Does this system meet
that criteria?
3 In this problem, why did you work with conduit flow in L/s?
Answers
2 Usually pipes are designed for a velocity of 0.6 m/s. Does this system meet
that criteria?
Most of the pipes exceed that velocity during peak flow. The ones that do
not are those with very low flow rates.
3 In this problem, why did you work with conduit flow in L/s?
The loads in L/d would give huge values for pipe flow while the default
flow rate of L/s would provide numbers easy to work with.
Module Overview
The purpose of this workshop is to introduce the pressure features in SewerGEMS
GVF-Convex solver. You will open an existing system file and enter the data for the
pressure elements. The drawing already includes the existing gravity pipes. For
this workshop, you will use the GVF-Convex solver. This course material has been
developed for the SewerGEMS V8i (SELECTseries 4) platform, at a minimum the
Version 08.11.04.54. Modelers currently using versions prior to SewerGEMS V8i
(SELECTseries 4), 08.11.04.54, are strongly encouraged to consider upgrading
today to start taking advantage of the latest features and interoperability
advantages of V8i.
Module Prerequisites
• Modeling Basics
• Gravity Collection Systems
Module Objectives
After completing this module, you will be able to:
• Open an existing (preloaded) model
• Draw pressure elements
• Enter pump characteristics
• Determine system head curves
• Model wet wells
Getting Started
In this section you will open an existing SewerGEMS file and review what has
already been entered for you.
3 Close out of the profile dialogs when you are finished reviewing them.
Use the following figure as a guide to layout the first part of the network:
2 Click on MH-1, move your cursor to the right toward the stream
(southeast direction), right click, select Wet Well from the menu and left
click to place.
3 Move your cursor to the left, right click to select Pressure Pipe (the cursor
will automatically change to a pressure junction) and place the node.
4 Right click, select Pump and place PMP-1.
5 Right click, select Pressure Junction and place J-2.
6 Hold down the Ctrl key to place the set of vertices click along the main
force main as shown in the figure above.
7 When you reach the end point right click, select Manhole and place MH-
18.
8 Right click, select Conduit, move the cursor to the left, right click to select
Outfall then place the node.
Note: Do not worry about the spacing of elements; you will use User Defined Length
to get the correct lengths.
9 Right click to select Done and then click the Select tool.
10 Add a parallel pump to the pump station, by clicking on the Layout tool,
selecting Pressure Pipe.
11 Click on J-1, then right click to select Pump and place PMP-2 parallel to the
first pump.
12 Right click, select Pressure Junction and click on J-2 to complete the
layout.
13 Click on the Select tool when finished.
The piping around the pump station should look roughly like this:
Note: You may need to drag around some labels to achieve this appearance. (If you
have made mistakes with element labels, you can correct them in the
Properties manager for the individual elements.)
Note: The best way to enter the elevation data is to double click on each element and
type in the value on the Properties manager.
2 Repeat for each element except for WW-1 which will be done in the
following exercise.
FM-1 4.6
FM-2 3.0
FM-3 3.0
FM-4 563.9
FM-5 3.0
FM-6 3.0
Note: You only need to enter data for one pump definition in this section because
both pumps share the same properties. (Do not worry about pump efficiency
data; you do not need it for this model. Initial status is not set with the pump
curve definition.)
The Pump Definitions dialog should look like this:
4 Click Close.
5 Double click on PMP-1.
6 Click in the Pump Definition field and select Pump Definition – 1 from the
drop down menu and notice that the Status (Initial) is set to On.
7 Repeat for PMP-2 except that for PMP-2, the Status (Initial) is set to Off.
8 Close out of all dialogs so you are back to the drawing pane.
2 If there are any problems, correct them and save the file.
This brings up the Pump Curve dialog. Here you can specify to view the
Head curve, Efficiency curve, or both, as well as specify the times to be
shown. Since this is just a steady state model there is ony time 0.00 hours.
2 Leave the default settings and click OK to bring up the pump curve.
You should see the following:
5 When the dialog opens, set the Maximum Flow to 63 L/s, check the box
for time 0.0, and click on the Compute button above the graph.
6 Close this dialog and click No to the question of whether to save the curve.
7 Fill out the table at the end of the workshop.
Note: Note that the * column shows a check for PMP-2 indicating that this property
was changed from its parent.
11 Close this dialog and switch the active scenario to 2Pumps.
12 Run the model.
The Pipe Report in the Detailed Calculation Summary should look like this:
4 Make Loads the current scenario by clicking the Make Current button.
Results Table
Workshop Review
Now that you have completed this workshop, let’s measure what you have
learned.
Questions
1 What is the Total Flow for the gravity portion of this system (flow to wet
well) and how does it compare with the pressure portion?
2 Review the results for PMP-1 and 2. How do the operating points of these
2 pumps relate to the design point?
3 Review the results for the force mains in the system. What is the headloss
gradient in mm/m for FM-4?
4 What is the velocity in FM-1? Is this appropriate?
Answers
Pump flow (each) (L/s) 36.2 (PMP-1) 20.9 (PMP-1) 36.2 (PMP-1)
0 (PMP-2) 20.9 (PMP-2) 0 (PMP-2)
1 What is the Total Flow for the gravity portion of this system (flow to wet
well) and how does it compare with the pressure portion?
Pumped flow is greater than inflow to wet well. Wet well level will be
dropping.
2 Review the results for PMP-1 and 2. How do the operating points of these
2 pumps relate to the design point?
Flow is less than design flow indicating that the head that the pump is
working against is greater than estimated during design. This could be
corrected by using a pump with higher head or increasing the size of the
pipe to reduce head loss. Remember also that this run was made with the
wet well nearly empty. As the wet well increases, head loss will decrease
and flow will increase.
3 Review the results for the force mains in the system. What is the headloss
gradient in mm/m for FM-4?
6.5 mm/m with one pump running, 8.5 mm/m with two running.
The beginning of this workshop will use the GVF convex solver. The dynamic
routing section will use the Implicit solver. This course material has been
developed for the SewerGEMS V8i (SELECTseries 4) platform, at a minimum the
Version 08.11.04.54. Modelers currently using versions prior to SewerGEMS V8i
(SELECTseries 4), 08.11.04.54, are strongly encouraged to consider upgrading
today to start taking advantage of the latest features and interoperability
advantages of V8i.
Module Prerequisites
• Modeling Basics
• Gravity Collection Systems
• Using Pumps and Forcemains
Module Objectives
After completing this module, you will be able to:
• Enter pattern loading data and assign patterns to manholes
Nov-14 75
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
Getting Started
76 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
Note: The system shown in the image has already been entered for you, including
data on pipe sizes, invert elevations, and lengths, as well as manhole ground
and sump elevations and dry weather sanitary average loads.
