Professional Documents
Culture Documents
34 23 71-OCS TESTING AND COMMISSIONING-Rev 5c
34 23 71-OCS TESTING AND COMMISSIONING-Rev 5c
SECTION 34 23 71
PART 1 - GENERAL
1.1 DESCRIPTION
A. The Work specified in this Section includes final testing and commissioning of the
Overhead Contact System (OCS), and the furnishing of acceptance measurement
and test equipment required for the tests.
B. The Contractor shall furnish the special tools as specified in Section 34 23 70 for
acceptance measurement and test equipment:
D. At completion of the work, all acceptance measurement and test equipment shall be
turned over to Metro in serviceable condition.
B. The Contractor shall perform the Work included in this Section in strict
accordance with the requirements of the Approved Contractor's Quality Control
Program.
1.3 REFERENCE
A. Pertinent provisions of the following listed standards shall apply to the work of this
Section, except as they may be modified herein, and are hereby made part of this
Specification to the extent required:
B. Federal, State and Local Authorities: All applicable codes and regulations.
1.4 SUBMITTALS
3. Training schedule.
B. Test Program Plan: The Contractor shall submit a Test Program Plan for
acceptance. The purpose of this plan is to ensure that the Contractor has
considered all of the testing requirements contained in this and other sections of the
specifications, and has made adequate provisions for testing in his overall program
plans and schedules, and to achieve an early mutual understanding between the
Contractor and Metro on the range, depth and other aspects of tests to be
conducted. The Test Program Plan shall contain as a minimum the following data:
1. A flow diagram indicating the logical sequence of tests, starting with factory
tests and continuing on to conclude with field demonstration tests.
3. An outline and format of the procedure and test data sheets for each type of
test.
C. Test Procedures: Test procedures shall be submitted for acceptance. The test
procedure shall include, as a minimum: Objective and scope; test set-up; test
equipment to be used; personnel required for the test; estimated duration of the
test; pass/fail criteria; and samples of data sheets to be used. All tests must be
performed in accordance with the test procedures. No deviations will be allowed
unless accepted by Metro.
D. Test Reports: Six (6) certified copies of Test Reports shall be submitted for
acceptance. Test reports must contain all the data obtained during tests, an
analysis of the data and conclusions relating to the test pass/fail criteria outlined in
the test procedure. A test that fails must be repeated and any corrective action
taken to pass the re-test must be outlined in a new test report.
E. Types of Tests: The types of tests to be covered in the Test Program Plan shall
include those required for testing and commissioning the Overhead Contact System
following completion of construction, as specified hereinafter in Part 3 of this
Section. The following commissioning tests are required:
1. Acceptance Measurements.
A. The field service engineer and operation and maintenance instructors shall be
qualified to perform the functions as indicated. The Contractor shall submit a
resume for each individual nominated, a minimum of 120 days prior to the approved
scheduled date for the commencement of training.
PART 2 - PRODUCTS
2.1 MATERIALS
A. General
2. The Contractor shall provide spare parts as required to conduct the start-up
and testing.
3. The Contractor shall furnish the special tools, and all other equipment and
personnel services necessary to make Acceptance Measurements. The
Contractor shall also provide all the electrical equipment and personnel
services required to perform the OCS Electrical Tests.
PART 3 - EXECUTION
A. The Contractor shall provide the services of a qualified field support engineer at the
project site, to assist as required during startup and system integration testing.
B. Upon approval, the field service engineer shall advise Metro on traction power
system energization and start-up.
C. The field service engineer shall have a thorough knowledge of the Overhead
Contact System as well as installation, start-up, and testing requirements for all
components furnished under this Contract.
D. The field service engineer shall be available on site 5 working days after notification.
Weekly logs shall be maintained and submitted. Logs shall show tasks performed
with dates and duration.
3.2 START-UP
A. The Contractor shall provide labor and tools to support integrated system testing.
Testing support includes:
B. The Contractor shall advise Metro regarding test procedures, analysis of results,
and recommended correction actions.
A. The acceptance measurement and test equipment will be used by the Contractor
and Metro for checking the location of the contact wire, and verifying that the
registration assemblies conform to the clearance requirements of the pantograph
clearance envelope. Each item of equipment will be used as follows:
3. The mobile height and stagger gauge will be used only on electrically de-
energized overhead catenary/conductor rail, and for two purposes:
a. For visually checking the location (height and stagger) of the contact
wire throughout the completed new electrified lines/conductor rails.
B. One insulated telescoping height measuring stick, and one optical stagger gauge,
shall be readily available for use at any time during the construction and acceptance
measurement periods.
C. All measuring tapes, poles, sticks, etc., used to collate data when the OCS is
energized must be non-conducting. In no circumstances will use of metallic or
conductive measuring tapes, chains and other devices be permitted.
A. Upon completion of all construction, the Contractor shall measure the contact wire
height, stagger, and other required dimensions and record the readings on an
Acceptance Measurement Form, in the presence of Metro.
