4. PROJECT POWER SUPPLY: STUDY OF ENERGY EFFICIENCY: (The title of entrepreneur or legal entity who has
Designer: (name of the entrepreneur or legal entity Producer: prepared a study or studio, office)
which produced part of the technical documentation (Name and scientific name)
seat) (Authorization number)
Authorized person:
Chief designer: (name and scientific name) Authorization
License number: (number of personal license) Signature:
Signature:
(Name and scientific name) (number of personal license) 2.2.1. (2,3 ..) SUMMARY Technical report control
Appendix 5. Appendix
6.
DECLARATION acting technical control, SAREZIMEOM STATEMENTS OF CERTIFIED LITTA About
REPORTS TECHNICAL CONTROL PREDVIĐENIMMERAMA for fulfillment of basic requirements
ZAOBJEKAT
Authorized person: (Name and scientific name) Pursuant to Article 128 of the Law on Planning and Construction ( "Official Gazette of RS",
( 6P ° D Nos. 72/09, 81/09 - correction, 64/10 - US, 24/11, 121/12, 42/13 - US 50 / 13 - US, 98/13 -
Authorization
US, 132/14, 145/14, 83/18, 31/19 and 37/19 - dr. Act) and the provisions of the Ordinance
Signature: on the content, manner and process of making and ways of checking the technical documents
by class and purpose of objects, such as:
Number of technical documents: (identifier from the record en- authority / legal person)
Place and date: (place and date of manufacture)
CHIEF DESIGNER
Appendix 7. for the preparation of (design) which is part of the (types of papers) to (a type of construction,
namely the work) of the object (name of object with the location, number cadastral parcel
DECLARATION OF INVESTORS, acting STRUČNOGNADZORA and cadastral municipalities) is determined by:
AND CONTRACTOR (Name, professional title) (number of personal license)....................
that during the works (e.g., production facility HHHHH Commercial to KP HH / HHH H Appendix 9.
CO in H), there was a deviation of the Project for the execution of the object, that is, the
conceptual design (for structures, or works from article 145. LPC, which is not prescribed
project design witha performance), wherein a state is equal to the projected liquid state. GENERAL DOCUMENTATION OF ARTICLE 28
Investor: (name and surname or name of the investor, address) OVOGPRAVILNIKA
responsible person / representative: (name)
Signature:
Professional supervision: (name of the entrepreneur / legal entity acting terms of expertise
0.3. DECISION ON DETERMINING THE CHIEF DESIGNER Chief designer: License (Name, professional title) (number
number: of personal license)
Pursuant to Article 128a of the Law on Planning and Construction ( "Official Gazette of RS",
Nos. 72/09, 81/09 - correction, 64/10 - US, 24/11, 121/12, 42/13 - US 50 / 13 - US, 98/13 - Signature:
US, 132/14, 145/14, 83/18, 31/19 and 37/19 - dr. Act) and the provisions of the Ordinance on
the content, manner and process of making and ways of checking the technical documentation
Part of the project: (identifier from the register enter-
by class and purpose of objects, such as:
beginners / legal person)
GLVANIPRRETKATN Place and date: (place and date of manufacture)
for the preparation of (kinds of technical documentation) for (a type of construction, namely
the work) of the object (name of object with the location, number cadastral parcel and
cadastral municipalities) is determined by: 1.2. CONTENTS (Projects)
1.1. Home (project work) (A completed Form No. 9)
(Name, professional title) (number of personal license) ....................
1.2. Contents (project work)
Investor: (name and surname or name of the investor, address, 1.3. Decision on determining the designer (project work)
place) 1.4. Statement by the designer (project work)
Responsible / representative: (name)
1.5. text documentation
Signature:
1.6. numerical documentation
1.7. Graphic documentation
FORM AND TECHNICAL DOCUMENTATION Text items and illustrations certify all participants in the development
ELECTRONIC SIGNATURE FOR POTREBEOBJEDINJENE and technical control of the project in the manner prescribed by these Rules.