Wet Well Elevation Elevation Elevation Use High Elevation Diameter (m)
(Minimum) (Initial) (m) (Maximum) Alarm? (High Alarm)
(m) (m) (m)
Nov-14 77
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
Note: Make sure your Flow units are in L/s before entering the data below.
3 Select Pump Definition-1 to make sure the data entered is accepted and
the graph updates properly.
4 Close the Pump Definitions dialog.
78 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
Controls
You are now going to define the controls (a list follows) that will turn the pump on
and off.
• On if wet well elevation is above 17.37 m.
• Off if wet well elevation is below 14.63 m.
Nov-14 79
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
5 Click the ellipsis button next to the drop-down menu for Element and
select WW-1 from the drawing.
80 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
9 To specify the THEN Action to trigger the control, click the New Simple
Action ellipsis button for the THEN section.
10 Click the Select ellipsis button on the next line and pick PMP-1 from the
drawing.
Nov-14 81
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
When done, the first control statement should look like this:
82 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
Note: It is important to click the ellipsis button and create a new simple action/
condition and not to try modifying the current ones you will find in the drop-
down menu.
In this section you will walk through the steps to create your dry weather steady
state scenario.
Nov-14 83
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
6 Close out of the dialogs so that you are back at the drawing pane.
84 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
2 Close the User Notifications dialog and review the results in the Detailed
Calculation Summary dialog box that appears after calculation.
Note: A good way to observe the results is to view the profiles. Several have already
been created for you.
For example, select View > Profiles and open MH-1 to O-1.
3 Close the profile and fill in the results of in the table at the end of the
workshop.
Note: You can find results in the properties manager, FlexTables, annotations etc.
Nov-14 85
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
Setting up Patterns
For an EPS run, you must indicate the time of day loading patterns. In this system
all the manhole nodes follow the same pattern as given.
3 1
6 1.4
9 1.2
12 1.4
15 0.9
18 1.1
21 0.6
24 0.4
86 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
5 Fill out the remainder of the table using the information in the previous
table.
Nov-14 87
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
Setting up Diversions
Manhole MH-5 can overflow when the flow into it exceeds 315.45 L/s. To model
this, you need to set up a diversion at that node in accordance with the table.
0 0
315.45 0
630.90 252.36
88 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
Note: The new conduit should be pipe P-13 and its exact location and properties do
not matter.
Nov-14 89
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
Size: 900 mm
90 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
Note: Make sure the units are set to L/s before entering data.
All that you need to change for this scenario is the type of simulation you are
running and to create a scenario to apply those changes to.
Nov-14 91
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
92 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
4 Double click on EPS Dry and select EPS Run as the GVF/Pressure Engine
Calculation option.
5 Close the Properties manager and on the Scenarios manager, click Make
Current to make the EPS Dry scenario the current scenario.
Nov-14 93
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
94 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Steady/EPS Dry Weather Loading
8 Watch how when the pump is running and the wet well level drops, the
pump moves up its curve until it shuts off (operating point goes to 0,0).
Nov-14 95
Copyright © 2014 Bentley Systems, Incorporated
EPS Wet Weather Loading
9 Open one of the profiles (e.g. MH-1 to O-1), expand to full screen and
animate it by selecting the Play (Green) button. Observe the changes in
water level.
10 Fill in the table and answer the questions at the end of the workshop for
the steady state and EPS dry weather runs.
You will add a hydrograph to MH-1, MH-6, MH-10 and MH-12. To reduce your
typing in this workshop, you will use the same hydrograph for each manhole,
96 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
EPS Wet Weather Loading
except MH-12. Of course, in a real system each manhole will have its own
hydrograph based on flow measurement, which you will likely copy and paste
from some external source.
4 With No Wet Weather highlighted, click the New button to create a new
child alternative for the wet weather loading.
5 Name the alternative Wet Weather.
Nov-14 97
Copyright © 2014 Bentley Systems, Incorporated
EPS Wet Weather Loading
0 0 0
3.00 0 0
14.00 0 0
24.00 0 0
98 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
EPS Wet Weather Loading
Nov-14 99
Copyright © 2014 Bentley Systems, Incorporated
EPS Wet Weather Loading
10 Select the Graph button and view the graph of the hydrograph.
14 Next, highlight the Inflow (Wet) Collection field for manhole MH-6 and
click the ellipsis button to open the Inflow (Wet) Collection dialog.
15 Select New > Hydrograph Load.
100 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
EPS Wet Weather Loading
16 Instead of typing in the values again, highlight the first cell in the
hydrograph table and click Ctrl-V.
Note: Make sure you do not have an extra row after pasting the data in and make
sure that you have an entry for 24.00 hours. You can check the graph if you
would like.
17 Click OK.
18 Repeat this process for MH-1.
19 For MH-12, enter the hydrograph from the column labeled MH-12 in the
table at the beginning of this exercise.
20 Click OK when you are done entering the data.
The hydrograph should look like this:
Nov-14 101
Copyright © 2014 Bentley Systems, Incorporated
EPS Wet Weather Loading
When you are done, the Infiltration and Inflow: WetWeather dialog
should look like this:
102 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
EPS Wet Weather Loading
4 Double click on EPS Wet and in the Properties manager change the
Infiltration and Inflow alternative to Wet Weather.
5 Close this dialog and make EPS Wet the current scenario.
6 Save the file.
Nov-14 103
Copyright © 2014 Bentley Systems, Incorporated
EPS Wet Weather Loading
Note: In this case, there is an overflow in P-13 to O-2 between hour 5 and 9.
4 Examine the differences in pump operation between dry and wet weather
by right clicking on PMP-1, choose Graph and click OK.
104 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
EPS Wet Weather Loading
Note: You will see how the pump cycles during wet weather.
Nov-14 105
Copyright © 2014 Bentley Systems, Incorporated
Overview of the Scenario Comparison Tool
Note: The graph shows how the pumps cycle differently during the wet weather
event.
7 When you find time of max flow, set that as the time using the Time
Browser (Analysis > Time Browser).
8 If you have time, view some other profiles and graphs.
9 Save your file.
10 Complete the answers at the end of the workshop.
Since we have multiple scenarios in this model, let’s take a look to view the
differences between two of them.
106 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Overview of the Scenario Comparison Tool
5 Click OK.
Nov-14 107
Copyright © 2014 Bentley Systems, Incorporated
Overview of the Scenario Comparison Tool
The Scenario Comparison dialog will be updated to look like the image.
