CDLD Policy Implementation Procedures (Revised Edition)
CDLD Policy Implementation Procedures (Revised Edition)
CDLD Policy Implementation Procedures (Revised Edition)
CDLD POLICY
Implementation
Procedures
NOTIFICATION/LGE&RDD/CDLD Unit/2019
DATED 24 October, 2019
Authored by:
Syed Ishfaq Ur Rehman (Senior Policy Advisor, Khyber Pakhtunkhwa CDLD Programme)
Tariq bin Farooq (Senior CDLD Institutionalization Specialist, Khyber Pakhtunkhwa CDLD Programme)
Muhammad Irshad (Senior Devolved Planning Process Specialist, Khyber Pakhtunkhwa CDLD Programme)
Reviewed by:
Nadeem Bashir (Team Leader, Khyber Pakhtunkhwa CDLD Programme)
Said Rehman (Programme Coordinator, CDLD Policy Implementation Unit, LGE&RDD, Government of Khyber Pakhtunkhwa)
Muhammad Farooq Khan (Key Expert, Khyber Pakhtunkhwa CDLD Programme)
Approved by:
Secretary (Local Government, Elections and Rural Development Department, Government of Khyber Pakhtunkhwa)
Visualised by:
Asghar Ali Khan (Senior Communication Specialist, Khyber Pakhtunkhwa CDLD Programme)
Designed by:
Wasim Abbas (Ad.Sense Printing & Advertising, Peshawar)
The European Union supports the Government of Khyber Pakhtunkhwa to implement the Provincial Policy “Community Driven Local Development (CDLD)” through
financial resources, and technical assistance provided by Hulla & CO Human Dynamics GmbH & Co KG. The overall objective is to build responsiveness and
effectiveness of the State to restore citizen trust, stimulate employment and livelihood opportunities, and ensure the delivery of basic services.
This document has been produced with the financial assistance of the European Union. The contents of this document are the sole responsibility of the CDLD
Programme and can under no circumstances be regarded as reflecting the position of the European Union.
Revised
CDLD POLICY
Implementation
Procedures
NOTIFICATION/LGE&RDD/CDLD Unit/2019
DATED 24 October, 2019
C O NTENTS
Acronyms 3
A n n e x u r e s
Annexure 1. VILLAGE COUNCIL DEVELOPMENT PLAN (VCDP) FORMAT 46
Annexure 2. MIS BASED PROJECT EVALUATION AND RANKING CRITERIA 49
Annexure 3. CBO PROJECT SOCIO-ECONOMIC AND TECHNICAL FEASIBILITY FORMAT 54
Annexure 4. TERMS OF REFERENCE OF CBO SUB-COMMITTEES 58
Annexure 5. LETTER OF CBO REGISTERATION FROM P&D DEPARTMENT 60
Annexure 6. DETAILED PROJECT PROPOSAL (DPP) FORMAT 61
Annexure 7. CHECKLIST OF CBO PROJECT FILE 65
Annexure 8. RECOMMENDATION BY CONCERNED LINE DEPARTMENT 67
Annexure 9. PLANNING AND DESIGNING (DPP) REVIEW FORMAT 68
Annexure 10. FORMAT FOR SCREENING AND EVALUATION OF DPP BY TEC 72
Annexure 11. CBO GRANT AGREEMENT 75
Annexure 12. WORK ORDER TEMPLATE 87
Annexure 13. HANDING / TAKING OVER OF PHYSICAL INFRASTRUCTURE PROJECTS 89
Put in place fiscal and regulatory framework for CDLD where local communities are
in charge of executing local development/service delivery initiatives;
Build the capacity of relevant public sector entities and functionaries at the district
level to operationalize CDLD; and
Provide an enabling environment for CBO to access public funds earmarked for
CDLD initiatives.
1.2. Rationale
The Khyber Pakhtunkhwa Community Driven Local Development Policy (CDLD Policy)
document provides an overall framework for any community driven development in
Khyber Pakhtunkhwa. In compliance with the CDLD Policy, Finance Department issued
instructions in the shape of notification No. FD/EU/CDLD/1-1/2013 dated 15 August
2014, which explains the detailed implementation procedures for any intervention under
the Policy. The CDLD Policy implementation procedures are reviewed on annual basis
for continuous improvement in the quality for CDLD Programme. This is also reflected
in the performance matrix agreed with the European Union. Based on the learnings
of implementation stakeholders, the CDLD Policy implementation procedures were
revised in 2017 and issued by Local Government Election and Rural Development
Department (LGE&RDD) on 23 June 2017 vide NOTIFICATION/LGE&RDD/CDLD
Unit/2017. Likewise, for second review, EU mission’s recommendations, Third Party
Verification (TPV) firm findings, and submission of the annual review workshop held in
June 2019 were presented to PCRC in its 17th meeting which were approved. Based on
the approval, the CDLD policy implementation procedures were revised. Subsequently,
Budget Support
Divisional Commissioner
Deputy Commissioner
District Development Committee (DDC)
As part of the institutional mechanism, various committees are constituted both at the
provincial and district level to operationalize and implement the CDLD Policy and Programme
according to the notified procedures. This chapter explains the composition and functions
of these committees.
Designation Position
Secretary LGE&RD Department, Govt. of Khyber Pakhtunkhwa Chairman
Secretary Finance Department, Govt. of Khyber Pakhtunkhwa Member
Secretary Planning & Development Department, Govt. of Khyber Pakhtunkhwa Member
Secretary Social Welfare and Women Development Department,
Member
Govt. of Khyber Pakhtunkhwa
Secretary Elementary & Secondary Education Department,
Member
Govt. of Khyber Pakhtunkhwa
Secretary Health Department, Govt. of Khyber Pakhtunkhwa Member
Secretary Public Health Engineering Department, Govt. of Khyber Pakhtunkhwa Member
Secretary Agriculture Department, Govt. of Khyber Pakhtunkhwa Member
Secretary Environment Department, Govt. of Khyber Pakhtunkhwa Member
Director-General LGE&RD Department, Govt. of Khyber Pakhtunkhwa Member
Commissioner of respective Divisions Member
A representative of the European Union Delegation, Islamabad Member
One representative from the Civil Society Organization nominated by the Chair Member
Coordinator, CDLD LGE&RD Department, Govt. of Khyber Pakhtunkhwa Secretary
Designation Position
Director-General LGE&RD Department, Govt. of Khyber Pakhtunkhwa Chairman
Additional Secretary (Dev) Finance Department, Govt. of Khyber Pakhtunkhwa Member
Chief Rural Development, P&D Department, Govt. of Khyber Pakhtunkhwa Member
Director Admin / HR, Directorate General of LGE&RD Department,
Member
Govt. of Khyber Pakhtunkhwa
Team Leader, CDLD Technical Assistance Team Member
Coordinator PIU-CDLD, LGE&RD Department, Govt. of Khyber Pakhtunkhwa Secretary
The PIU (previously called CDLD Coordination Unit) is liable to monitor and
coordinate the CDLD policy implementation related matters in support of Sub-
committee and PCRC. Currently, this unit is working under the umbrella of
Directorate of LGE&RDD. The PIU is headed by Additional Secretary LGE&RDD
also called Programme Coordinator-CDLD. The functions of this unit are given
under section 2.1.2 of CDLD Policy document.