PROCEDURE Electronic signing is done after creating skog electronic document in
a prescribed format (.pdf, .dwg, .dwf (.dwfx)).
Electronic signing copies of required project is done:
introduction
1) the designer responsible person (entrepreneur or prav- legs of the
Certain terms used in this paper are tracing the meaning: person who is the holder of the design documentation);
1) document in the paper form is a document written in (the ratio of 2) chief designer;
printed) of the paper and is hand-signed by an authorized thereto, the legs of 3) responsible person / representative acting technical control.
persons, and stamped (when this is required by law); If the drawings are prepared as separate electronic
2) an electronic document is the document was originally in the ski documents, electronically signed them only chief designer.
electronic form, in a suitable electronic format (.pdf or .dwg or .dwf (.dwfx) b) The main volume
format), which is electronically signed by qualified electronic signature, and
a document that is originally created in a paper form, which is digitalized in electronic document format
accordance with the present attachment;
3) digitization of the documents is the translation of documents from The electronic document is prepared in .pdf format and is signed
point 1) of paper into electronic form (translating into .pdf for- mat) for the electronically.
purpose of integrated procedures, in accordance with this confirmation and Overa
ordinances that a qualified electronic signature that the electronic copy
faithful to the original form of the document . The main volume certify all participants in this project in the manner
4) electronic signature is an electronic signature put on a qualified prescribed by these Rules.
electronic document (.pdf, .dwg or .dwf (.dwfx) format), for the purpose of Electronic signing is done after the creation of an electronic document
unified procedure. The work steps .pdf format electronic documents is in a prescribed format (.pdf).
necessary to make the positioning of the electronic signature, so what is the Electronic signature main volumes are made:
point (field) that will bind an electronic signature. Positioning is performed 1) the designer responsible person (entrepreneur or prav- legs of the
on the first page of an electronic document, so that the new electronic person who is the holder of the design documentation);
signature is clear and visible. When the electronic document formats .dwg 2) chief designer.
and .dwf (.dwfx) does not perform positioning;
5) verification of the technical documentation prepared in electronic v) Projects (parts of the project according to the areas)
form or digitized for purposes of unified procedure, you is- electronic
signature, or putting on that documentation of the qualified electronic Format of electronic documents
signature advocating membership to the legal or authorized person of the
designer, and the qualified electronic signature of responsible and / or the General, textual and numerical documentation prepared in .pdf format
main developer od- nasal other people, when prescribed by these regulations; and electronically signed.
From the standpoint of unified procedure is that it is technically Graphic documentation project is delivered as one or more electronic
acceptable documents handwritten signatures responsible designers and other documents in the following formats:
persons that is provided to sign these documents, under the condition that the 1) .dwg or .dwf (.dwfx) which are electronically signed or
document is then digitizes (ypdf format) in accordance with this regulation, 2) .dwg or .dwf (.dwfx) that are not digitally signed, with a supporting
or that the technical documents in .doc format, enter clip pictures of your document .pdf format with the same content that is digitally signed.
handwritten signature, and thereafter converted to .pdf format or to technical
Overa
documentation in .pdf. format sign the appropriate functionality .pdf format
and to electronically sign the persons listed in this Annex. General, text, numeric and graphic documentation of projects certify
Form and sign the technical documentation participants in making this project work in the manner prescribed by these
Rules.
Documents comprising the technical documents are prepared as one or Electronic signing is done after creating skog electronic document in
more electronic documents (parts). a prescribed format (.pdf, .dwg or .dwf (.dwfx)).