Note: As you can see, all the available alternatives are listed in the left pane of the
dialog, and on the right you will see those same alternatives, except that the
alternatives that are different between each scenario are highlighted. Also,
note that for the Infiltration and Inflow alternative in the left pane, the icon
contains a red mark depicting that the alternatives are different between the
two selected scenarios. The icon with the green check indicates that there are
no differences.
6 Click on the Infiltration and Inflow alternative in the left pane.
Note: This will return a summary of the comparison which indicates the time when
the comparison was run, which scenarios were used, and the number of
elements and attributes for which there were differences.
108 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Overview of the Scenario Comparison Tool
Note: As you can see, you are shown that Inflow (Wet) Collection is different for four
manholes in the model.
9 Click the Select in Drawing button and choose Select in Drawing from the
menu.
Nov-14 109
Copyright © 2014 Bentley Systems, Incorporated
Dynamic Wave Routing using the Implicit Solver
10 Move the Scenario Comparison dialog out of the way and see that the four
manholes are selected in the model.
Exercise: Creating a new Physical Alternative for the side Weir at P-13
1 Select Analysis > Alternatives.
2 Expand Physical so you see the base alternative.
110 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Dynamic Wave Routing using the Implicit Solver
3 Rename the base alternative to Rating Curve at P-13 by using the Rename
button.
4 With Rating Curve at P-13 highlighted, click the New button to create a
new child alternative for the side weir.
5 Name the alternative Side Weir at P-13.
Nov-14 111
Copyright © 2014 Bentley Systems, Incorporated
Dynamic Wave Routing using the Implicit Solver
4 Double click on Dynamic Wet and in the Properties manager choose Side
Weir at P-13 for Physical Alternative.
5 Close the Properties manager and on the Scenarios manager, click Make
Current to make Dynamic Wet scenario the current scenario.
112 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Dynamic Wave Routing using the Implicit Solver
4 Click in the Start Control Structure field and select <Edit Conduit Control
Structures>.
5 In the Conduit Control Structures dialog that opens, select New > Weir and
enter the following information:
Crest Elevation (m): 34.93
Has Flap Gate? False
Structure Top Elevation (m): 35.97
Weir Type: Side weir
Side Weir Coefficient: 1.66
Weir Length (m): 1.2
6 Close this dialog and make sure Control Structure -1 is selected as the Start
Control Structure for P-13.
Nov-14 113
Copyright © 2014 Bentley Systems, Incorporated
Dynamic Wave Routing using the Implicit Solver
Exercise: Calculating with the dynamic wave solver and reviewing results
You are now ready to run the dynamic wave solver.
1 Make sure your current scenario is set to Dynamic Wet.
114 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Dynamic Wave Routing using the Implicit Solver
Nov-14 115
Copyright © 2014 Bentley Systems, Incorporated
Dynamic Wave Routing using the Implicit Solver
6 View the results and fill in the last column of the table.
Note: The differences between the diversions and the weir are due to those
two approaches not matching. You could adjust the weir or the
diversion to make them match fairly closely.
You may want to create a profile along some path and animate it as you did with a
previous run.
116 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Results Table
Results Table
Fill in the table and answer the questions on the next page.
Workshop Review
Now that you have completed this workshop, let’s measure what you have
learned.
Questions
1 Are there overflows in the system? When?
2 Does the pump have enough capacity for the flows? Why?
3 What is the ratio of maximum flow at the outfall between wet and dry
days? Is that high?
Nov-14 117
Copyright © 2014 Bentley Systems, Incorporated
Workshop Review
Answers
2 Does the pump have enough capacity for the flows? Why?
Yes, but during the wet weather peak flows it takes a long time to pump
down the wet well. It is pretty much on continuously.
3 What is the ratio of maximum flow at the outfall between wet and dry
days? Is that high?
About 2 to 1. It is fairly high for a sanitary sewer system which indicates I/I
problems.
118 Nov-14
Copyright © 2014 Bentley Systems, Incorporated
Geospatial Data Tools (metric)
Module Overview
In this workshop you will be given data in the form of shapefiles to construct a
model. You will use ModelBuilder, TRex and LoadBuilder to create and run the
model for normal flow and peak flow conditions. You start with a blank model file
and end up with a complete workable model. You will use the GVF-Convex Solver
for this exercise although all model building tools apply to all solvers. This course
material has been developed for the SewerGEMS V8i (SELECTseries 4) platform, at
a minimum the Version 08.11.04.54. Modelers currently using versions prior to
SewerGEMS V8i (SELECTseries 4), 08.11.04.54, are strongly encouraged to
consider upgrading today to start taking advantage of the latest features and
interoperability advantages of V8i.
Module Prerequisites
• Modeling Basics
Module Objectives
After completing this module, you will be able to:
• Build a sewer model from shapefiles using ModelBuilder
• Import node elevations using TRex
• Import loading data using LoadBuilder
• Import a shapefile as a background image
Getting Started
Check to make sure that the files below are in the following location: C:\Bentley
Workshop\SewerModelingSI\Starter\GISData.
• BillingMeter.shp
• Contours.shp
• GravityPipe.shp
• ManholeNodes.shp
• PictureOfNetwork.jpg
You may not have any software to view these files on your workshop computer. If
you do, open these files and view them. If you do not, open the
PictureOfNetwork.jpg to view the image.
ModelBuilder
In this section you will use the ModelBuilder tool to build your network.
ModelBuilder lets you use your existing GIS data to construct a new model or
update an existing model. ModelBuilder supports a wide variety of data formats,
from simple databases (such as Access and DBase), spreadsheets (such as Excel or
Lotus), GIS data (such as shape files), to high end data stores (such as Oracle, and
SQL Server), and more. Using ModelBuilder, you map the tables and fields
contained within your data source to element types and attributes in your
SewerGEMS model. The result is that a SewerGEMS model is created.
ModelBuilder is the first tool you will use when constructing a model from GIS
data. The steps that you take at the outset will impact how the rest of the process
goes.
Note: You must now specify the data source you will be using for your network.
8 For Select a Data Source type, select ESRI Shapefiles from the drop-down
menu.
9 For Select your Data Source, click the Browse button and navigate to;
C:\Bentley Workshop\SewerModelingSI\Starter\GISData and while
Note: The manhole file contains invert elevations and labels, while the pipes file
contains pipe description, diameter and Manning’s n.
13 Click the Next button and you will be on the Specify Spatial Options step.
14 The Coordinate Unit should be set to m.
15 Check the box for Create nodes if none found at pipe endpoint, although
with this data set it will not matter.
16 Check the box for Establish connectivity using spatial data because the
pipes in the shapefile in this example do not contain information about
their end points.
