LP 02 - Post Ops
LP 02 - Post Ops
SDL-Nobel Workshop
LP002
Page 1 of 10
Lifting Date: 07/05/2021
Title : Lifting of the Winch Frame 002
Plan No: Rev: 00
Number of personnel required / roles and competency level of supervision (PIC) required:
1 x Mobile Crane Operator
1 x EOTC Crane Operator
2 x Load Handlers
1 x Banksman
All certification is in accordance with 100572 – BP Management of Lifting Operations and Lifting Equipment
Certified Lifting Appliances and Accessories to be listed including details of operating capacity (Specify Type,
WLL, Capacity charts or rigging mode):
Page 2 of 10
Lifting Date: 07/05/2021
Title : Lifting of the Winch Frame 002
Plan No: Rev: 00
1. All personnel associated with lift should review Risk Assessment and complete TBT prior to commencing
lifting operation.
2. Banksman, crane operators to ascertain environmental conditions are within crane parameters before
commencing lifting operation.
3. Lifting crew ensure no conflicting activities are ongoing in surrounding/landing areas and /load path is clear
of obstructions.
4. Lifting crew ensures barriers have been placed covering all intended load path during lift.
5. Lifting crew to carry out final checks to ensure no dropped object hazards such as tools and other equipment
have been accidently left on the load.
6. Mobile Crane operator to set up Crane at nominated area at max radius of 6 mtr.
7. EOTC Operator bring Overhead Crane above the frame in dedicated area.
8. Install all accessories as shown on the picture (2 leg wire rope sling with 25 Te shackle on each leg should be
installed on the padeyes near the winch, two 8 Te round slings should be installed on other end padeyes by 25
te shackle, top end attached by 35 Te shackle to the load cell on EOTC hook)
9. Banksman give signals to crane operator to bring the hook above the load.
11. Under the instruction of the banksman position crane boom over the load (max boom length is 11.5mtr) and
ensure load line is plumb.
12. Truck should park in line with the load in a distance of about 2 meters.
13. Banksman check that Crane hooks alignment is in line. Banksman to instruct Crane operators to slowly take
the tension, slowly take weight of load and stop and ensure the weight of load is proper on the both cranes
(check the load on EOTC with the load cell – load should be no more than 7.88 Te) and slings are not twisted.
14. Lift the load at maximum 1.5mtr height from the ground and stop.
15. Banksman give the signal to the truck driver to move under the load.
16. Once in place, Banksman ensure truck driver is away from truck and load on a safe area.
17. Banksman confirm the landing point and give signal to lower down slowly.
18. As soon as load is landed to the bed of the truck Banksman check correct position and security of the load.
20. Riggers disconnect the slings from the hooks and load.
24. Above mentioned steps to be used for Lifting both Winch frames. Crane will be repositioned
and all parameters will stay same as mentioned in LP.
Page 3 of 10
Lifting Date: 07/05/2021
Title : Lifting of the Winch Frame 002
Plan No: Rev: 00
ONSHORE
Page 4 of 10
Lifting Date: 07/05/2021
Title : Lifting of the Winch Frame 002
Plan No: Rev: 00
Diagrams, Drawings, Photos or Sketches (include key dimensions, showing pick up and set down locations):
Drawings or sketches may be on a separate sheet; best practice is to have scaled sketch on top of underground utilities drawing
however a sketch with dimensions is acceptable.
For Mobile Cranes Plan View – Pick up, set down location, direction and path of slew/load. Crane location and set up
dimensions. Proximity of underground services. Worst Case radius. Outrigger position and load spreading details.
For Mobile Cranes Side Elevation – Head room limitations. Boom clearance. Tail clearance at slew path. Height of load at
worst case.
Pic.1
Page 5 of 10
Lifting Date: 07/05/2021
Title : Lifting of the Winch Frame 002
Plan No: Rev: 00
Crane selected model and capacity: Liebherr Mobile Crane 1100-4.2 SWL 100 Te
Page 6 of 10
Lifting Date: 07/05/2021
Title : Lifting of the Winch Frame 002
Plan No: Rev: 00
Page 7 of 10
Lifting Date: 07/05/2021
Title : Lifting of the Winch Frame 002
Plan No: Rev: 00
For none pre-slung loads – Pad eye / shackle interface details, Interface between accessories and lift points, sling tensions
and bending efficiency, refer to sketch if required:
Assessment to whether to use tag lines, hands free poles including their hazards and limitations:
Pre-use inspection and physical test of the end stops of the runway beam if applicable:
Specify the method used to identify underground utilities if applicable, i.e. refer to site underground utilities drawings or if the
drawings are not available the sub-surface survey should be conducted by competent person using techniques/tools such as ground penetrating
radar, pipe and cable locator, electromagnetics etc. to determine underground utilities.
Approved by: S. Krokhina Job Title: Lifting Coordinator Signature: Date: 14.03.21
Page 8 of 10
Lifting Date: 07/05/2021
Title : Lifting of the Winch Frame 002
Plan No: Rev: 00
Detailed safe operating limits of the lifting equipment (capacity charts or load curves).
Page 9 of 10
Lifting Date: 07/05/2021
Title : Lifting of the Winch Frame 002
Plan No: Rev: 00
1 Check that the crane driver has carried out his pre use inspections
Əmin olmaq ki kran operatoru gündəlik yoxlamanı keçirib və yoxlama vərəgəsini
doldurub
2 Check radius / counter balance charts with the crane driver /
Kran operatorla birlikdə kranın yükqaldırma cədvəlini yoxlamaq
3 Check that worksite is free from any obstruction /
İş yerində maneələrin olmamasını yoxlamaq
4 Check the path of the load for any obstruction /
Yükün yolundə maneələr olmamasını yoxlamaq
5 Check landing area for any obstruction /
Yük qoyulan yerin maneələrin olmamasını yoxlamaq
6 Check if the exclusion zone was properly barriered /
Əmin olmaq ki təhlükəli zona baryer olunub
7 Check the safe working load of rigging is greater than the weight of the load to be
lifted /
Əmin olmaq ki avadanlığın yükqaldırma qabiliyyəti qaldırılan yükün çəkisindən artıqdır
8 Is the equipment certified /
Əmin olmaq ki yükqaldırma avadanlığın sertifikatı var
9 Carry out pre use inspection of rigging equipment /
İstifadədən qabaq yükqaldırma avadanlığları yoxlamaq
10 Check the rigging arrangements and ensure there is no potential for load swinging
during the lift /
Yoxluyub əmin olmaq ki yük düzgün qoşulub və yükqaldırma zamanı yellənməyəcək
11 Carry pre lift inspection of item to be lifted for dropped objects /
Qaldırılan yükün üzərində düşən əşyaların olmamasını yoxlamaq
12 Make sure all members of the work party have read and understand the work method
statement /
Əmin olmağ ki yükqaldırma əməliyyatında iştirak edən işçi heyyət yükqaldırma planını
oxuyub və başa düşüb
Page 10 of 10