FITCHE TOWN
SUMMARY FOR 4 STORY OFFICE BUILDING
A) SUB STRUCTURE
B) SUPER STRUCTURE
6) FINISHING ETH.BIRR
7) GLAZING ETH.BIRR
8) PAINTING ETH.BIRR
9) SANITARY ETH.BIRR
Window
Window
a) W1 = 5700mmx12400mm m2 141.36
b) W2 =1500mmx5800mm m2 34.80
c)W-2 = 5700mmx15130mm m2 172.48
d) W-2 =5700mmx8040mm m2 91.66
Item
Description Unit Qty Amount
No
Main Building
e) W-2 = 5700mmx12400mm m2 141.36
f) W-2 = 2750mmx7410mm m2 40.76
g) W-2 =9100mmx2100mm m2 37.80
h) TW-1=5700mmx800mm m2 4.56
i) TW-2=2600mmx800mm m2 4.16
j)TW-4=1200mmx800mm m2 28.80
j)TW-3=2600mmx1500mm m2 58.50
h) TW-5=700mmx800mm m2 33.60
Window doors
10. PAINTING
10.01
Three coats of plastic emulsion paint to internal wall and
concrete surface m2 8,946.26
10.02
Ditto as item No.8.01 but to concrete ceiling m2 2,760.55
10.03 Quartize paint to external wall surface m2 3,121.00
Total Carried to Summary