18 Click Next 3 times until you get to the Specify Field Mappings for each
table step (the defaults on the 2 steps we skip are fine for this exercise).
Note: This field mapping step enables you to associate specific fields in the shapefile
with properties in the model.
19 Highlight the ManholeNodes table on the left side of the screen and set
the following:
Table Type: Manhole
Key Fields: LABEL (not <label>)
X and Y Field: Leave as is
20 Under Field, select ELEV_INV as the shapefile field and in the Property
drop-down menu, select Elevation (Invert). Select meters (m) for the
Unit.On the left side of the ModelBuilder Wizard, highlight the GravityPipe
table.
21 Set the Table Type to Conduit.
22 Select LABEL for Key Fields and leave Start and Stop as <none>.
23 Set the following:
D: Diameter (inches) or (millimeters)
N: Manning’s n,
MATERIAL: Material.
24 Click Next.
25 Select the Yes radio button for the question, Would you like to build a
model now? and then click Finish.
Note: If you are prompted with the following screen, click Yes to accept.
Note: The ModelBuilder Wizard will create a model and display the ModelBuilder
Summary dialog, indicating that 155 conduits and manholes were created, plus
an additional node corresponding to the outfall.
29 If the model does not appear on the screen, select View > Zoom > Zoom
Extents to bring up the drawing.
The model should look like this:
Note: Notice that the Elevation (Ground) is 0. You will need to import ground
elevations from a contour shapefile.
Note: This is more important when large files are used as a data source.
7 For this dataset it does not matter if you check the box for Also update
inactive elements.
Note: The message means that two nodes fell outside of the contour shapefile and
have no value for ground elevation.
Note: This manhole is actually the outfall of the system and must be morphed into an
outfall element.
2 To morph the element, select the Outfall element type, from the layout
menu and drop it on top of the manhole.
You will be prompted with the following:
6 Notice that it does not have an invert elevation; enter 77.72 as the
Elevation (Invert) (m).
The profile will automatically open up and looks like the one shown:
Note: You can see that the pipes slope downhill but you can also see areas where the
engineer could have selected better invert elevations to achieve a more
consistent slope.
4 Close the profile and save the file.
LoadBuilder
Next you will use LoadBuilder to import individual water meter billing data to load
the model. LoadBuilder is a tool used to assign flows to elements. If you already
know what flows to assign to an element, then you should use the other methods
such as inflow, sanitary loads, or stormwater loading. The power of LoadBuilder is
that it can take loading information from a variety of sources such as customer
meter data, system flow meter or polygons with known population or land use
and assign those flows to elements. LoadBuilder is oriented to the types of data
available to describe dry weather flows.
4 Click Next.
5 Select the ellipsis button next to Node Layer: and highlight Manhole\All
Elements as the nodes to be loaded.
6 Click Select.
7 For Billing Meter Layer, click the ellipsis button and browse to the starter
file folder to select the BillingMeter.shp file and click Open.
8 Click OK for this next message:
9 The Load Type Field should be set to TYPE, the Usage Field is USE and the
units are L/day.
10 Uncheck the Use Previous Run box since we have not computed the
model.
11 Click Next.
The Calculation Summary will appear.
12 This system has fairly low flows, so make sure the units of flow are L/s. If
they are not, right click on the Load column header and selecting Units
and Formatting.
13 Select L/s for the Unit so the raw data will be converted to L/s.
15 Leave the multipliers as they are because you are interested in average
flow for now.
16 Click Next.
17 The Results Preview will appear. Browse through the values of manhole
loads.
21 Click Finish and when compete, the following message should appear
indicating the number of records imported.
4 Click OK.
Note: Notice the two nodes at the far south that fall outside of the contour shape file.
Also notice where the streets (and pipes) are it is fairly flat.
5 You can turn off this background by un-selecting it in the Background
Layers manager.
Note: You will see that there are issues caused by two manholes with a ground
elevation lower than the manhole invert.
You will notice that two of the manholes did not have a ground elevation
because they were outside the bounds of the contour file.
4 Click the Initialize button (third button in on the right window pane).
Note: This indicates that the flows are very low in this system, typical of upstream end
of collection systems.
6 Find the flow at the outfall by double clicking the outfall node.
8 Click OK.
Note: Note which pipe has the maximum value for Depth/Rise (try using Sort >
Descending).
9 Set the tractive stress units to Pascals by right clicking on that value in the
Property manager (or column header in FlexTable), select Units and
Formatting, and set Unit: to Pascals.
10 Find the velocity and tractive stress in that pipe.
11 Fill in the results at the end of the workshop.
12 Save your file.
7 Click OK.
8 Make the Peak scenario the current scenario by selecting it from the
scenarios drop-down menu or by clicking the Make Current button in the
Scenarios manager.
9 Open the Sanitary Load Control Center (Tools > Sanitary Load Control
Center).
12 Click OK.
Results Tables
SewerCAD/SewerGEMS Sanitary Results Table
Property Average Load Peak Load
Workshop Review
Now that you have completed this workshop, let’s measure what you have
learned.
Questions
1 Were the velocities very high during average flow conditions?
3 If you could redesign the system, how would you have changed it?
Answers
Results Table
Property Average Load Peak Load
3 If you could redesign the system, how would you have changed it?
Because I had limited ground slope to work with, I would try to go deeper
at the downstream end. If I ended up being too deep, I would have
reviewed a very flat section of the system and looked at the possibility of
installing a lift station.
This course material has been developed for the SewerGEMS V8i (SELECTseries 4)
platform, at a minimum the Version 08.11.04.54. Modelers currently using
versions prior to SewerGEMS V8i (SELECTseries 4), 08.11.04.54, are strongly
encouraged to consider upgrading today to start taking advantage of the latest
features and interoperability advantages of V8i.
Module Prerequisites
• Modeling Basics
• Gravity Collection Systems
• Using Pumps & Forcemains
• Extended Period Simulations
Module Objectives
After completing this module, you will be able to:
• Use a Background file (dxf) to draw a network to scale
• Set design constraints and apply SewerGEMS automated design to size pipes
• Create and view engineering profiles
Note: If you do not see the background file, select View > Zoom > Zoom Extents.
Note: Notice that the elevations run from roughly 155 m to 150 m so you have very
little slope to work with. Also note that there are 4 lots, 17-20 that are on the
other side of a drainage divide. We will assume that these lots will have
individual grinder pumps to raise the wastewater to the first manhole.
3 Select the Units tab, click Reset Defaults > System International.
4 Click OK to go back to the drawing.
Network Layout
We are now ready to lay out the network.