The DDC shall undertake the functions related to CDLD Programme at the
district level under the chairmanship of respective Deputy Commissioner. The
composition and functions of DDC are as under:
Designation Position
Deputy Commissioner (DC) Chairman
District Education Officer (male) Member
District Education Officer (female) Member
District Health Officer Member
District Planning Officer Member
District Director of Agriculture Member
District Director of Livestock and Dairy Development Member
District Officer Fisheries Member
Executive Engineer, Communication & Works Member
Executive Engineer, Public Health Engineering Member
Executive Engineer, Irrigation Member
Assistant Director, LGE&RD Department Member
District Officer, Social Welfare & Women Empowerment Member
District Officer, Water Management Member
Tehsil Municipal Officer, District Headquarter Member
Divisional Forest Officer Member
One woman representative nominated by DDC Member
Senior Programme Engineer Member
Programme Officer-Social Mobilization Member
One representative from the Civil Society nominated by DDC Member
Additional Deputy Commissioner Finance & Planning Secretary
DDC may co-opt any other officer in the district as a member to provide technical
or specialized input. The DDC is empowered to designate, the member from civil
society organization, or any other district officer to provide technical backstopping
specifically for specialized and livelihood projects. A minimum of ten members
i. Approve annual work plan at the beginning of each fiscal year as per section
4.1.
ii. Accord technical and administrative approval to the eligible projects submitted
by CBOs.
iv. Ensure fund equity to benefit the neediest communities and village or
neighborhood council (VC/NC) in the district.
viii. Hold at least quarterly progress review meetings to monitor physical and
financial progress including Village Council Development Plan (VCDP)
related activities, status of accomplishment of annual targets of Programme
related activities, disbursement to CBOs, compliance of TPV, EU mission
and technical assistance (TA) team recommendations, status of internal
monitoring visits as mentioned in section 5.1, and implementation issues
related to CDLD Programme etc. The decision of such a meeting must be
communicated to all stakeholders both at district, divisional and provincial
level.
ix. Resolve issues and bottlenecks in the implementation of the approved CBO’s
projects as per instructions given in section 6.3.
xi. Ensure compliance with policy directions and implement any other business
logic related to CDLD Programme assigned by PCRC.
Designation Position
Additional Deputy Commissioner - Finance and Planning (ADC-F&P) Chairman
Member/
District Planning Officer, District Government
Secretary
One Engineer from District Line Department Member
Assistant Director, LGE&RDD Member
Senior Programme Engineer Member
Programme Officer-Social Mobilization Member
A female nominee of the Social Welfare & Women Empowerment Department Member
Note: District in-charge of the relevant sector department shall attend as a member when
projects related to the sector are considered in the TEC.
ii. Evaluate and approve the itemized costs of the project as per Market Rates
Schedule (MRS).
iii. Assess and approve the quality of items given in the project design document.
iv. Grant technical sanction to new, revised and re-estimated DPP and
recommendation to DDC for approval.
vi. Act as Price Evaluation Committee; evaluate and approve the cost of non-
scheduled items and provide guidance in special cases where the rate of any
item is found missing in MRS.
vii. Any other assignment advised by the DDC and Deputy Commissioner
The SMT shall consist of Programme Officer Social Mobilization (PO SM)
and Social Mobilizers (both male and female). The SMT shall work under
the direct supervision of PO-SM and shall report to ADC (F&P). This team
shall be responsible to implement the entire functions of social mobilization
i.e. VC/NC wise planning of activities, allocation of VC/NCs to each of tehsil
based CDLD staff member, preparation of VCDPs in coordination with
Secretary VC/NCs, preparation of socio-economic feasibility of VC/NC
wise projects, formation/reactivation of CBOs (men/women), preparation
of social part of DPP, CBO record keeping, capacity building of CBO’s
representatives, facilitation to CBOs during registration, bank account
opening, signing of grant agreement with district administration, on job
support to CBO’s sub-committee members during project implementation,
reporting, development of case studies, preparation of success stories,
CBO level conflict management, facilitation to internal and external
monitoring teams etc. as per approved terms of references (TOR). Both
the social mobilization and engineering teams shall work in synchronized
manner which shall be ensured through joint work and field planning. At
the district level, the team shall work in close coordination with district
administration and concerned line departments. At tehsil level, the team
shall undertake its functions under the supervision of respective Assistant
Commissioner whereas regular reporting line will remain the same.
This chapter explains the fund flow mechanism/grant management processes under CDLD
programme. Details of the fund flow mechanisms established both at the provincial and
district level are as under;
Variable Factors
As contemplated by the Khyber Pakhtunkhwa Local Government Act (LGA) 2013, for
working out the shares of the individual VC/NC in the target districts, population shall be
the sole criterion as calculated on the basis of last preceding census officially published.
Population of VC/NC
_______________________
Funds of VC/NC = Total district funds in particular year x
Total population of the district
A maximum of 10.35 percent of the total CDLD allocated budget during a year
shall be earmarked to meet management and social mobilization support costs
of the Programme unless changed by PCRC including operational cost related
to hiring of human resources for CDLD projects, CDLD related costs of districts
administration, office of the respective Commissioners, CDLD PIU, social
mobilization activities implementation cost and the LGE&RDD.
The funds utilized will be reported on a monthly basis to PIU by using the following
template:
Expenditure
Object Object Amount Expenditure till Cumulative
till the Current
Code Description Released Last Month Expenditure
Month
Developmental
Funds
Operational
Funds
Total
i. After signing a grant agreement with district administration, the CBO shall
then submit a fund requisition form along with a resolution for the release
of first and subsequent installments as per the annexures 11.2, 11.3, 11.4
attached with CBO grant agreement.
ii. SPE and PO SM shall review/validate the request and submit to ADC (F&P)
on note sheet for preparation of simple receipt, sanction, which will be
submitted to DC along with project files for approval.
iii. After approval and signature, the Finance & Planning Office shall submit
the signed simple receipt and sanction to DAO for preparation of cheques.
iv. The DAO will prepare cheque and send it back to Finance and Planning
Office within one week. or the DAO prepare cheque on the title of CBO.
v. The Finance & Planning Office write a letter to managers of the respective
banks, subjected “transfer of amount to CBO account” along with CBO
bank account detail and cheque issued by DAO. In the latter case, the
cheque will be delivered to the CBO in the presence of two witnesses from
the same CBO and its receipt will be acknowledged in writing
Release of 2nd and 3rd installments shall be contingent upon the following
conditions which need to be fulfilled:
i. Upon submission of fund requisition along with a resolution for the release
of 2nd / 3rd instalment, the SPE/PO SM shall review/validate it and forward
it to RISE through RIE for preparation of MB and narrative and financial
reports on the prescribed formats.
