Professional Documents
Culture Documents
Para 14 - State of U.P. vs. Ram Nath
Para 14 - State of U.P. vs. Ram Nath
I n m a n y contracts, d u r i n g t h e progress o f t h e w o r k , as a r e s u l t o f
drastic change i n designs, d r a w i n g a n d specifications, t h e contractor i s
required to execute t h e tendered i t e m s f o r i n excess o f t h e tendered
quantities o n w h i c h invariably h i s tender i s based. S o m e t i m e s t h e
excess o r additional quantities o f s o m e o f t h e tendered i t e m s exceed b y
1 0 0 % to 5 0 0 % even m o r e . I n such cases a question often arises
w h e t h e r t h e contractor u n d e r t h e variation clauses i s liable to execute
t h e extra o r additional quantities o f t h e tendered i t e m s a t t h e tendered
rate to a n u n l i m i t e d extent. I t often happens t h a t a contractor, f o r
various reasons, quotes a n a b n o r m a l l y h o w rates f o r certain i t e m s t h e
quantities o f w h i c h a r e few o r h e m a y b e h a v i n g s o m e facilities to
execute t h a t i t e m s i n question a t comparatively l o w rates. A n o t h e r
aspect f o r consideration o f t h i s question w i l l b e t h a t t h e contractor
tendered h i s rates o n t h e basis o f t h e quantities m e n t i o n e d i n t h e
tender a n d also t h a t d r a w i n g s , designs a n d specifications a n d i f t h e
quantities o f a n y o f t h e tendered i t e m s increased drastically o r b e y o n d
a n y reasonable percentage, w i l l b e liable to execute t h e same b e y o n d
a n y reasonable l i m i t . S i m i l a r question w i l l arise w h e n there i s reduction
i n t h e tendered quantities o f t h e tendered i t e m o r i t e m s . I n such a
situation, t h e m o s t i m p o r t a n t factor to consider w i l l b e as to w h a t
w o u l d b e t h e reasonable variation i n t h e tendered quantities s o as to
b i n d t h e contractor to execute a t t h e tendered rate. I t has been
suggested b y D u n h a m i n h i s Treaties o n contract, specifications o f L a w
f o r Engineers, ( 1 9 5 8 ) E d i t i o n , a t p . 2 1 4 t h a t a change o f less t h a n 5 %
w i l l b e insufficient to constitute a j u s t c l a i m f o r a n extra w o r k . I t has
been f u r t h e r suggested t h a t t h e contract s h o u l d state t h e permissible
variation in the quantities and such a statement will avoid many
arguments.