Note: The last node element in the line is the outfall. When you are about to lay out
that node, right click and change from Manhole to Outfall.
Note: If you should happen to mess up the labeling of the elements, do not worry.
You can either re-label the elements in the FlexTables after you lay them out or
simply understand that your labeling is different from that in the instructions
and keep track of that fact.
3 Lay out the pipes in Knob Hill Court and Vista Court as shown in the
drawing on the next page.
4 When you tie the Knob Hill Court line into MH-3, right click and select
Done.
Note: Before you begin, you may want to right click at the top of the Label column
and select Sort > Sort Ascending to make sure the manholes are listed in the
correct order.
3 Enter the following ground elevations:
Structure Elevation (Ground) (m) Elevation (Invert) (m) Your Initial (m)
Structure Elevation (Ground) (m) Elevation (Invert) (m) Your Initial (m)
Note: The elevations in the column Elevation (Invert) are some quick and dirty initial
guesses as to what the invert elevation should be. However, as a design
engineer, you are not required to use them. Feel free to modify those values
and place them in the Your Initial column. Enter those values for Elevation
(Invert).
4 Make sure that Set Rim to Ground Elevation? is checked for all manholes.
10 In the Global Edit dialog, select Catalog Conduit in the Value: drop-down
menu and click OK.
11 Click in one of the Catalog Class fields and then click on the ellipsis button
that comes up.
This will bring up the Conduit Catalog manager.
12 Click on the Synchronization Options button and select Import from
Library.
13 In the Engineering Libraries manager expand Conduit Catalogs Conduits
Library - Metric.xml and circle.
14 Scroll down to Circle, PVC and click in the check box.
17 In the Global Edit dialog, select Circle - PVC for the Value field and then
click OK.
18 Right click the Size column heading and select Global Edit.
19 Select 300 mm for Value and click OK.
20 Use the Global Edit function on the Material column and set it to PVC.
21 Make sure Section Type is set to Circle for all conduits. If necessary use the
global Edit function on the Section Type column and set it to Circle.
The Conduit FlexTable in part should look like this:
2 When the dialog opens, click on the New button and select Count Based.
3 Rename it to NewResidential (use the red T on top of the left pane to edit
the name).
4 Enter Residential in the Count Load Unit field.
5 Make sure the Unit Load units are in L/day.
Note: If it is in some other unit, right click on the units, select Units and Formatting,
and change the Unit to L/day with 0 as the Display Precision.
6 Enter 1,514 L/day for Unit Load and 3 for Population Equivalent (people
per residence).
4 In the Global Edit dialog, select NewResidential for the Value: and click
OK.
MH-1 5
MH-2 4
MH-3 3
MH-4 3
MH-5 2
MH-6 2
MH-7 2
MH-8 4
MH-9 3
4 Check the box for Ten State Equation and then click on Select.
5 Next change the Population Unit for this equation to Capita x 103.
Exercise: Setting the calculation options to use the new extreme flow
1 Select Analysis > Calculation Options.
2 Double click on Base Calculation Options to bring up the Properties
manager.
3 Select Extreme Flow Setup – 1 for the Extreme Flow Setup field.
Note: You could have also opened the Sanitary Load Control Center.
3 Click on the New button and select Pattern Load – Base Flow and Pattern.
4 Enter 3.79 L/s for Base Flow and Fixed for Pattern.
Note: You may have to change the units to L/s before entering the values.
5 Click OK.
Note: Make sure the units for Infiltration Rate per Loading Unit is in L/day before you
enter the value below.
Infiltration Load Type Pipe Rise-Length
Infiltration Loading Unit mm-km
Infiltration Rate per Loading Unit 1,893 L/day
8 After each edit, click OK.
When you are done, the columns related to infiltration should look like
this:
If you had any validation errors the User Notifications dialog will list the
errors.
2 Click OK and save the file.
Note: You will see some messages that minimum velocity constraint was not met in
the User Notifications dialog. This is expected because of the flat slopes.
2 Browse through the different tabs to review the results.
Reviewing Results
There are many ways of viewing results, such as using the properties manager,
FlexTables, graphs, color coding etc. In this example, you will be using element
annotation.
Y Offset: -7.6
Note: You will now see the slope annotated on each pipe.
5 Double click on Label under Conduit in Element Symbology.
6 Change Y Offset to 7.6, click Apply and OK.
Note: Now the labels for the conduits will be above the pipes making them easier to
read.
Note: The manhole labels have been moved in the screen shot above so that the
annotation could be viewed more easily. You can move the labels on your end
as well if you would like.
5 Fill in the first column of the results table at the end of this workshop.
Profiles
It is also helpful to view the profile.
5 Close the Engineering Profile and Profiles manager to get back to the
drawing pane.
Automated Design
In this section you will set the options to have SewerGEMS design pipes using the
extreme flows you set up.
3 Click Close.
Design Constraints
You must now set constraints for the automated design. With this first design run,
we will be showing what happens when you do not have a velocity constraint. You
will get minimum slope for each pipe and all the rest of the elevation change
shows up in the last pipe. This is not very good, but it is what SewerGEMS does in
this situation.
2 The Velocity tab should show a Velocity (Minimum) of 0.00 m/s and a
Velocity (Maximum) of 4.57 m/s.
3 Click on the Slope tab and set the Slope (Minimum) to 0.003 m/m.
Note: The automated design will change the physical properties, so we need to create
a new Physical Alternative.
4 Click in the field for Physical and select <New…> from the drop-down
menu.
5 Name the new alternative Auto Size and click OK to get back to the
Properties manager.
7 In the Scenarios manager, make the Design scenario the current scenario
by clicking on the Make Current button.
You will see a red check mark on the scenario icon after you click that
button:
4 Click on the Node tab and for OF-1, uncheck Design Structure Elevation?.
5 Close out the Design Constraints Alternative: Base Design and Alternatives
managers.
Computing
You are now ready to compute the model and run the automated design.
The design run will go to completion and display the Detailed Calculation
Summary.
3 Review the summary and then close it.
Note: You will notice that you failed to meet the velocity constraint even though you
may have done better with steeper pipe slopes. This is because pipe slope is
generally controlled to minimize burial depth and that takes precedence over
velocity constraints. Note the slopes in the pipe to minimize cover.
Second Design
We are not satisfied with the design that we obtained and want to get higher
velocities and better slopes.
In this run we are going to constrain the minimum velocity to 0.3 m/s and the
minimum slope to 0.0075 m/m to get more reasonable slopes and velocities.
Note: The primary difference in this run is that you are going to force a minimum
slope in conduits CO-1 to CO-5 of 0.0075 with a maximum of 0.01.