ii. The RISE will visit the site and prepare MB on government-approved
prescribed format to be subsequently verified by RIE and endorsed by the
SPE. The Social Mobilizer will support CBO in the preparation of narrative
and financial report.
iii. The SPE will review and endorse MB and PO-SM will review and endorse
narrative and financial report along with other reports and submit to ADC
F&P for the preparation of simple receipt and sanctions through Account
Assistant.
iv. The ADC F&P will submit a simple receipt, sanctions, validated MB,
endorsed narrative and financial reports, along with project files to DC for
approval and signature.The Finance & Planning Office shall submit the
signed simple receipt and sanction to DAO for preparation of cheque.
v. The DAO prepares cheque and send back to Finance and Planning office.
vi. The Finance & Planning Office write a letter to the Managers of respective
banks, subjected “transfer of amount to CBO account” along with CBO
bank account detail and cheque issued by DAO.
viii. After approval of 2nd / 3rd installment, Finance Department shall submit
the original copy of sanction and simple receipt to District Account Office
for the issuance of a cheque which is to be credited to CBO bank account.
However, prior to the release of the third instalment, the physical work
should be verified by the PoE and is found completed with quality and
No No
ii. If an amount has been released to CBO and CBO is not willing to complete the
agreed milestones the case shall be forwarded to the tehsil conflict management
committee for review and decision. Before this step, the social and technical
teams will try their level best to make the CBO functional. If CBO is not willing,
then Chairman committee will take administrative action against the CBO’s
office bearers for the recovery of government fund in accordance with existing
government rules and regulations.
i. The CDLD district team as mentioned in section 2.2.3 shall be contracted from
the open market by the district administration under specific terms of reference
and fixed remuneration as individual consultants in light of section 28 of Khyber
Pakhtunkhwa Public Procurement Regularity Authority (KPPRA) Rules, 2014. In
subsection 4 of section 28, it is mentioned that “for key assignments, interviews
may be set up and capability of the candidate should be evaluated”. For increased
transparency, accountability and to check the capability of candidates, the district
administration may follow section 3 and section 8 of the “Khyber Pakhtunkhwa
policy regulating appointment to posts in development project” amendment
notification No.SO(Policy)/E&AD/1-25/2017 issued on 6/12/2017. This may only
be utilized as a tool for shortlisting and preparation of final merit lists. However, the
agreement will be signed by the candidate with the respective DC as an individual
consultant in light of section 28 of KPPRA rule 2014.
ii. All the items related to the office establishment/operations of CDLD district team
shall be procured in accordance with the KPPRA Rules, 2014.
This chapter explains the mechanism for implementation of the entire CDLD project cycle
management and also provides an in-depth understanding of various processes to be
undertaken in compliance with CDLD Policy. The following steps constitute a complete
CDLD project cycle which shall be followed for implementation of CDLD schemes.
Planning
(Annual work planning)
Closure Identification
(Handing over, O&M) (VCDP preparation, VC / NC
wise merit list)
Implementation Formulation
(Agreement, releases, work (CBO formation, DPP
order, supervision) preparation)
4.1. Planning
At the start of each fiscal year, DC will call a meeting of all DDC members including
respective Assistant Commissioners and CDLD district team to undertake annual work
planning in the following manner:
During the annual work planning, the following factors shall be considered for
targeting a geographic area for the implementation of CDLD project cycle;
i. At the beginning of each fiscal year, a detailed and robust work plan shall be
developed jointly by the district administration, the CDLD district team and
other relevant stakeholders headed by DC. The work plan shall consider
100% coverage of VC/NCs in each district during a fiscal year.
ii. Allocation of 20% of the annual budget for women-specific projects and 5% for
livelihood related infrastructure shall be considered.
iii. The VC/NCs will be selected for the implementation of the entire CDLD
project cycle on the basis of seasonality, vulnerability, geography, and other
local factors.
vi. Data entry of revised VCDP priority needs shall be planned before the end of
each fiscal year.
vii. A clear timeline shall be mentioned for all the activities related to project cycle
management and DDC is authorized to implement the plan in accordance with
the approved milestones and timelines.
viii. Approval of DPPs shall be planned before 30th April so that grant agreement
could be signed with the CBOs and physical work could be initiated in the
fiscal year.
ix. Review of annual work plan shall be carried out by district administration in
collaboration with the relevant stakeholders at least on a quarterly basis.
4.2. Identification
The Khyber Pukhtunkhwa Local Government Act (Amendment), 2019 stipulates
decentralized development planning. In compliance with LGA (Amendment), 2019
section 15 (substitute of section 29 of LGA 2013) subsection iii “identify development
needs of the area for use by Tehsil Local Government in prioritizing development plans
for the tehsil”, Village Council Development Plans (VCDPs) shall be developed under
CDLD in the respective VC/NCs identifying and prioritizing development needs of the
area. The preparation and annual review of VCDP shall be supervised and randomly
monitored by the ADC (F&P) and AD-LG to ensure that the process is completed
in compliance with the VCDP preparation guidelines. It shall be mandatory for all
development stakeholders including elected representatives, line departments, and
NGOs to consult the respective VCDP while initiating any developmental activity at VC/
NC level. In each district, the AD-LG office shall be responsible for the implementation of
VCDP related activities. However, the district administration or LGE&RDD may assign
the task to CDLD district team or any other entity to support the preparation and annual
review of VCDP. In this regard, the following steps shall be followed in compliance with
the detailed guidelines issued by the Director-General Local Government (DGLG)/PIU.
a. In each district, based on the VCDP list of priorities, CDLD-MIS shall generate
a merit list of priority needs for each VC/NC, under the screening and project
selection criteria given in section 4.2.4 for for funding under CDLD.
b. Projects that fall within the range of 0.3 to 3.5 million PKR shall be considered
under CDLD.
e. The operation and maintenance (O&M) of the project shall primarily be the
responsibility of CBO.
The elected and appointed representative in each VC/NC with the support of SMT
shall hold inclusive broad-based community consultative planning meetings with
all relevant stakeholders in coordination with the Secretary VC/NC, to identify and
prioritize the overall needs. Schemes under the following sectors are eligible for
funding under CDLD Policy:
i. The consultative planning process shall give due attention to the needs of
women and girls, marginalised groups like minorities, handicapped, elderly,
homeless persons, transgender and victims of disaster (if any).
ii. During the consultative planning process, a list of prioritized needs shall
be prepared which shall be revised on an annual basis with the active
involvement of all stakeholders of VC/NC. The VCDP preparation/revision
format is attached as Annexure-1.
iv. After the preparation of VCDP, the elected council of VC/NC shall approve
the VCDP document and shall refer to AD-LG for quality review and further
dissemination to all stakeholders for the integration of prioritized needs in
Annual Development Programmes (ADPs).
v. The quality review of approved VCDP shall be completed by ADLG office with
the technical assistance of SMT or any other technical support available.
vii. The quality review of VCDP data in CDLD-MIS shall be completed by DEO
with the facilitation of SMT.
viii. This process of VCDP preparation/revision shall take place from March to
May for the next fiscal year not later than the finalisation of Tehsil and VC/NC
ADPs.