The textual part of the technical documentation prepared in .pdf format Electronic signature part of the project is done:
and electronically signed. 1) responsible person of the designer of the project work
Graphic part of the technical documentation prepared in tracing (entrepreneur or legal entity who is the bearer of the work of the technical
possible formats: documentation);
- .dwg or .dwf (.dwfx) which are electronically signed or 2) responsible designer of the part of the project;
- .dwg or .dwf (.dwfx) that are not digitally signed, with a mandatory 3) technical control of the work in a project (only in the case when a
preparation and the same content of the document in the PDF format, which prescribed of the design of the building permit).
is electronically signed. If the graphic documentation preparation as well as one or more
In the event that the technical documentation preparation as well as separate electronic documents, e-mail it / them signed only responsible
more specific electronic documents is done electronically by signing each design.
part, in the same way that no document signed uniqueness.
g) Statement of investors, supervision and performers of electronic
Overview of mandatory formats and modes of verification document format
electronic signature different parts tehničkedokumentacije
Statement investors, professional supervision and the contractor to be
submitted with the project to perform as a confirmation that there were no
a) A copy of an electronic document projektaFormat
deviations during the execution of works prepared in .pdf format and
electronically signed.
Overa
Text excerpts from part of the project (title page, the statement of the
A statement certified by the investor, professional supervision and the
acting technical control of the main-volume), prepared in .pdf format and
contractor on the na- act prescribed by this ordinance.
electronically signed.
Electronic signing is done after the creation of an electronic document
Drawings copy of the project are being prepared, as is- day or more
in a prescribed format (.pdf).
electronic documents in the following formats:
Electronic signing statements are made:
1) .dwg or .dwf (.dwfx) which are electronically signed or 1) responsible person of the investor;
2) .dwg or .dwf (.dwfx) that are not digitally signed, with a supporting 2) responsible person acting professional supervision (entrepreneur
document .pdf format with the same content that is digitally signed.
or legal entity holding the professional supervision);
3) responsible person contractors.
Detailed reports and studies to be submitted with the technical
documentation
Detailed reports and studies prepared in .pdf format and are signed
electronically.
Overa
Elaborate studies and certify persons who were drafted.
Electronic signing is done after the creation of an electronic document
in a prescribed format (.pdf).
Electronic signature surveys or studies carried out:
1) responsible person maker studies or studies (enter- beginners, or
legal entity that has developed a study to Dee or Student);
2) authorized person who prepared the study or studies.
SUMLRNI PRR.PŠD FORMLTA ELPKTRONSKIH OFFERING DOCUMENTS AND ELECTRONIC
SIGNATURE LICAKOJA
and delegations -
graphic dokjms lva n. Jčnna / optionally
------------ ------------ P olgovornn designer
Omcija 1 Yes
1 le ss mrilaže (e
signed)
Option 2 olgovorni designer
Yes Yes
(e (e
signed) not-
signed)
DECLARATION Yes
INVNSTITO (elektronskn
RL signed)
PROFESSIONAL
NLDZORL and P lics responsible investors
Contractor □ Acting responsibly lg loaf! Nalta
(prsduzetni or legal lg that is
carries, the expert natz)
□ - chain by responsible
contractors
-
EJ1LBORLTI I Yes
Studijní (remanded (elektronskn
attached to the signed)
tshničku
doklmetacij})
□ responsible lg slabor maker; or stud
(ireduzetnika, the ratio of the legal
entity who expresses slaborat and
study)
A person or an immediate ovlašIsno j
izralnlo study yl study
Dšitalni Format
Persons who elekgronski signed
You and DSO
.pdf .dwg or, DWF dokumsnt
(.dwfx)
REPORT 0 p- Yes
prsdssdnik komisijs and
hnpčkom (elsktronskn
potlisano) all members of the
PREGLPDU
technical inspection or -
just predssnik
Commission. When the
electronic dokumenl
created by scanning the
original dokumag in
paper form which "is
certified licsicnim
stamps and personally!