5 Click in the Design field and select <New…> from the drop-down menu.
6 Name this alternative DesignWithSlope and click OK.
6 Check the Specify Local Pipe Constraint? for pipes CO-1, CO-2, CO-3, CO-4,
and CO-5 and enter 0.0075 m/m for their Slope (Minimum) and 0.010 m/
m for Slope (Maximum).
Note: You may need to right click at the top of the Slope (Minimum) column and
change Display Precision to 4.
10 Close out of the Calculation Summary and the User Notifications dialog if
it comes up.
The profile also looks better although excavation costs will be greater.
11 Fill out the table at the end of the workshop and think about which
solution you would recommend.
Results Table
Scenario
Note: Values may be slightly different because of the placement of the manholes can
differ from one individual to another.
Workshop Review
Now that you have completed this workshop, let us measure what you have
learned.
Questions
1 Did you have adequate velocities in this system in the initial design? Why?
3 What other way could you have served the 4 homes on the other side of
the drainage divide?
4 Would you prefer your original invert elevations or the values you got from
the first or second automated design? Why?
5 What else can you do about the low velocities in pipes CO-1 and CO-8?
Answers
Scenario
Note: Values may be slightly different because of the placement of the manholes can
differ from one individual to another.
1 Did you have adequate velocities in this system in the initial design? Why?
No. There was low flow with not much slope.
3 What other way could you have served the 4 homes on the other side of
the drainage divide?
Had their wastewater flow by gravity to a single small lift station and pump
over the divide.
4 Would you prefer your original invert elevations or the values you got from
the first or second automated design? Why?
The best solution is really a judgment decision trading off the extra
excavation costs with the better velocities. This is a tough problem
because you are dealing with some negative ground slopes.
5 What else can you do about the low velocities in pipes CO-1 and CO-8?
There really is not much you can do because the flow is very close to zero
most of the time. This is unfortunately typical in the small sewers at the
upper end of collection systems. If you looked at the depth of flow in CO-1,
you would have seen that it was on the order of 0.02 m.
Module Overview
In this workshop, you will use rainfall to drive the wet weather flow model.
Assume that you have flow monitoring data so that you know the coefficients for
unit hydrographs for each basin. You have collected flow data for four large
catchments and want to model the large storm sewers that receive this flow. You
will work with a schematic drawing in SewerGEMS that already has the sub-
watershed layout.
This course material has been developed for the SewerGEMS V8i (SELECTseries 4)
platform, at a minimum the Version 08.11.04.54. Modelers currently using
versions prior to SewerGEMS V8i (SELECTseries 4), 08.11.04.54, are strongly
encouraged to consider upgrading today to start taking advantage of the latest
features and interoperability advantages of V8i.
Module Prerequisites
• Modeling Basics
• Gravity Collection Systems
• Using Pumps & Forcemains
• Extended Period Simulations
• Dynamic Flow Routing
Module Objectives
After completing this module, you will be able to:
• Assign outflow nodes for catchments as well as enter and assign unit
hydrographs for catchments
Getting Started
This section walks you through opening an existing file and laying out a conduit
network. You will create and assign storm events for your model, assign
catchments to their associated manholes and convert rainfall runoff to system
flows using the Generic Unit Hydrograph Method.
1 To begin laying out the network, click on the Layout tool and select
Conduit.
2 Simply left click on your drawing to place the manholes and conduits at
the appropriate locations.
3 After you lay out MH-5, right click and select Outfall.
4 Place the outfall, then right click and select Done.
If necessary, click the Select tool to deactivate the Layout tool.
Note: You may wish to move each manhole label to just below the manhole by
dragging the labels to the desired locations.
Note: The easiest way to enter this data is to use the FlexTables.
2 Click on the FlexTables button or go to View > FlexTables.
Because the drawing is a schematic, you will want to change all the
lengths from scaled to user defined.
4 Right click on the Conduit Type column, select Global Edit and set to User
Defined Conduit.
5 Right click on the Material column, select Global Edit and set to Concrete.
This should automatically set the Manning's n to 0.013.
After you have entered in the manhole properties, your table should look
similar to the one here:
4 Set the Elevation (Ground) (m) to 8.23, and the Elevation (Invert) (m) to
6.71.
Note: The engineering library is a set of .xml files that you can share among the
people in your organization to standardize and to simplify entry of data you use
frequently, like design storms.
5 Expand Dimensionless Rainfall Curves and expand SCSTYPES.XML.
6 Click on TypeIII 24 hr and then click Select.
7 In the Generate Storm Event dialog that comes up, enter the following:
Curve Label: 2 Year
Return Event: 2
Depth Type: Cumulative
8 Click OK.
Your Storm Data dialog should look as follows:
3 Click Close.
3 For this catchment, MH-1 is the outflow node so click on MH-1 in the
drawing.
You will then see a dashed line from the catchment centroid to the
manhole and the Properties manager will be updated to reflect that MH-1
is the outflow node for CM-1.
4 Repeat these steps for the other 3 catchments.
In this workshop, you will convert rainfall to runoff to system flows using a
Generic Unit Hydrograph method. The coefficients that determine the shape of
the unit hydrograph for this approach are based on flow metering for a known
rainfall event. The unit hydrograph represents the response of each catchment to
a unit of (25.4 mm) rainfall. Each catchment, which represents a large number of
pipes and manholes that are not modeled here for simplicity’s sake, is
represented by its own unit hydrograph. The size and shape of the unit
hydrograph is determined by the size and slope of the catchment, its soil
properties and impervious cover, and the extent of depression storage.
1 For each catchment, verify that the following are set in their Properties
dialog:
Runoff Method: Unit Hydrograph
Loss Method: Constant Loss Rate
Constant Loss Rate (mm/hr): 0
Next you will enter in the hydrographs for each catchment given in the
table.
2 In the Property manager for CM-1, click in the field Unit Hydrograph Data
and click the ellipsis.
This opens the Unit Hydrograph Data editor for CM-1.
3 Enter the Time vs. Flow values given in the table for CM-1.
Warning: Make sure the units are correct before entering any data.
Flow (L/s)
4 Click OK.
5 Repeat this process for each catchment.
6 Save your file.
Note: Since this is a 24 hour storm, we will need to run the model longer than the 24
hour default duration.
1 Select Analysis > Calculation Options or click the Calculation Options
button in the toolbar.
2 Double click on Base Calculation Options to bring up the Properties
manager.
Reviewing Results
In this section you will compare your catchment flows using graphs and review
your water surface using profiles.
4 Find the peak flow and time to peak flow for each catchment and
complete the results table for Storm 1 found at the end of this workshop.