Only those prioritized needs of VC/NCs shall be eligible for consideration under
CDLD which qualify the below-mentioned screening criteria:
Under the above screening criteria, any given indicator inked as “Yes”, will result
in outright rejection of the prioritized project.
Projects which qualify the above screening criteria shall then be evaluated against
the evaluation criteria given below. Any project that secure maximum score will
be shortlisted for funding under CDLD in that particular VC/NC. This two-stage
screening and scoring is entirely automated and shall be executed through CDLD-
MIS.
Based on project eligibility criteria, a VC/NC wise merit list of prioritized projects
shall be generated. The ADC (F&P) shall refer the CDLD-MIS based automated
VC/NC wise merit list of prioritized projects to the concerned line departments
to check possible duplication of funding from other sources. In response, the
concerned line department shall issue a non-duplication certificate to those
projects which are not funded by any other source.
c. During the validation of such projects, SMT and concerned line agency shall
ensure that the sustainability plan provided by CBO is viable.
d. Prior to the preparation of DPP, the SMT shall also ensure that the CBO has
the capacity to run the vocational centre and the CBO possesses appropriate
human and physical resources and the department is willing to own the
vocational centre.
e. No O&M and recurring cost shall be budgeted for such projects in the DPPs
Upon receipt of VC/NC wise merit list of prioritized projects from the respective line
departments, the SMT shall contact the concerned community through Secretary
VC/NC to undertake social and financial feasibility. The SMT shall:
i. Validate the information mentioned in the VC/NC wise merit list of proposed
projects.
ii. Ensure that the project is socially desirable, economically viable, financially
feasible, and the community is willing to implement the proposed scheme in
compliance with the CDLD modality.
iii. Ensure that the community is willing to contribute a 10% share in cash or kind.
iv. Ensure that the CBO members are willing to contribute preferably PKR.100
(user charges) per beneficiary household per month in CBO saving account
during the implementation till completion of the project for O&M of the project
During the visit, if the proposed scheme is found socially desirable then PoEs
shall conduct a survey of the site for technical and environmental feasibility.
After conducting social feasibility, the concerned community along with PoE will
undertake technical and environmental feasibility of the scheme. During technical
feasibility and detailed survey, the projects such as gravity flow schemes,
culverts, bridges, buildings, hand pumps, tube wells, dug wells, etc. are required
to be carefully assessed. For certain projects, specific tests are required. These
include water quality tests for Drinking Water Supply Scheme (DWSS), Electrical
Resistivity Test (ERT) for sub-surface water schemes, and soil bearing capacity
tests before the preparation of DPP. Prior to the initiation of such projects the
following steps shall be undertaken;
iii. Upon receipt of successful test results, the beneficiary community/ CBO
will provide a copy of the test results along with invoice/bill to the PoE and
subsequently, the cost shall be added in DPP with the project cost and paid
to the community.
iv. Prior to payment of the amount mentioned in the invoice, the PoE may verify
the test results.
v. In case of failure of test results, further work shall be abandoned and only
cost of the test shall be paid to the respective community or CBO as per the
invoice/bill; and no extra payments shall be made to the claimant. In such
cases, beneficiary community or CBO shall provide a copy of the test results
with the original invoice to PoE for onward submission to SPE. The CDLD
SPE will submit the case to ADC (F&P) for onward approval from respective
Deputy Commissioner (DC).
vii. In case of considering sub-surface water, at least one resistivity test shall be
required.
If the project is found feasible in all aspects then SMT will initiate the process
of social mobilization with providing support in the preparation of DPPs. Social,
technical, environmental and financial feasibility shall be conducted on the
prescribed format attached as Annexure-3.
iii. The capability of CBO to resolve any dispute that may arise during the
whole course of social mobilization and project implementation is vital.
Under CDLD, DCs in the respective districts are authorized to register the
CBOs formed/revitalized by the SMT for the purpose of CDLD Programme
as per the advisory from P&DD attached as Annexure-5. For this purpose,
CBO will pass a resolution for registration to be registered with the
concerned DC. The DC may authorize any District Officer to register the
CBO on his behalf.
The SMT will support the CBOs in the opening of bank account which
is mandatory for accessing CDLD funds. Following are pre-requisite for
opening CBO bank account:
vii. Attested copies of CNICs of all members of the general body and
executive body.
After approval from DDC, the SMT along with PoEs shall arrange the
following formal and informal capacity building events for the CBO office
bearers, CBO sub-committee members and VC/NC Secretaries:
ii. The SMT shall conduct periodic CBOs Managers Conferences at tehsil
or district level to share the implementation results of CDLD modality,
progress, implementation issues and way forward.
In addition, the SMT and PoEs shall provide on-job support to CBOs during
project implementation. Social Mobilizer and concerned Engineer shall
plan a joint visit to CBOs for providing on-job support in the implementation
of the CDLD project. Prior to the visit, the CBO shall be informed to ensure
the availability of general body members, subcommittee members, and
office bearers as required. In addition, during the visit, both shall support
and provide on-job training to CBO maintaining CBO proceeding register,
saving or O&M fund records, project-related stock register, mastroll, cash
book, receipts, etc. for internal record.
ii. Cost estimates shall be based on latest approved Market Rate Schedule
(MRS), with fixed 10% community contribution (in cash/kind), and less 17%
iii. Material mentioned in the DPP is locally available and the CBO has the
capacity to implement and sustain the project.
Moreover, separate files for each DPP will be prepared for approval by the
respective DC. In addition, the SPE shall validate (countersign) each page of all
the DPPs. The checklist of CBO project file is attached as Annexure-7.
Once the process of preparation of DPP is completed, the SMT and PoEs
shall facilitate the CBO to submit DPP in the office of ADC (F&P). Prior to
submission of DPPs, PoEs shall ensure that the pre-feasibility tests are
conducted from government-approved/recommended institutes/vendors
and the test results are part of DPPs.
4.4. Approval
Before the project is approved by the DDC, the following tasks will be performed:
ADC (F&P) shall, within three working days, send the DPP to the focal person
notified by the concerned line department through SPE and PO-SM to, check the
duplication of funding from any other source, validate data provided in the DPP,
check feasibility and cost estimates, and O&M arrangements of the scheme. The
concerned line department shall respond on the prescribed format attached as
Annexure-8 within three days.