signatures
TECHNICAL To Yes Applicant
DOKUMNN- January 1, 2018, if (slektronskn
Thaci polnosilac čahtsva signed)
produced Nijs able to
TSHNIČK) 1 lc will prilažs
I
IIOIIIMCAII documentation
A before 1 delivery in Instead
January formatuDnu ILN elektronsknh
2015. DWF (.dwfx) dokumsnata
YEARS formats, d \ CT or
.d \\ f (.d \\ fh)
dostvl> a ss original
tshnička
lokumsntacija in
paper form
ANNEX 13. - position display panels notification, the situational view,
- typical sections, schedules, details and calculations,
CONTENTS OF THE TECHNICAL DOCUMENTATION FOR
CONSTRUCTION 10) To build a smaller pumping stations, etc. ispravačkih station. not
OBJECTS AND WORKS OF ARTICLE 145. provided for in the planning document, and the function of the building and
LAW ON PLANIRSTRENGTHENING AND DEVELOPMENT OF reconstruction of buildings listed in Annex IV. 5) -9) of this Annex:
SEIZDAJE DECISION ON APPROVAL OF WORKS - technical description and list of publications,
- see the position of the station, on the situational display,
- typical sections, schedules, details and calculations,
1) For auxiliary facilities referred to in Article 2, item 24) of the plan- 11) For reconstruction:
her and construction, except for buildings which, according to the by-law - preliminary design of architecture or design which determines an
prescribes are not necessary to obtain an act of the competent authority: object in space, showing the state that was established on the basis of archival
- preliminary design of the architecture, or design, which specifies project, with the obligatory reference to the archival project or archive a
the object in space (for the objects which are not of the building, for example. project or survey of the current state of the project if the archive does not
ri own well, septic tanks and the like.) with the statement of the designer that exist, for facilities or part of a facility that is covered by papers,
the object satisfies the basic requirements of mechanical resistance and - Conceptual projects by area, depending on the types of papers that
stability, are running,
2) For objects referred to in Article 2, item 24a) of the Law on 12) For adaptation:
planning and the building of, in addition to facilities for which, by-laws, it is - technical description and list of publications,
not necessary to procure an act of the competent authority: - display condition is determined on the basis of archival this
- preliminary design of architecture, with a statement that the projection, with the obligatory reference to the archival project or archive a
responsibility of a designer object meets the basic requirements of project or survey of the current state of the project if the archive does not
mechanical resistance and stability, exist, the object or part of a facility which is covered by RA and codes,
3) For works on capital maintenance of the facility or part (joint work, - architectural basis with display of the tackle of the wall, for the
apartment or other separate part): single room, and includes work which, when such works are performed,
- technical description and list of publications, 13) For Rehabilitation:
4) To remove barriers for people with disabilities: - display condition is determined on the basis of archival this
- technical description and list of publications, projection, with the obligatory reference to the archival project or archive a
5) For the construction and reconstruction of secondary or con- project or survey of the current state of the project if the archive does not
ditional distribution network utility infrastructure and other public spaces exist, the object or part of a facility which is covered curious Vima, with
(parks, squares, car-pedestrian path in open blocks, etc.) Within the existing marked elements and parts of the building and / or installation on which is
street regulation in accordance with the actual situation on the ground: carried out repairs,
- conceptual design that defines the object in space, showing the - Preliminary Design Structure repair, if done rehabilitation of the
state that was established on the basis of archival project, with the obligatory structural elements, or any other preliminary design for the repair, according
reference to the archival project or archive a project or survey of the current to the type of work to be performed,
state if the archival project do not exist, the object or part of the facility which 14) For works on the existing building, and repairing or replacing
included the works: equipment, plant, equipment and installations of the same or lower capacity,
- Conceptual projects by area, depending on the types of papers that but which does not affect the stability and security of the facility, not the
are running, replacement of structural elements that do not affect the safety of adjacent
6) For the planning and reconstruction of roads and other free areas buildings, traffic does not affect fire protection and environmental protection,
to gain importance in the context of their existing regulations, in accordance but that can change the external appearance with the necessary approvals, in
with the actual situation on the ground: order to increase the effectiveness of energy more efficient building:
- conceptual design that defines the object in space, showing the - display condition is determined on the basis of archival this
state that was established on the basis of archival project, with the obligatory projection, with the obligatory reference to the archival project or archive a