5 Click the down arrow next to the Chart Settings button and select Display
Annotation Labels to see the labels in the profile.
Historical Scenario
In this section you will create a new scenario based upon observed storm data
and calculate the scenario to review the results.
0 0.00
1 5.08
2 20.32
3 7.62
4 15.24
5 2.54
6 0.00
6 Click OK.
7 Enter the values given in the hyetograph table on the previous page.
8 Click Close.
Note: Note that each of the catchment flows is higher for this scenario (representing
the historical storm, where the previous scenario represented an SCS
hypothetical storm with the same 50.8 mm depth).
Hint: If you accidentally closed the Summary screen, you can reopen it by selecting
Report > Calculation Executive Summary.
4 Fill in the Historical Storm Table in the Results section at the end of the
workshop.
1 With the Historical Run scenario still active, select Edit > Select by
Element > Conduit to select all conduits in the model, then right click
them and select Graph.
2 Click OK on the Graph Series Options dialog to open the graph of flow vs.
time.
3 Select the Graph Series Options button, uncheck Flow and select Flow/
Capacity (Design) as the attribute to graph.
Results Tables
CM-1
CM-2
CM-3
CM-4
Historical Storm
Catchment Time to Peak (hrs) Peak Flow (L/s)
CM-1
CM-2
CM-3
CM-4
CO-1
CO-2
CO-3
CO-4
CO-5
Workshop Review
Now that you have completed this workshop, let’s measure what you have
learned.
Questions
1 Why are the peak flows higher for the second storm even though the
cumulative precipitation is the same for both storms?
3 Look at the profile. What would occur at the outfall to make the water
level behave like this?
4 The pipe sizes increased downstream but there was less excess capacity in
CO-4 than any other. What could explain that?
5 If the rainfall increased over these events, which manhole would overflow
first? Why?
Answers
Historical Storm
Catchment TIme to Peak (hrs) Peak Flow (L/s)
CO-1 47
CO-2 30
CO-3 72
CO-4 101
CO-5 39
1 Why are the peak flows higher for the second storm even though the
cumulative precipitation is the same for both storms?
Rain in the second storm occurred over a shorter period of time and thus
was more intense.
3 Look at the profile. What would occur at the outfall to make the water
level behave like this?
Conduit discharged to receiving water body at a depth below the water
surface (i.e. submerged outfall).
4 The pipe sizes increased downstream but there was less excess capacity in
CO-4 than any other. What could explain that?
In this case, CO-4 had the mildest slope.
5 If the rainfall increased over these events, which manhole would overflow
first? Why?
Most likely MH-4 because it is at the upstream end of the pipe with the
lowest slope. You would need to run the model to verify this because
system behavior is not always intuitive.
Module Overview
In this workshop, you will run SewerGEMS using the EPA SWMM (Storm Water
Management Model) explicit solver and analyze water quality impacts of a
chemical spill in the collection system.
This course material has been developed for the SewerGEMS V8i (SELECTseries 4)
platform, at a minimum the Version 08.11.04.54. Modelers currently using
versions prior to SewerGEMS V8i (SELECTseries 4), 08.11.04.54, are strongly
encouraged to consider upgrading today to start taking advantage of the latest
features and interoperability advantages of V8i.
Module Prerequisites
• Modeling Basics
• Gravity Collection Systems
• Using Pumps & Forcemains
• Extended Period Simulations
• Dynamic Flow Routing
• Catchment Hydrology
Module Objectives
After completing this module, you will be able to:
• Calculate a model using the SWMM explicit solver
• Perform a SWMM water quality analysis in the SewerGEMS interface
Getting Started
This section runs you through opening an existing file, computing it and taking a
quick review of the results of the system using color coding.
Note: All of the data has been entered in this model and it is ready to run.
2 Click the Compute button and review the results in the Calculation
Summary.
3 When you are done reviewing the results, close out of the summary
dialog.
You will notice that color coding of the conduits by Flow has already been
set up.
4 Click on the Animation Control button or select Analysis > Time Browser
and animate the drawing through time.
5 Watch the flow move through the system to the outfall node at the
bottom of the system.
SWMM Scenario
This section will guide you through using the SWMM Engine Type.
To let the program know that you would like to compute the model using the
SWMM engine, you will need to change the calculation options.
Note: You will notice a red check mark will appear next to the SWMM Run Scenario.
Note: Remember that SWMM uses an explicit solver while the default SewerGEMS
solver uses implicit methods.Also note that the SWMM output report is set up
to use imperial units not metric.
8 Close the SWMM Output Report.
9 Save your file.
Hint: Remember to use the Edit > Find Element tool to help you quickly locate the
element you are interested in.
3 Select O-4 in the drawing pane, right click and select Graph.
After you select Graph, the Graph Series Options dialog comes up and
defaults to the current scenario as well as Hydraulic Grade.
4 Check both scenarios to be viewed on the same graph, uncheck Hydraulic
Grade, and check Flow (Total Out).
6 To view the numerical results, select the Data tab and scroll through the
results.
Note: Note that the SWMM solver showed a different startup but both gave similar
results.
Note: Change the units to L/s by right clicking the Flow column heading and selecting
Units and Formatting….
7 View the results for the other elements in the same way.
8 View the color coding animation with this solution.
9 Notice some odd color changes, but overall the patterns are the same.
10 Complete the first part of the Results Table.
11 Save your file.
6 Set up two points corresponding to Time 0 and 24 hours and let the
Concentration be 1000 mg/L for both.
Note: The spill occurred between 4 hrs and 4.2 hrs at a rate of 0.28 L/s.
5 Enter the table data to describe the spill.
0 0
3.99 0
4.00 0.28
4.20 0.28
4.21 0
24 0
6 View the graph of the inflow to ensure that it looks like the slug load here:
7 Close the graph and click OK to close the Inflow (Wet) Collection dialog.
Now you need to indicate which pollutograph the run should use.
8 In the manhole Properties manager for B2-242, click the ellipsis button
next to Pollutograph Collection.
9 In the Pollutograph Collection dialog, click the New button.
10 Use the drop down under Pollutograph to select Chrome Spill.
11 Click OK.
2 From the SWMM Output Report, notice that 0.47 lbs of chromium entered
the system.
Note: Now we need to check how the chromium dispersed as it moved downstream
and became diluted by continuing with the rest of the steps in this exercise.
3 To fill in the Table 2 of the Results Tables at the end of this workshop and
to see the chromium calculations, click on the element you are interested
in.
4 In the Properties manager for that element, click on the ellipsis button in
the Pollutants Collection field.
5 Read off the time of arrival, time of peak, peak concentration and end
time of pollutant.
