Name of Project : Construction of New Bridge 70 m, 2 Span Pre-Stressed Box Girder Double Cell

Location of Project : Be'e Mos River, Kasnafar, Dare, Dili Municipality

TIME SCHEDULE

Duration Weight 1st Month 2nd Month 3rd Month 4th Month 5th Month 6th Month 7th Month 8th Month 9th Month 10th Month 11th Month 12th Month
NO. ITEM DESCRIPTION UNIT QTY
(week) (%) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

100 GENERAL REQUIREMENTS


102 Mobilization and Demobilization Ls 1.00 48.00 0.59 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Traffic Management and Safety Ls 1.00 48.00 0.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Project Name Plate Ls 2.00 2.00 0.01 0.00 0.00
Measurement and Fixing Ls 1.00 4.00 0.06 0.02 0.02 0.02 0.02
200 EARTHWORKS
201 Clearing and Grabbing Ha 0.27 2.00 0.01 0.00 0.00
204(1) Structure Excavation cu.m. 3,777.80 16.00 0.44 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
206(2) Granular Material for Backfill cu.m. 7,997.64 8.00 2.66 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33
300 SUB BASE AND BASE COURSE
303 Aggregate Base Class A cu.m. 245.45 6.00 0.43 0.07 0.07 0.07 0.07 0.07 0.07
400 SURFACE COURSES
402 Bituminous Prime Coat sq.m 1,636.31 1.00 0.10 0.10
403 Tack Coat sq.m 608.00 1.00 0.02 0.02
404 Asphaltic Concrete Binder Coarse (AC-BC) sq.m 1,636.31 2.00 1.80 0.90 0.90
405 Asphaltic Concrete Wearing Coarse (AC-WC) sq.m 608.00 2.00 0.47 0.24 0.24
500 BRIDGE CONSTRUCTION
Concrete Pile Cast in Steel Pipes (K-300), D =
501 (18) m 1,080.00 8.00 34.45 4.31 4.31 4.31 4.31 4.31 4.31 4.31 4.31
1000mm
505 Reinforcing Steel kg 168,230.20 25.00 9.34 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37
506 (1) Concrete K-200 for Lean Concrete cu.m. 64.79 7.00 0.36 0.05 0.05 0.05 0.05 0.05 0.05 0.05
Structural Concrete K-250 (Concrete Works Include
506 (2) cu.m. 136.47 4.00 0.97 0.24 0.24 0.24 0.24
Framework Works)
Structural Concrete K-300 for Abutment, Pier and
506 (3) Sidewalk (Concrete Works Include Framework cu.m. 855.15 18.00 9.45 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52
Works)
Structural Concrete K-500 for Box Girder
506 (4) cu.m. 581.34 12.00 13.89 1.16 1.16 1.16 1.16 1.16 1.16 1.16 1.16 1.16 1.16 1.16 1.16
(Concrete Works Include Framework Works)
512 (5) Elastometic Bearing Pad 500x500x25,4 each 12.00 4.00 0.91 0.23 0.23 0.23 0.23
512 (5) Elastometic Bearing Pad 750x750x25,4 each 6.00 4.00 0.97 0.24 0.24 0.24 0.24
507 (1) Strands Cable kg 34,673.18 6.00 2.69 0.45 0.45 0.45 0.45 0.45 0.45
508 Post Tensioned Prestressing and Grouting nos 36.00 8.00 7.73 0.97 0.97 0.97 0.97 0.97 0.97 0.97 0.97
509 Tendon m 1,430.18 12.00 1.66 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14
510 Expansion Joint m 22.00 2.00 0.09 0.05 0.05
512 PDA Test Pile nos 3.00 1.00 0.11 0.11
Road Lighting, Steel Pole Single Armature, LED
513 each 6.00 4.00 0.36 0.09 0.09 0.09 0.09
Lamp 100 Watt
514 Panel Box and Accessories each 1.00 4.00 0.01 0.00 0.00 0.00 0.00
DRAINAGE AND SLOPE PROTECTION
600
STRUCTURE
606 Stone Masonry (Retaining Wall of Water Guide) cu.m. 3,546.15 20.00 8.53 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43
607 Plastering 20mm Thickness with 1Pc : 4sd sq.m 1,406.00 20.00 0.23 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
608 Galvanised Pipe 4" for Drainge m 58.00 20.00 0.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
609 Gabions cu.m. 856.00 6.00 1.38 0.23 0.23 0.23 0.23 0.23 0.23
700 MISCELLANEOUS STRUCTURES
706 (1) Warning Sign each 8.00 4.00 0.06 0.01 0.01 0.01 0.01
707 (1) Reflective Thermoplastic Pavement Marking sq.m 54.81 4.00 0.07 0.02 0.02 0.02 0.02
800 BIO ENGINEERING WORK
801 (4) Vegetative Propagation each 24.00 4.00 0.04 0.01 0.01 0.01 0.01
TOTAL 100.00
Weekly Accomplishment 0.00 4.71 4.71 4.77 4.77 5.27 5.27 5.27 5.27 1.10 0.94 0.94 0.94 2.24 2.24 2.68 2.68 2.68 2.68 2.68 2.68 2.68 2.68 2.38 2.38 2.43 2.05 2.05 2.05 2.29 2.29 3.46 3.36 0.95 0.93 0.45 0.45 0.45 0.45 0.50 0.50 0.12 0.12 0.14 0.14 0.04 0.04 0.02 0.02
Cumm. Accomplishment 0.00 4.71 9.43 14.2 19.0 24.2 29.5 34.8 40.0 41.1 42.1 43.0 44.0 46.2 48.4 51.1 53.8 56.5 59.2 61.8 64.5 67.2 69.9 72.3 74.6 77.1 79.1 81.2 83.2 85.5 87.8 91.3 94.7 95.6 96.5 97.0 97.4 97.9 98.4 98.9 99.4 99.5 99.6 99.7 99.9 99.9 100 100 100

Prepared by:

Eng.Paul
Engineer