Upon recommendations of the line department, the SPE and PO-SM will ensure
the planning and design review of DPPs in the prescribed format attached as
Annexure-9. After planning and design review, the DPPs shall be submitted to
ADC (F&P) for onward submission to TEC.
i. After the validation of DPPs by the line department, SPE and PO-SM at
first place and/or after rectification of errors, the ADC (F&P) shall convene
a meeting of the TEC within one week, by circulating a working paper. SPE
and PO-SM shall present the DPPs in the TEC meeting. After evaluation of
ii. The rectified DPPs shall be presented to TEC and after granting technical
sanction, DPP shall be forwarded to DDC for approval.
i. DDC meeting shall be convened within ten days after the TEC meeting. ADC
(F&P) shall circulate agenda and working paper to all DDC members.
ii. All technically sanctioned DPPs shall be submitted to the DDC for review.
iii. SPE and PO-SM shall present the DPPs to the DDC.
iv. DDC shall grant approval of those projects which are completed from all
aspects.
v. Minutes of the DDC meeting shall be issued and circulated to all concerned.
vi. Based on the approval of DDC, DC will accord the administrative approval.
After the administrative approval, the ADC (F&P) will submit a request to DGLG/
PIU LGE&RDD for the release of funds equivalent to the cost of projects approved
the DDC. DGLG/PIU LGE&RDD shall review and forward the funds request to
Finance Department for release of funds.
4.5. Implementation
Once the scheme is approved, the following steps are to be taken for implementation
of the scheme:
After the administrative approval, the CBOs shall be called for the signing of the
agreement by district administration through SMT. The grant agreement between
the Deputy Commissioner and CBOs is attached as Annexure-11. The subject of
such negotiations shall be agreed to the achievement of various project milestones
and other performance targets, their delivery schedule, reporting requirements
and their frequency, and the terms and conditions of releases of first, second and
third installments. After mutual agreement, the contract shall be signed between
The original copy of approved DPP shall be retained in the office of ADC (F&P)
with an original copy of the signed agreement and other related documents for
office record and ready reference. At the time of agreement signing, CBO shall
ensure to submit two copies of approved DPP to the office of ADC (F&P) in which,
one copy of DPP shall be handed over to PoEs. Whereas, CBO shall hold the
same copy of DPP and agreement for its record and onward utilization during the
implementation of the project.
Community schemes under CDLD Programme are smaller in size and are
expected to be completed within the stipulated time. In rare cases, if a CBO
contract agreement is expired, the following steps shall be considered:
ii. Contracts which are expired prior to the completion of projects, due to
deficiencies found on part of CBO, the CBO shall provide justification
for the delay of a project in form of resolution to TEC with ratification
from the Secretary of the respective VC/NC.
iii. In response, the TEC shall forward its recommendations to DCC for
the approval of an extension of the CBO project contract agreement.
In case, if the CBO fails to provide justification with mentioning valid
reasons regarding extension of contract agreement then TEC is
authorized to close the project based on work done.
Prior to the issuance of work order, 1st installment is released to the CBO as
mentioned in section 3.4.1. After the release of 1st installment, the ADC (F&P)
shall issue the work order attached as Annexure-12 to CBO within 10 days
(for all pending agreements signed with CBOs) for commencement of work at
the project site. Moreover, in order to ensure transparency, accountability, and
ownership, first installment cheque along with the work order shall be handed
over to office bearers (President and Secretary) of concerned CBO by the SMT
ii. The CBO shall prepare both social and technical records duly verified
by SMT and PoE.
iv. The CBO shall retain copy of the approved DPP, grant agreement, MBs
and progress reports for presentation to the external monitors/auditors.
vi. The ADC (F&P) office shall maintain the bank book and other records
related to the releases as mentioned in chapter 3.
The SMT shall also be responsible to provide the required social mobilization
and capacity building support to CBOs throughout the project implementation till
project completion as mentioned under section 4.3.3.
Once a CDLD scheme is completed, PoEs with the support of SMT shall install
project information board as per the following details:
i. The standard specimen is followed during the design of the project information
board.
ii. Contents of the project information board are correct and insignia of the
government and donor are visible.
iii. At the project site, the project information board is installed at an appropriate
place.
iv. For information of the general public, a consolidated list of CDLD projects
shall be displayed on large size project information board in each tehsil, at the
tehsil entry point.
The O&M of CDLD projects which are to be handed over to line departments
shall be the sole responsibility of the concerned department whereas, O&M of the
projects which are handed over to the CBO shall be the sole responsibility of CBO.
During the implementation, SMT shall monitor the O&M plan in the respective VC/
NCs to ensure that the O&M plan is being implemented and the collection of O&M
fund is being deposited in the CBO bank account.
After the completion of CDLD project, DDC shall decide to formally handover
the community-owned projects i.e. DWSS, street pavements, hand pumps, and
drainage system etc. to the CBOs. Whereas the projects constructed within
the premises of the government-owned facility e.g. missing facilities within a
government school or basic health unit shall be handed over to the concerned
government line agency. Handing/taking over certificates for both scenarios are
attached as Annexure-13. In this regard district administration through AD-LG
shall ensure that Secretary VC/NC has recorded the data of completed CDLD
schemes in the inventory register of respective VC/NC.
Social Social
Orientation Pre-VCDP Economic Mobilization
of VC / NCs Annoucement and and Capacity
Formulation on VCDP Financial Building of
of District Feasibilities CBOs
Annual Work
Plan
Monitoring, Evaluation and Reporting
Installation
Technical Technical Signing Issuance of Handing
of Project
Review by Sanction by of CBO Work Order Over of
Information
CDLD Team TEC Agreement to CBO Project
Board
i. Any request for changes in the scope of the scheme shall be forwarded to
TEC in form of a resolution by the concerned CBO.
iii. Considering the remoteness and vulnerability of the area, TEC is competent
to re-appropriate the cost of transportation and other scheme related items
which are not specified in the MRS. However, the re-appropriations shall be
made within the project cost.
vii. While doing changes as explained above, SPE, TEC, and DDC shall ensure
that the revisions made are consistent with the public benefit.
ix. Any escalation in the project cost before the implementation would require
approval of DDC, after technical sanction from TEC provided that escalated
cost is less than PKR.3.5 million and available budget of the VC/NC. Prior to
technical sanction, TEC shall ensure that:
If escalation takes the cost of the project beyond PKR.3.5 million, such projects
shall be referred to PCRC through DDC for consideration.
x. Any change in the design of a project, prior to the submission of DPP to TEC,
shall be reviewed by a joint committee of SPE, concerned PoE and PO-SM
provided that the approved cost, sector, mohalla of the project is not changed.
xi. Work execution not complying with engineering standards may be forwarded
to DDC. The DDC is authorised to withdraw all or a certain amount of funds for
the rectification of sub-standard work or close the project based on work done.
The government shall put in place robust and elaborated monitoring and evaluation
arrangements, which shall be comprised of both internal and external monitoring of CDLD
project activities.
CBO monitoring and audit committee is mandated to monitor all the activities
during the implementation of the project, check records and conduct an internal
audit and present their report to CBO general body for rectification
The SMT & PoEs are expected to work very closely in the field. They shall be
responsible for the monitoring and supervision of the entire CDLD project cycle
embedded throughout all stages.