reference to the archival project or archive a project or survey of the current project or survey of the current state of the project if the archive does not
state if the archival project do not exist, the object or part of the facility which exist, the object or part of a facility which is covered curious Vima, with
included works marked elements and parts of the building and / or installation on which is
- Conceptual projects by area, depending on the types of papers that carried out repairs,
are running, - conceptual design energy rehabilitation,
7) For the introduction of new types of traffic (trolleybus, the tram 15) To change the use of the facility without the construction works:
network, bicycle paths and the like.) In the regulation of the existing roads in - display condition is determined on the basis of archival this
accordance with the facts on the ground, as well as with drawing or projection, with the obligatory reference to the archival project or archive a
reconstruction of the infrastructure required for the operation of the unit project or survey of the current state of the project if the archive does not
system (underground and overhead power lines , public lighting, signage, exist, objects, or part of a facility that is covered by papers,
etc.) - architectural base with graphical and tabular paper describes zom
- conceptual design that defines the object in space, showing the existing / planned purpose,
state that was established on the basis of archival project, with the obligatory 16) Use change with the construction works:
reference to the archival project or archive a project or survey of the current - display condition is determined on the basis of archival this
state if the archival project do not exist, the object or part of the facility which projection, with the obligatory reference to the archival project or archive a
included works project or survey of the current state of the project if the archive does not
- Conceptual projects by area, depending on the types of papers that exist for the area covered by the work,
are running, - architectural base with graphical and tabular paper describes zom
8) For the reconstruction of the line infrastructure facilities in existing / planned purpose,
accordance with Article 2, item 32a) of the Law on Planning and - depending on the type of work, other activities are coordinated with
Construction: the contents laid down for reconstruction, renovation, repair,
- conceptual design that defines the object in space, showing the 17) For works on separation or merger of the business or living space:
state that was established on the basis of archival project, with the obligatory - in the case of increasing the number of functional units - as well as
reference to the archival project or archive a project or survey of the current for reconstruction,
state if the archival project do not exist, the object or part of the facility which - in the event of reduction in the number of functional units - de-
included works pending on papers as for adaptation or reconstruction,
- Conceptual projects by area, depending on the types of papers that 18) For the installation of the interior installation (gas, electricity,
are running, water, heating, and the like.) In the existing building:
- safety analysis and safety report for facilities vi- rail transport under - display condition is determined on the basis of archival this
Article 26 of the Law on planning and construction, projection, with the obligatory reference to the archival project or archive a
9) slabs to the notification area of 6 m2 and other equipment, project or survey of the current state of the project if the archive does not
- technical description and list of publications, exist for the area covered by the work,
- conceptual design installations that are installed, 10 kV, 20 kV and 35 kV power line, a transformer station type 10/04, 20/04
19) To work on the reconstruction and renovation works zE- lezničke kV and 35 kV and a part of the electricity distribution network (up to 1) of
infrastructure, in terms of the provisions of law that govern the railway the substation 10/04 kV, 20/04 kV and 35/04 kV to the place of connection
infrastructure: to the customer's facility:
- conceptual design that defines the object in space, showing the - technical description and list of publications,
state that was established on the basis of archival project, with the obligatory - position display type substations, one- sno route of medium / low
reference to the archival project or archive a project or survey of the current voltage grid on the layout view,
state if the archival project do not exist, the object or part of the facility which - typical sections, schemes and detailed budgets
included works 24) For the part of the medium-voltage network, which includes the
- Conceptual projects by area, depending on the types of papers that 10 kV and 20 kV and conduit 10 kV and 20 kV switchgears:
are running, - technical description and list of publications,
20) To set up masts and secondary, one- sno distribution parts of the - position display substation or the route of medium-voltage grid
electronic communications network: on the layout view,
- technical description and list of publications, - typical sections, schemes and detailed budgets
- see the position of the stairs, and route electronic communi- cation 25) For smaller pumping stations:
networks on the layout view, - technical description and list of publications,
- typical sections, schedules, details, - see the position of the station, on the situational display,
