Professional Documents
Culture Documents
Pisos Postensados Casos
Pisos Postensados Casos
Pisos Postensados Casos
Slab on Grade
Subbase t2=150-225
Subgrade
Uneven Ground Causes Restraint
Restrained shrinkage causes multi directional
cracking of the floor, curling and rapid disintegration
of structural integrity
A unreinforced floor is really a number of
smaller floors joined together
= JOINTS
Sawed
Contraction Joints
Formed
Construction
Joints
What Has Changed in the last 30 Years ?
Fast Moving
Consumer
Goods
Bigger
Warehouses &
Higher Racking
Efficient
Distribution
Higher
Stacking
Faster
Forklifts
24 Hour
Operations
Lets get the
good stuff
out FAST
Impact Point
Joints Aggregat
open duee looses
to cont
Drying act
and slab fault s when joint opens
Shrinkage and Curling
Sawed Cont ract ion Joint Sect ion
A facility managers worst problem – FAILED JOINTS !!!!!
Industrial Concrete Floors
• Following are examples of jointed
floors that were easy to construct and
would
• NEVER BE A PROBLEM
Rocking Slabs
Curled Edges
Joints cut too late
Joints too far apart
Inadequate Sub - base
Overloading
Curling of Joints
Why we need to reduce Joints
Damaged Wheels = $$$$$$$$$
Load
Tippage
Forklift
Maintenance
Floor
Repairs
joints unfilled 6-12mm wide 54%
joints unfilled over 12mm wide 47%
cracks over 6mm wide 45%
joints where slabs rock 44%
joints repaired but failed 44%
joints where filler became brittle 42%
cracks with spalled edges 39%
joints filler too soft to support 34%
cracks with islands 32%
joints opening 2-5mm 28%
joints with one side higher 27%
surface worn away 23%
joints with a metal screed key 16%
Results from the survey of over 200 USA Distribution facilities
• wheel replacement
• operator fatigue and moral
• increased housekeeping
• load tipping and breakage
• reduced building value
OUR INDUSTRY MISSION
No
Joints No
Curling
CAT 2
Floor
Tolerances
No
Cracking Wire
Guidance
OUR INDUSTRY MISSION
No Joints
No Curling
Francois Le Roux
Nyeleti Consulting
What are Post-Tensioned industrial slabs?
• Slabs on ground reinforced with Post-Tensioned
tendons consisting of steel cables
• Eliminate JOINTS
– PT Compression force counter shrinkage forces that
cause cracking
– Eliminate need for joints
– Extensive joint-free areas ~ 2500 sq.m
– Savings on joint cost, repair costs & downtime for
facility
Advantages of post tensioning
• Increased robustness
– If cracked by overload, crack held closed by
permanent compression force in slab
– Rapid deterioration & breakup avoided
– Ongoing repairs minimised
Typical applications
• Distribution Centres
& Warehouses
Typical applications
• Refrigerated stores
Typical applications
• Container-handling facilities
Typical applications
• Raft Slabs
Materials
High Tensile Strand
• 15.7 or 12.9mm dia, 7 wire cable
• Modulus c. 195 kN/mm²
• Approx 3 tonne coils
Duct (Void Former)
• Galvanised metal
• 70 or 90mm wide x 20mm high.
• 3 Strand also available
• Joints Tape Sealed
ANCHORAGES
Grout Tube
Anchor Block
Ducting
Anchor Casting
Corrosion-protective Grout
LIVE END
(For Stressing/Tensioning)
ANCHORAGES
Corrosion-protective Grout
Grout Tube
Ducting
Steel Strand
(Cable)
Bulbed Strand
Ends
DEAD END
Protruding cables cast into concrete to anchor cables
at the one end to allow tensioning at the other
Analysis and Design
Analysis stage
Key to success
is attention to detail
Installation stage
• Key items
– Subgrade preparation is key i.e.
Compaction & levels
– Isolate Columns etc
– 100% sand/poly cover
– Dowel sleeving
Installation stage
External Slabs
Prior to pour
Concrete Placement
• Key items :
– Proper planning
– Correct equipment
– Adequate Manpower
Post-Concreting
• Key items :
– Early formwork stripping for stressing vital
– Unlock blocking and joint systems
– Initial stress to control initial shrinkage cracking -
9Mpa concrete strength required
– Final stress - 25Mpa concrete strength required
Stressing
• Hydraulic Pump and Stressing jack
to tension strands/cables
• Certificate of Calibration essential for
each Jack & Gauge
Grouting
Post-Grouting
Post-concreting stage
• Clients requirements
Rehabilitated facility floor
Full production during
rehabilitation
CAT 2 regularity suitable for VNA
Phased construction
Lower life cycle cost
BACKGROUND
• Analysis Approach
Load transfer testing
Floor visual survey
BACKGROUND
• Visual survey
High percentage floor
defects
Shattered slabs, cracking,
joint failure etc.
• Poor surface regularity
BACKGROUND
Long Section of Row K-J
0.060
0.050
Vertical floor level (m)
0.040
80mm level difference
0.030
0.020
-0.020
-0.030
-0.040
Distance (m)
BACKGROUND
Transverse regularity of aisle BB
0.008
0.006
Height in m from datum
0.004
0.002
0.000
0.000 0.500 1.000 1.500 2.000 2.500
-0.002
-0.004
-0.006
-0.008
-0.010
Meters from datum line
Joint 1 Between J1 and J2 Max limit
Min Limit Joint 2 Joint 4
Betwee J4 and J5 J5
OPTIONS OFFERED
Conventional Rehabilitation
Bonded post tension slab (150mm
thick) on slip membrane
Continuously reinforced slab (175mm
thick) on slip membrane
200mm SFRC on slip membrane
Other Problems
1. Building constraints
a. Saw tooth roof with 4.5m height
beams at low end
b. Cable trays at 4.5m height
c. CANNOT OPEN A BOOM PUMP
d. Columns at 10m grid
(MOVEMENT RESTRICTIONS)
e. 4 Phases with 8 weeks wait
period between pours
WHY PT
Eliminating
all control
joints
Jointless
Max floor
150mm thick
pour up to
5000m2
No transverse Eliminate
joints slab curl
WAREHOUSE LAYOUT
Warehouse layout
4446m²
2556m²
POST TENSIONING LAYOUT
POST TENSIONING LAYOUT
1. Edge reinforcement
POST TENSIONING LAYOUT
POST TENSIONING LAYOUT
1.Movement joints
a.Movement was estimated as
0.5mm / m to free edge.
b.Main movement joint
estimated as 18mm
c.Measured on site as 12mm
to date (after 60days)
Tensioning direction
Tensioning direction
Construction sequence
1. Installation of
a. Polyterm Sub base
b. Formwork and slip sheets
c. PT system
d. Concrete and finishing
CONSTRUCTION SEQUENCE
4. Post Tensioning
CONSTRUCTION SEQUENCE
Post tensioning
Initial tensioning at 9MPa
Final at 25MPa
CONSTRUCTION SEQUENCE
Finish product.
End