PoE/SMT shall
i. Ensure the compliance of monthly work plan duly approved by the SPE and
PO-SM.
ii. Draw the layouts physically on site of the project as per the approved design
and present all the sections of grant agreement in a CBO meeting, and ensure
iii. Monitor that the CBOs are utilizing the material as per the specification
mentioned in DPP.
iv. Monitor and supervise the quality of physical work as per the approved design
and within the approved budget.
v. Monitor the timelines for the accomplishment of each milestone given in work
plan, procurement plan and O&M plan in the approved DPP.
vi. Ensure proper reporting social, technical and financial aspects of projects
during the project implementation.
vii. Ensure proper monitoring visits in accordance with the guidelines, preparation
of financial and technical reports, preparation and verification of MBs.
ix. Support district administration and any other relevant stakeholder during a
visit to CBOs and project site.
xi. Monitor that CBO holds all relevant records which are to be presented to
external monitors, auditors i.e. copy of approved DPPs, copy of signed grant
agreement, copies of resolutions, fund requisitions, bank statement, copies
of MBs, copies of technical and financial reports, a record of O&M fund and
comments of visitors etc. In case of any missing record, ensure the availability
of records.
xiii. Ensure the preparation and submission of each visit report to SPE for
monitoring, supervision and audit purpose.
xv. Ensure to enter the progress of the projects into CDLD-MIS soon after the
field visit
The PoE visits shall be carried out in accordance with the plan to be
prepared for each project on case to case basis in order to ensure that all
projects in a district are visited by PoE. The SPE may randomly visit projects
before the release of the final installment. PoE’s technical supervision and
assistance shall be in accordance with the government system. Following
is an indicative visit plan to be followed broadly while preparing a project-
specific visit plan.
i. The first visit shall be made to the proposed site on the basis of
information provided in the DPP with respect to the ground situation.
They shall orient CBO on the work plan, procurement plan regarding
the implementation of the project, specification of design, drawing,
material, maintaining project register and drawing layout, etc.
ii. In the second visit, standards and quality of materials shall be procured
(or samples of the materials delivered at the site) for the project to
ensure the pre-execution quality control measures and technical inputs
shall be checked. In addition, appropriate technical guidance shall be
provided to the CBO regarding initiation of physical work.
iii. In the rest of the visits prior to the last visit PoE shall undertake
monitoring and supervision of the physical work to check and verify
both the quality and quantity at the project site and provide required
technical inputs for work ahead and also ensure monitoring and
measurement of the work progress as per agreed work schedule.
ii. DDC, in each district, shall conduct quarterly meetings to review the findings
and take appropriate actions accordingly.
iii. Monitoring reports on prescribed format shall be submitted to the ADC (F&P)
in the DC Office, who shall prepare a summary for review by the DC, and
in turn, shall prepare quarterly monitoring reports to be presented in the
quarterly divisional monitoring meetings chaired by the Commissioner of the
respective divisions. Copies of the monthly, quarterly, and annual monitoring
reports shall also be sent to DGLG in the LGE&RDD.
iv. Regular coordination meetings will be ensured at the district level by the DC
through ADC (F&P) to review progress and shall ensure that the targets are
achieved in a timely manner and quality of the projects is satisfactory. The
coordination meeting shall be chaired by ADC (F&P) and the participation of
PoE, SMT and CDLD-TA staff shall be mandatory.
v. ADC (F&P) being CDLD focal person at district level shall compile monthly
progress report received from SMT and PoE (on 5th of each month), on
prescribed format issued by PIU/DGLG office.
vi. After review, the report shall be forwarded to Coordinator CDLD, Commissioner
Office of respective division and Chief Foreign Aid at P&DD on monthly basis
before 10th of each month.
ii. In addition, the DMO will prepare a random inspection schedule for its
monitoring team, covering at least 3% and 5% of the on-going CDLD projects
every quarter in each district.
iii. The Commissioner shall call and chair the divisional monitoring meeting on a
quarterly basis to ascertain the progress of the CDLD Policy implementation
on behalf of the LGE&RDD and ensure the progress is on track.
European Union
(MTE, Annual Assessment, EU Delegation)
Third Party Verification
CBO,
VC / NC
i. In case, 1st installment is disbursed into CBO account, the work order is issued and
the CBO is unable to undertake the physical work as per the contract agreement.
(Ref. Grant Agreement clause 9.1, 9.2-a, 10.1, 10.2), the SMT shall re-visit such
CBOs to further mobilize and to start the physical work in compliance with the
agreed work plan mentioned in the DPP. Even after the intervention of SMT, if the
CBO is found non-responsive, a special TEC meeting will be convened to obtain
the consent and recommendation of the concerned line department. Upon failure
of taking any decision, the case shall be forwarded to DDC for taking appropriate
administrative action.
ii. Any social conflict found during the implementation which may create hindrance
in smooth implementation of the project shall be referred to the Tehsil Conflict
Management Committee.
iv. In case, if a CBO is found dormant, the Social Mobilizer/Engineer shall meet the
CBO members/community and try to revitalize the CBO and resolve any impeding
issue. If they fail in their attempt, they shall update Assistant Commissioner in their
respective Tehsil to conduct a meeting with the office bearers of dormant CBO to
ensure compliance with the agreement signed between district administration and
the CBO.
At the district and divisional level, the complaints are to be registered or submitted
to a focal point designated by the competent authority i.e. DCs of respective districts
and Commissioners of the respective divisions. The assigned focal persons will be
responsible for recording and processing of complaints as per the notified procedure.
The working of complaint cells in the offices of Commissioner / DC will be followed as
per guidelines.
1. Website
2. The hotline
A. Basic Information
Name of VC/NC Ward / Union council
Tehsil District
Total population (as per latest
Total Household at VC / NC
published census report)
Number of revenue villages / sub villages Number of hamlets
Name of revenue villages / sub-villages
Name of hamlets
B. Detail of Council Members
B1. Detail of members VC/NC
Number of General Councilor Number of Youth Councilor
Number of Women Councilor Number of peasant councilor
Number of minority councilor
B2. Detail of Member Tehsil council & District Councils
Name of Tehsil Council Member Name of District Council Member
B3. Name of MPA B4. Name of MNA
C. Grass Root level organization at VC / NC
Numbers of Water User
Numbers of PTCs1
Committees (WUC)
Number of Primary Care Management
Number of CBOs2 (Men)
Committee (PCMC) members
Number of village organization
Number of CBOs (Women)
(VO)
Number of any other organized
Number of registered Village Organizations
forum
D. Details of social service institutes at VC/NC level
Number of GPS3 (for boys) Number of students
Number of GPS (for girls) Number of students
Boys=…............
Number of GPS (mix) Number of students =……….............…
Girls=….............
Number of GMS4 (for boys) Number of students
Number of GMS (for girls) Number of students
1
Parent Teacher Council
2
Community based organization
3
Government Primary School
4
Government Middle School
Income generation
Duration of project
by (Men / women
Potential funding
Project proposed
village / Mohalla
Name of village
Estimated cost
Beneficiary HH
intervention /
Name of sub
Number of
(In month)
Proposed
sources
(In PKR)
please)
/ both)
project
S#
G. During annual review of VCDP existing priority list of schemes and newly added priorities
Name of sub village / Mohalla
Proposed intervention /
Duration of project
Name of village
Estimated cost
(In month)
(Yes / No)
(In PKR)
project
please
(Yes)
S#
5
Government High School
6
It may be CDLD, VC/NC fund, Tehsil, District & MPA funds etc.