C. The Contractor shall execute corrections at no further cost to Metro, except for
adjustments required by Metro which are changes beyond the requirements
specified in the Contract Documents.
D. After execution of corrections, the Contractor shall remeasure and record affected
data and submit the results to Metro.
E. The work of this Section will not be complete until corrections are completed and
accepted by Metro.
A. At Contact Wire Level, the Contractor shall make the following checks, and remedy
unsatisfactory conditions uncovered therein:
4. Check messenger wire for damage to strands. Check conductor rail fittings.
7. Check that jumpers are of correct type, have adequate travel capability, are
properly fitted, and are well formed to reduce fatigue failure.
10. Check that a wire passing through a cantilever and not attached to it will
clear any part of this cantilever by at least 3 inches throughout the
temperature range 25-130 degrees F.
B. From the Ground, the Contractor shall make the following checks:
3. Check that hangers are plumb and within design position. Check the
conductor rail is installed plumb with adequate insulation and supports.
4. Check out safety requirements in accordance with General Order No. 95,
and other applicable safety codes.
5. Check the system integrity like section gaps and insulated overlaps, and
ensure all the installation in compliance with the design of Engineer Record.
A. General: The purpose of these tests is to verify the mechanical and electrical
clearances of the light rail vehicle (LRV) units on each section of the system. The
tests shall be conducted after all installations are complete. Any section found to
have insufficient clearance shall be adjusted to provide the required clearance.
C. LRV Clearance Envelope: Tests shall be performed with an LRV towed or pushed
through each track section. The following tests shall be performed:
1. Dead Slow Tests at Walking Speed: The driver of the towing unit must be
prepared to stop at short notice during these tests.
2. Procedures: The test entails short circuiting a discrete section of the OCS
by connecting the OCS to its rails at one end, and applying a DC voltage at
the other end. The length of section under test should be about 1 to 2
miles. The test shall be carried out in the following steps:
in series).
3. Precautions: The tests required for the loop resistance require passing
relatively high DC currents through the OCS and rails. Proper regard must
be paid to safety. Test zones shall be clearly identified. All safety
requirements established in the Safety program concerning the public, work
personnel and equipment shall be strictly enforced. Personnel not directly
associated with the tests should be clear of the tracks. The section of OCS
and associated feeders under test must be isolated from the adjacent
sections of the system.
shall be used for the test. Hi-pot tests shall be carried out on the
OCS sections as soon as possible after the continuity tests have
been completed, in order to ensure that all of the section being
tested is electrically continuous and is subjected to the test voltage.
Leakage currents between 0 and 5 mA can be expected for section
lengths of 1-2 miles.
2. Procedure for Main Line Tracks: Along-track feeders which are electrically
common to the OCS but disconnected from the substations. Adjacent OCS
sections which are electrically isolated from the section under test shall be
grounded by connecting the OCS to the rails. All surge diverters shall be
disconnected from the section under test. A DC test voltage shall be
applied to each OCS section in 1 kV increments up to the nominal test
voltage. The test voltage shall be held for 30 seconds at each increment.
Circuit connections shall be as shown in Attached Figure D-1. The leakage
current at each value shall be measured and recorded as shown in attached
Table D-1, together with the weather conditions and temperature.
C. Section Proving:
3. The means of testing shall be through the energization of the OCS from
Traction substations and the applicable opening and closing of circuit
breakers, load breaks and disconnect switches. Contractor shall prove
that appropriate sections of OCS are energized and de-energized by
means of OCS voltage detection equipment. Any section of OCS that
should be de-energized, but is found to have a voltage of 50 volts or
greater will be deemed to have failed.
2. Procedure:
e. This procedure shall be repeated for each surge arrester location for
which a ground resistance measurement is required.
1. The current collection performance between the LRV and the OCS.
2. The adequacy of the power supplied by the OCS for required vehicle
performance.
B. Procedures:
2. During the current performance tests, particular attention shall be paid to:
4. The Contractor shall provide equipment for video recording of the current
collection performance tests. The video taping of one or more round trips
on the LRT extension is necessary to obtain significant data regarding
pantograph behavior and wire test. Provide a file with test data, which can
be printed, and record the force between the wire and the pantograph, wire
height, wire stagger, arcing (if any), distance travel and speed and location
of the specific event. The contractor shall deliver five videotapes with
recorded data in Excel format, which shall be used to facilitate detailed
analysis of the OCS after the tests have been made.
5. If adjustments are made to the OCS or to track alignment after the initial
tests, the tests shall be repeated on the affected sections, and their results
documented in the same manner as detailed in the preceding paragraphs.
A. Analysis of test results shall be performed jointly by Metro, the Overhead Contact
System designer, and the LRV manufacturer.
A. Records shall be made of all tests listed under Paragraph 3.06, 3.07, 3.08, 3.09 and
3.10 in accordance with the requirements of the:
Exhibit A
Exhibit B
DATE: _______________________________________
TEMPERATURE: ________________________________________
Exhibit C
Exhibit D
DATE: _______________________________________
TEMPERATURE: ________________________________________
END OF SECTION