6 You can approximate the times from the graphs although you can also
view the exact numbers in the Data tab.
7 Complete Table 2 and answer all questions at the end of this workshop.
Results Tables
B2-242
B2-281
O-4
Hint: See exercise Computing and reviewing the Water Quality Run to fill in Table 2.
Workshop Review
Now that you have completed this workshop, let’s measure what you have
learned.
Questions
1 Did you get essentially the same results from the Implicit and Explicit
solvers? Why?
3 What could you do at the treatment plant if you received a call informing
you of this spill?
4 What if you had a sanitary loading at the manhole where you loaded the
spill?
Answers
1 Did you get essentially the same results from the Implicit and Explicit
solvers? Why?
Yes. Both solved the same St. Venant equations. They just used different
numerical methods.
3 What could you do at the treatment plant if you received a call informing
you of this spill?
Use the model to determine when it would hit and take a train off line to
protect it from the spill. If you have equalization, place this volume in the
equalization tank and isolate it.
4 What if you had a sanitary loading at the manhole where you loaded the
spill?
You would need to adjust the concentration to account for dilution with
the sanitary flow.
Module Overview
In this workshop you will be analyzing a combined sewer system with a diversion
chamber to assess overflows during storms. The network model and pipe
properties have already been entered. You must enter a description of the storm
event and catchment properties and evaluate the performance during wet
weather events.
This course material has been developed for the SewerGEMS V8i (SELECTseries 4)
platform, at a minimum the Version 08.11.04.54. Modelers currently using
versions prior to SewerGEMS V8i (SELECTseries 4), 08.11.04.54, are strongly
encouraged to consider upgrading today to start taking advantage of the latest
features and interoperability advantages of V8i.
Module Prerequisites
• Modeling Basics
• Gravity Collection Systems
• Using Pumps & Forcemains
• Extended Period Simulations
• Dynamic Flow Routing
• Catchment Hydrology
• Water Quality
Module Objectives
After completing this module, you will be able to:
• Model and compute dry and wet weather scenarios
• Set up diversions in a sewer network
• Analyze a combined sewer system
Getting Started
Exercise: Open and modify an existing model
1 Start SewerGEMS and open the existing SewerGEMS file
CSOAnalysisSI.stsw from C:\Bentley Workshop\SewerModelingSI\Starter.
Your file will look like the figure here.
Note: Note that the drawing is annotated with the pipe diameter and slope. Pipe
inverts and lengths have been assigned, as well as the physical properties for
each of the manholes.
You need to edit the outfall to the WWTP and the Overflow to represent a
free outfall boundary condition.
2 To do this for WWTP, simply double click on WWTP to open the Properties
manager.
All the other information for WWTP has been entered for you.
4 Change the Boundary Condition Type for Overflow to Free Outfall as well.
3 0.8
6 1.1
9 1.5
12 1.2
15 1.2
18 1.0
21 0.7
24 0.5
4 We do not want to work with loading in L/day so right click on the units for
Base Flow, select Units and Formatting and set Unit to L/s.
5 Click OK.
6 Select Hydraulic Pattern-1 from the dropdown menu for Pattern and
enter a Base Flow of 84.95 L/s.
CM-1 CM-2
SCS CN 60 50
Note: CM-2 is less densely developed so it has a lower SCS Curve Number.
Instructions for assigning the Outflow Element follow the table.
Hint: Most of the values from the table above can be entered directly into the
respective catchment Properties manager.
2 Double click on CM-1 to open its Properties manager.
3 To assign the outflow node, click in the cell next to Outflow Element, use
the drop-down menu and pick <Select…>.
4 Then click on the appropriate manhole node (MH-1) and a dashed line will
appear from the catchment label to the manhole.
5 Enter in the remaining data for CM-1 into the Properties manager.
6 Continue by entering in the data for CM-2 into its Properties manager.
7 Save your file.
We need to add a side weir at the upstream end (start end) of CO-6.
1 Double click on CO-6 to bring up the Properties manager.
2 Change the field Has Start Control Structure? to True.
This will add the field Start Control Structure to the Properties manager for
this conduit.
3 Click in the Start Control Structure field and select <Edit Control
Structure...>.
7 Close the dialog, and then close out of the Alternatives manager.
Note: Notice how the flow through CO-6 and CO-7 is zero. The weir directed all the
flow to the WWTP on a dry day as desired.
3 Close the Calculation Detailed Summary dialog and all other dialogs until
you are back in the drawing pane.
Note: Notice how the water level almost reached 94.79 m at the peak hour, which
would have resulted in an overflow.
Warning: If your HGL is jagged or is not smooth, you are seeing a small instability in the
dynamic engine. This sometimes occurs when conditions change rapidly or when
the slope is near critical. Shorten the Calculation Time Step or the Y Iteration
Tolerance in your Calculation Options and run the simulation again to remove the
instability.
4 Several profiles have already been created. View each of them and think
about what they are showing.
5 Fill out the first column of the results table at the end of this workshop.
1 Select Components > Storm Data to bring up the Storm Events manager.
2 Click on the New button and select Time-Depth.
3 Rename Time-Depth - 1 to Big Storm.
4 On the Storm Event Input tab, click the New button and select Add Return
Event from Dimensionless Curve.
This brings you to the Engineering Libraries.
5 Expand the Dimensionless Rainfall Curves and SCSTYPES.XML.
6 Highlight Type III (24 hour) and click the Select button.
8 Click OK.
Your dialog should look as follows:
9 Click Close.
3 Edit the properties of Stormy Day so that it uses the Base Active Topology
alternative.
9 From the Properties manager, choose Stormy Day alternative from the
pull down menu next to the Rainfall Runoff alternative.
2 Add a new set of calculation options by clicking the New button and
naming the new options Time Step 0.005.
3 Double click on Time Step 0.005 and in the Properties manager, change
the Calculation Time Step to 0.005 hours.
5 Click on the scenario Stormy Day, and in the Properties manager, set the
Calculation Options to the newly created option, Time Step 0.005.
Results Table
Workshop Review
Now that you have completed this workshop, let’s measure what you have
learned.
Questions
1 Why is the SCS method appropriate for determining runoff in combined
sewers but not sanitary sewers?
2 Why did we need to reduce time step size in stormy day run?
3 Was the ratio of peak dry weather flow to peak wet weather typical of
combined systems?
Answers
2 Why did we need to reduce time step size in stormy day run?
Starting and stopping of flow over weirs can lead to instability in numerical
solution. This instability can be overcome by using smaller time steps.
3 Was the ratio of peak dry weather flow to peak wet weather typical of
combined systems?
Yes, the flow was about 6 times larger which is not uncommon.