7
It may be CDLD, VC/NC fund, Tehsil, District & MPA funds etc.
(ongoing, completed,
cancelled etc.)
other)
S#
Signed by:
Letter from Secretary VC/NC and resolution from elected council of VC/NC for the approval
of VCDP are mandatory.
Principle
S# Sector Specific project Beneficiary of the
project
1 Education Additional room in girls’ school Women
2 Education Missing facilities in girls’ school Women
3 Education Solarization in girls’ school Women
Repair and rehabilitation in girls’
4 Education Women
school
5 Health Labour room Women
6 Health Solarization in labour room Women
Social welfare and community
7 Vocational center for women Women
development
8 Sports, culture & tourism Construction of park Both
9 Education Additional room in boys’ school Men
10 Education Missing facilities in boys’ school Men
11 Education Solarization in boys’ schools Men
Repair and rehabilitation in boys’
12 Education Men
school
Social welfare and community
13 Construction of Eid Gah Men
development
Social welfare and community
14 Vocational center for men Men
development
15 Sports, culture & tourism Play ground Men
16 Agriculture, livestock and fisheries Godown Both
17 Agriculture, livestock and fisheries Storage room Both
Veterinary hospital, clinic and
18 Agriculture, livestock and fisheries Both
missing facilities
19 Health Construction of additional room Both
20 Health Repair and rehabilitation of rooms Both
21 Health Missing facilities in health Both
22 Health Solarization in health facilities Both
23 Health New health Facility Both
24 Irrigation/water management Irrigation channel/water courses Both
25 Irrigation/water management Check dam Both
26 Irrigation/water management Water harvesting structure Both
27 Irrigation/water management Tube well Both
28 Irrigation/water management Protection wall Both
Village / Mohalla VC / NC
Tehsil District
Date Number of Participants
1. Representation of all beneficiary 2. Participants agreed to resolve the
households are available in the meeting? same issue as prioritized by MIS from
(Y/N) * VCDP priority list? (Y/N) *
3. Does CBO exist? (Y/N)
4. Name of existing CBO
If Y, Q 4, 5 & 6 applicable.
6. Beneficiaries willing to revitalize the
5. Date of formation of existing CBO (if any):
existing (Y/N) *
7. Beneficiaries are willing to form a CBO 8. Community is willing to carryout O&M
(if there isn’t any). (Y/N) * of the project? (Y/N) *
9. Is there any social conflict/dispute? (Y/N) 10. Main tribes in the village:
11. Languages: 12. Main Sources of Income/ livelihoods:
13. Total HH 14. Beneficiary HH:
15. Male Beneficiaries: 16. Female Beneficiaries:
17. Total beneficiaries: 18. Requested Project Sector
*Negative response against any of the asterisk factor will result in project unfeasibility.
Social Benefits:____________________________________________________________
________________________________________________________________________
Economic Benefits:_________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
On Site
If Yes, Monitoring
Environmental Screening Questions Yes No Management
Mitigation Plan Responsibility
Responsibility
Activity may destruct/degrade natural
habitat?
Activity may degrade marginal lands?
Activity may significantly increase the
use of fertilizers application?
Activity may lead to erosion, vegetation
loss, and gully formation?
Activity may cause siltation due to
flooding and further meandering rivers
and waterways?
Activity may cause degradation of
protected habitats due to destruction in
and around protected areas?
Activity may cause Bio-diversity loss
due to a decrease in wild plants and
animal species?
8
To be filled after test result.
Signature:_____________________________ Signature:_________________________
I Secretary VC/NC confirm/verify, that the information related to the subject scheme is
correct in my knowledge. I am also verifying that no duplication appears to be involved in
the implementation of the subject project.
Signature: ____________________
________________________________________________________________________
________________________________________________________________________
Signature: ____________________
Dated: ____________________
• Responsible for the implementation of all milestones agreed in approved DPP work
plan, procurement plan and operation and maintenance plan.
• Get complete information from concern engineer about all components of approved
DPPs i.e. total estimated cost (CDLD share, community share), measurements of
project, drawing, design, required material, quality, and quantity of material, etc.
• Keenly observe the instructions delivered by implementing engineers and adopt the
same standards during the implementation of the scheme.
• During the implementation of the project, ensure proper record keeping of procured
material receipts, stock register, cash book, roaster and attendance register, labor
payment record, vehicle’s fares, and payments against the utilization of machinery,
etc. for CBO internal record.
• Cooperate with and facilitate the visiting line department and district monitoring
officials for inspecting their schemes under execution in all respects. Ensure that all
the necessary records are available on-site and can also be produced to the visiting
officials on demand.
Remarks of visiting officer about the project recorded in project register.
• To inform the general body of CBO about project total estimated cost, received cost
from government, expenses and the quality and quantity of work on a monthly basis.
• Presentation of signed documents i.e. cash book, stock register, payment register,
saving/O&M fund register, etc. to monitoring and auditing committee for their
verification and signatures on fortnightly basis. This will ensure the transparency of
CBO internally.
• Close coordination with concern line department for getting any guideline related to
operation and maintenance of the project.
• Ensure the monthly collection of O&M fund from all beneficiary households in support
of President and Secretary of CBO.
• Ensure close coordination with all stakeholders within and outside the CBO.
• Get complete information from concern engineer about all components of approved
DPPs i.e. total estimated cost (CDLD share, community share), measurements of
project, drawing, design, required material, quality, and quantity of material, etc. to
perform better monitoring and audit function.
• Inspecting the material and work quality and quantity, identifying issues and reporting
to the general body of CBO.
• Preparing an action plan for resolving issues and fixing responsibility for
implementation.
• Check stock register, cash book, raster and attendance register, receipts with the
materials procured by PMOMC during implementation and maintain check and
balance between released amount and expenditures.
• Monitor all the activities during the implementation of the project, check records
and conduct an internal audit and present their report to CBO general body for
rectification.
Note: Both committees are responsible to submit their reports to their general body.
General CNIC
Secretary Phone#
Gender
2. Particulars for the proposed project
2.1. Name of the project
2.2. Beneficiary details
3.3 Site Location: (South, East, West, North including location of the beneficiary population vis-
à-vis the main population centre, a major road or any other reference point. This should be
duly reflect in the map attached.
3.4 Work plan with mile stone, activities and timelines (Mark ü (start to end)
S# Milestone Activity Timeline (start to end)
1 W1 W2 W3 W4 W5 …..
1 Social Record
First Application/concern VC/NC wise MIS based merit list
شی ٹ
Attendance sheets / � احرضی
Resolutions from CBO
By laws
ت
Beneficiary list / مس�ف�ی�د وہےن واےل رھگاونں یک رہفتس
Village Map
Registration
Account Opening record (copies of CNIC etc.)
