Republic of the Philippines

PROVINCE OF SURIGAO DEL NORTE


Municipality of ___________

PROJECT PROPOSAL FOR FOOD FOR WORK

I. Title of the Project : (Indicate here the proposed project/activity)


II. Location/Project Area : :
III. Project Duration :
IV. Total Number of Beneficiaries :

SEX: MALE: _______ FEMALE: ___________

PER CLIENTELE CATEGORY:

SENIOR CITIZEN:
PWD:
SOLO PARENT:
FORMER REBELS:
PWUD:
Others, please specify:

Please indicate also the number of


PANTAWID :
NON-PANTAWID:
Listahanan Poor:

V. Rationale :

Indicate here the following information:


 Disaster event that struck the municipality, affected families, damaged
houses, number of evacuees, damaged to livelihood and properties
 Describe the current condition of the affected LGU
 Describe the rehabilitation and recovery activities proposed
 Discuss how the food for work would benefit the affected beneficiaries
 Specify the activities/project to be proposed and the benefits to the
affected families
 Discuss who are the beneficiaries of this FFW activity

The municipality of Bacuag was heavily affected when Typhoon Basyang


struck in the morning of February 13,2017. Typhoon Basyang brought heavy
rains which caused flash flood affecting 2,446 families in 9 barangays. The
storm left with 74 persons injured, ten (10) houses totally damaged and 181
houses partially damaged. Lots of livestocks and working animals found
dead, rice fields and other agricultural properties were heavily damaged
which greatly affect the livelihood and the economic situation of the families.
Food became scarce because of the disaster.

The roads that were flooded are filled with muds woods and other solid
materials brought by flood waters that has caused disturbance to
accessibility. The houses are also full of muds and different kinds of dirty
materials that families need to allot days to clean up so it can be safe to live
in. aside from the houses, Day care Centers and school classrooms in some
school, churches and other important infrastructures have incurred damages
and were not spared with the annoying situation the aftermath of flooding.
The whole picture of barangays is dirty. People need to help and work
together to clear, clean their houses, infrastructure, facilities and the whole
community.

Families affected need help. They need food augmentation to mitigate


hunger while working together to clear, clean all the mess brought about by
disaster. Thus, this food for work assistance is being proposed.

VI. Objectives:

1. To encourage community participation in bringing back the normal


situation of the community.
2. To provide food assistance to beneficiaries in lieu of cash incentive as
they work for the benefit of the community.
3. To provide incentive to those strong-willed persons who offered
themselves to help in the community works.
4. To have a clean environment a community that is comfortable to live
at.

Enumerate the objectives of this FFW activity

VII. Brief Description of the Project:

Bacuag is one of the heavily affected municipalities of TS Basyang


affecting 2,446 families and incurred damages to infrastructure facilities such
as roads, schools, barangay halls, day care centers, houses and properties.
To facilitate immediate restoration, people need to work together for a
minimum of three days to have all the cleaning and clearing done the soonest
possible time.
Briefly discuss here the project/activity to be conducted
Indicate the expected number of days the activity/project will be completed
and the required number of persons to work

Barangay Tota- Part Activities/Project to Location of Estima- No. of Total


lly ia- be worked on (pls. the ted persons FFPs
damag lly specify length and Project/Act No. of Require require
ed dam width (meters) for ivity days to d to ment (2
houses age each activity complet work days
d e the (note: work is
Hou work should equivale
ses base on nt to 1
the FFP)
computa
tion of
technica
l staff
e.g
Enginee
r)
Example for Brgy. 126 126 126
Surigao City: Cagniog houses persons benefici
4mX5m temporary at 10 aries x
wooden house days per 5FFPs
construction house= (for 10
1,260 days)=
days 630FFP
s
Cambuayo 5 2 Cleaning/ clearing 3 days
n of roads,canals,
houses, barangay
hall,schools,day
care
Center,Barangay
Site
Campo Cleaning/ clearing 3 days
of roads,canals,
houses, barangay
hall,schools, day
Care Center,
Multipurpose hall
Dugsango 3 Cleaning/ clearing 3 days
n of roads,canals,
houses, barangay
hall,schools
Pautao 4 6 Cleaning/ clearing 3 days
of roads,canals,
houses, barangay
hall,schools
Payapag 1 2 Cleaning/ clearing 3 days
of roads,canals,
houses, barangay
hall,schools
Poblacion 0 0 Cleaning/ clearing 3 days
of roads,canals,
houses, barangay
hall,schools
Pongtud 3 Cleaning/ clearing 3 days
of roads,canals,
houses, barangay
hall,schools
Sto. 0 0 Cleaning/ clearing 3 days
Rosario of roads,canals,
houses, barangay
hall,schools

VIII. Budgetary Requirements:

FUND SOURCE CASH IN-KIND


COUNTERPART COUNTERPART
DSWD None Total beneficiaries: 126
Number of days: 10
days
Total FFPs required:
630 (1 FFP for 2 days
work)
MLGU Counterpart Indicate the in-kind
counterpart and the
equivalent cost
BLGU Counterpart
Other donors, please
specify (e.g. IOM,
TESDA)
TOTAL

Note: maximum of 10 days for families with damaged houses


: 1 Family Food Pack (pre-packed) is worth Php694.00. This is
equivalent to 2 days consumption for a family of 5 which means 1 FFP for 2
days work.

IX. Target schedule of Activity:

The Food for Work project shall be done in the month of March 2018
specifically on the first week. The beneficiaries are required to sign a daily
attendance and submit photos before, during and after completion of the work
with signed Relief Distribution Sheet upon receipt of the food incentive.

X. Recommendation:

The undersigned respectfully request and recommends the approval of a


3 days FOOD FOR WORK PROJECT for the municipality of Bacuag for a
total of 6,249 food/family pack that would benefit the 2,143 family victims
of TS Basyang.

Prepared by:

MSWDO

Noted by:

Municipal Mayor

Recommending Approval:

MELANIE G. JUAN
OIC-Division Chief, DRMD

Approved by:

MARI-FLOR A. DOLLAGA-LIBANG
Regional Director
Note: Please attach the before pictures (area of the project location) as well
as the masterlist of the beneficiaries in the submission of this project proposal
.

DOCUMENTS TO BE COMPLIED AFTER THE PROJECT COMPLETION:

1. Geotagged PICTURES DURING THE FFW ACTIVITY


2. GEOTAGGED PICTURES AFTER THE PROJECT COMPLETION
3. ACCOMPLISHMENT REPORT
4. Signed RDS