Professional Documents
Culture Documents
Cef - Week 32 Report
Cef - Week 32 Report
This report reflects the weekly construction progress for the secondary school and it is compiled by
the Clerk of works and reviewed by the CEO Charlene Education Foundation. The report highlights
work on by 3 contractors on 6 ongoing construction projects.
ACTIVITES EXECUTED DURING THE COURSE OF THE WEEK UNDER DIFFERENT CONTRUCTORS
This Hoima based company was contracted to build the three classroom block which is finished and
currently completing labs 1&2 and in the middle of constructing the bathrooms for girls. The
contractor has also been contracted to build an incinerator at the school girl’s wing.
03rd/ 07 / 2022 Fixing drainage channel cover slabs Another layer of ever green
Painting classroom windows paint was added on classroom
windows
04th/ 07 / 2022 Casting drainage channel cover slabs Suitable formwork for the
cover slabs was made and wire
mesh included before casting
to reinforce the concrete
05tht/ 07 / 2022 Excavating the splash apron foundation at Some Workers stayed idle due
the shower room block to lack of materials on site
06th / 07 / 2022 Blinding the splash apron foundation at Concrete of 1:3:6 mix ratio was
the shower room block used to blind the splash apron
Cleaning lab 1 block foundation.
07th / 07 /2022 No serious activities of site Workers are idle on site
08th/ 07 / 2022 Brick work for the splash apron at the A stretcher bond was used to
shower room block build the splash apron
09th/ 07 / 2022 No active work on site
CHARLENE EDUCATION FOUNDATION WEEKLY REPORT (WEEK 32)
The company has its headquarters in Masindi Municipality. It finished the construction of the 18
stance lined latrines (Students 10 stances, Teachers quarters 4 stances and school Admin 4
stances) and a dormitory block at the school complex. It also delivered 20 Musizi trees for the
environmental restoration obligations and these have been planted.
High bury general contractors is based in Masindi. It completed the construction of the 4 in 1
teacher’s quarters at the school. It is currently embarked on the construction of the Kitchen and
Dining facility at the school.
03rd/ 07 / 2022 Supporting aligned trusses at the kitchen Only treated timber was used
section of the dining hall block
04th/ 07 / 2022 Supporting aligned trusses at the kitchen 100x50mm timber pieces were
section of the dining hall block used for support and ceiling
Fixing verandah ceiling fixing
05tht/ 07 / 2022 Purlin fixing at the kitchen section of the Purlin spacing was 900mm c/c
dining hall block
Fixing verandah ceiling
06th / 07 / 2022 Purlin fixing at the kitchen section of the Expanded metal lathe from
dining hall block roofing was used for the
Fixing verandah ceiling verandah ceiling
07th / 07 /2022 Filling hardcore in the built splash apron Steel hardcore was used for
at the dining hall the splash apron
Fixing verandah ceiling
08th/ 07 / 2022 Filling hardcore in the built splash apron White paint (weather guard)
at the dining hall was applied on fascia board
Fixing verandah ceiling timber
Painting fascia board
09th/ 07 / 2022 Filling hardcore in the built splash apron Wood glue was applied at
at the dining hall fascia board joints.
Fixing fascia board timber
CHARLENE EDUCATION FOUNDATION WEEKLY REPORT (WEEK 32)
Figure 4: Crashing hardcore placed in the splash apron at the dining hall block
Figure 5: Fixing roof purlins at the kitchen section of the dining hall
CHARLENE EDUCATION FOUNDATION WEEKLY REPORT (WEEK 32)
Figure 8: Filling the Fixed expanded metal lathe with mortar at the dining hall block
Site visit by CEO-Charlene, Director-Cane investments and the Quality assurance engineer
The visit was aimed at identifying defects and also suggesting possible ways to fix them before the
retention period (4months from April) expires.
Figure 11: CEO-Charlene inspecting the built incinerator at the girls' dormitory
Figure 12 CEO-Charlene, Quality assurance engineer and contractors inspecting the work finishes in Lab 2 block
CHARLENE EDUCATION FOUNDATION WEEKLY REPORT (WEEK 32)
Figure 13: Inspecting the tank stand and its foundation under construction
Figure 14: The Quality assurance engineer and cane investment leaders inspecting the staff quarters’ latrine
CHARLENE EDUCATION FOUNDATION WEEKLY REPORT (WEEK 32)
The steel structure is 12m high with a baseplate welded at its bottom. The baseplate is to be fixed
onto a concrete pedestal by 4 M20 bolts
Figure 15: Substructure and super structure of the Wi-Fi network booster
Figure 16: Applying silver paint on the super structure of the network booster to protect it against hostile
environment
CHARLENE EDUCATION FOUNDATION WEEKLY REPORT (WEEK 32)
Mukati
Contractors
Classrooms
Makati
Contractors
Science labs
Mukati
Contractors
Girls bathroom
facility
Mukati
Contractors
Incinerator
Cane
Investments
Girls dormitory
Cane
Investments
18 stance pit
latrines
High bury
General
Associates
Teachers
quarters
High bury
General
Associates
Kitchen &
Dining
CHARLENE EDUCATION FOUNDATION WEEKLY REPORT (WEEK 32)