Account opening receipt
Land acquisition certificate (if applicable)
Grant Agreement between CBO and Deputy Commissioner
Others
2 Technical Record
CBO Socio-economic and technical feasibility
Survey sheet
Survey checklist
Water quality, resistivity and any other test (if applicable)
Detailed Project Proposal
i. Site plan
ii. Design Justification
iii. Detailed Drawing
iv. Detailed Cost estimates
v. Pre-Pictures
Non-duplication certificate from concern line Department
Desk Review of DPP
Technical Evaluation Committee (TEC) Screening sheet
3 Administrative Records
TEC meeting minutes (sanction of project highlighted)
Special TEC minutes in case of any variance related to project
District Development Committee minutes (approval of project highlighted)
Administrative Approval from Deputy Commissioner (AA of project highlighted)
Work Order from district Administration
1 The facts and figures given in the VCDP have been checked
Designation:______________________________________________________________
A. Social Aspects
Remarks
# Section Description Recommendations
Yes No
General information about the community and proposed project
3
Land acquisition affidavit (if applicable) attached with
DPP
Undertaking by CBO management in section 7 of the
DPP is duly signed?
B. Engineering Aspects
Remarks
# Section Description Recommendations
Yes No
Are the cost estimates based on latest MRS with area factor
C-5
applied?
Is the cost of Non Schedule Items (NSI’s) and carriage and
C-6 transportation considered realistically and according to the
ground situation?
Remarks:
1. Name 2. Name
Designation Designation
Department Department
Signature Signature
Date Date
Designation Designation
Department Department
Signature Signature
Date Date
5. Name 6. Name
Designation Designation
Department Department
Signature Signature
Date Date
AN AGREEMENT
WHEREAS the First Party has approved a policy namely, “Community-Driven Local
Development”, to provide an enabling environment for CBOs duly registered, to access
public funds, in the sectors as specified in Annex: ’13.1’ of Schedule, appended to this
Agreement (hereinafter referred to as the Schedule). These public funds may be utilized for
the capacity building of community developing infrastructure, improve public service delivery
system identified by Second Party, (hereinafter referred to as the “development work”)
and shall help decrease the trust deficit between the public office and the community.
AND WHEREAS, the First Party desires to carry out the development work and the
Second Party agreed to implement the development work, supported financially by the First
Party, with the maximum of the____ % percent (hereinafter referred to as the “Government
Fund”), with the minimum (ten percent) 10% contribution by the Second Party, in cash or
kind i.e. in shape of labor, providing raw materials or other services towards the completion
of development work, as the case may be, (hereinafter referred to as the “Contributed
Fund”), on such terms and condition as specified under this Agreement.
3. Mode of Payment: 3.1 The payment from Government Fund to the Second
Party by the First Party shall be as follows:
Total Rs.__________
3.2 The First Party shall pay the first instalment to the
Second Party at the time of signing of this Agreement.
7. Force Majeure: The Parties shall not be responsible for any delay in
fulfillment of the obligations under this Agreement due to
circumstances of Force Majeure, such as acts of God,
war, riots, civil commotion, strike, lockouts and other
circumstances and disturbances, which are beyond the
control of both the Parties. Any Party unable to fulfill
the obligations under this Agreement shall immediately
within one week inform other Party of the beginning
and discontinuation of such circumstances. In the case
of fulfillment of the obligations, the time of limit shall be
extended for a corresponding period of time.
8. Dispute Resolution: 8.1 The Parties shall attempt in good faith to negotiate a
settlement to any dispute between them arising out of
or in connection with this Agreement;
IN WITNESSES WHEREOF, both the Parties hereto have herein set their hands and seal
the day and year first written above:
For and on behalf of the First Party. For and on behalf of the Second Party.
WITNESSES: WITNESSES:
Roads (Link / Rural Roads, Bridges, Culverts, Works (Street Pavement, Waiting Areas in public
Protection walls for Roads). service areas, Street lights).
Agriculture, Livestock, Fisheries and Farm Irrigation / Water Management / Soil and
Forestry (Fruit Processing units, Godowns, Water Conservation (Water Courses/channels,
Warehouses, Missing facilities in animal clinic / Check Dams, Flood protection walls, Water Storage
hospital, Fish Farms and hatcheries). Tanks).
Others.
Project Code:_____________________________________________________________
Tehsil:_______________________________ District:_____________________________
Bank Name:______________________________________________________________
Amount in Word:
(Resolution from CBO for the request of 1st installment must be attached with this form).
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
B. Achievement of milestones:
1 Milestone # .…………….......................................................……………………… %
2 Milestone # .…………….......................................................……………………… %
3 Milestone # .…………….......................................................……………………… %
4 Milestone # .…………….......................................................……………………… %
5 Milestone # .…………….......................................................……………………… %
(Field Engineer from PoE will provide support during the preparation of this report).
Period:___________________
(Item 1)
(Item 2)
(Item 3)
(Item 4)
(Item 5)
(Item 6)
(Item 7)
Total
(Field Engineer from PoE will provide support during the preparation of this report).
Period:___________________
(Item 1)
(Item 2)
(Item 3)
(Item 4)
(Item 5)
(Item 6)
(Item 7)
Total
To:
____________________________
____________________________
You are hereby advised to start physical construction work on the site with immediate effect
under the directions of engineer-in-charge. The said scope of work must be completed within
the stipulated time period of____________ months positively, effective from this______day
of_________ 201________.
1
2
3
4
5
Total:
GoKP (CDLD) Share (90 %):
CBO Share (10 %):
Note: The final payments would be carried out on work done basis as per GoKP standard
procedures in vogue.
CERTIFICATE-A
Basic Information:
Project Name:____________________________________________________________________________________________________
Sector:____________________________________________________________________________________________________________
VC / NC Name:___________________________________________________________________________________________________
Tehsil:_______________________________________________District:______________________________________________________
Completion Cost (in PKR):_______________________________________________________________________________________
Affirming the contract agreement and amendments, the project was started on____________________________
________________________________________ and successfully completed on_________________________________________
It is agreed that the repair and maintenance of the cited project will be the responsibility of the
concerned CBO while the line department will provide technical support on request. Secretary VC/NC
will oversee the periodic maintenance conducted by the CBO.
CERTIFICATE-B
Basic Information:
Project Name:____________________________________________________________________________________________________
Sector:____________________________________________________________________________________________________________
VC / NC Name:___________________________________________________________________________________________________
Tehsil:_______________________________________________District:______________________________________________________
Completion Cost (in PKR):_______________________________________________________________________________________
Affirming the contract agreement and amendments, the project was started on____________________________
________________________________________ and successfully completed on_________________________________________
It is agreed that the repair and maintenance of the project will be the responsibility of the concerned line
department from the date of handing over.
Date:_______________________________ Date:_______________________________
www.cdldta.pk
www.facebook.com/kpcdld
www.issuu.com/kpcdld