- budgets are the main structural elements for the purpose of - typical sections, schedules, details and calculations,
fulfillment of the basic requirements for building and general budgets 26) For ski-lift:
installations and equipment, - conceptual design of the route, which determines an object in
21) For individual power distribution and transmission poles: space,
- technical description and list of publications, - Conceptual projects by area, depending on the types of papers that
- see the position of the stairs, and the route elektrodistributiv- or not are running,
the transmission network on the layout view, - safety analysis and safety report for facilities vi- rail transport under
- typical sections, and details of the scheme, Article 26 of the Law on planning and construction,
- budgets are the main structural elements for the purpose of 27) To ski track:
fulfillment of the basic requirements for building and general budgets - conceptual design route of ski trails,
installations and equipment, - conceptual design and landscaping of counter-za- protect the ski
22) For construction and other works on electrical energy facilities slopes,
for the transformation and transmission of electricity (transformer 28) For connections to the existing water supply, sewage, etc. him-
substations, distribution lines and high voltage lines konaponski level of 110 dream. network:
kV and above): - technical description and list of publications,
- investment maintenance, - see the route the connection and the connection point on situacio-
- technical description and list of publications, nom view,
- Construction of single-column high-voltage lines, - typical sections, schedules, details and calculations,
- see the position of the stairs, and the route elektrodistributiv- or not 29) For the compressor unit for gas:
the transmission network on the layout view, - technical description and list of publications,
- budgets are the main structural elements for the purpose of - see the position of the compressor unit, the situational view,
fulfillment of the basic requirements for building and general budgets - typical sections, schedules, details and calculations,
installations and equipment, 30) For devices for the delivery of gas:
- rehabilitation, renovation and reconstruction of high-voltage lines, - technical description and list of works
- Conceptual projects by area, depending on the work performed, - see the position of the device, the situational view,
showing the state that was established on the basis of archival project, with - typical sections, schedules, details and calculations,
the obligatory reference to the archival project or archive a project or a 31) For power plants using renewable energy sources in- estimate the
snapshot of the current situation if the archival project does not exist, the total installed power up to 50 kW:
object or part of the facility which is absorbed by the work, - conceptual design that defines the object in space,
- replacement of ground wire with OPGW cable on visokonapon- - Conceptual projects by area, depending on the types of papers that
skim lines, are running,
- technical description and list of publications, 32) For typical hot water connections:
- situational display of the route covered by the work, - technical description and list of publications,
- typical sections, schedules, details and calculations, - see the route the connection and the connection point on the
- reconstruction of existing substations and switching stations in the situation of that view,
complex - performing motorgrader and other works to increase the number, - typical sections, schedules, details and calculations,
performance of redistribution and deployment of the functional units (the 33) For the construction of masonry fences:
electric field, about energy of the transformer and the relay house) and - technical description and list of publications,
replacement of accessories and equipment for increased capacity, - position the fence on the layout view,
- Conceptual projects by area, depending on the work performed, - the layout fences, typical cross sections, the scheme, the fine detail
showing the state that was established on the basis of archival project, with and calculations,
the obligatory reference to the archival project or archive a project or a 34) To set the electrical charger for electric only as cars, solar panels
snapshot of the current situation if the archival project does not exist, the and assembly-disassembly gangway to vima pathways and streets within the
object or part of the facility which is absorbed by the work, existing regulation:
- adaptation of the existing transformer stations and to the exchange - technical description and list of publications,
of aquatic plants in the complex - the execution of construction works and - see the position of the mounting structure or device, situational
other works on existing structures that are used for installation and Cioni view,
replacement of high-voltage equipment and installations of the same capacity - typical sections, schedules, details and calculations,
without changing the total number of functional units, - preliminary design for construction footbridge,
- Conceptual projects by area, depending on the work performed, 35) To set up the equipment and devices on hydro-meteorological
showing the state that was established on the basis of archival project, with stations on the respective vehicles, setting the pillars on which the half-
the obligatory reference to the archival project or archive a project or a pipe'm going for threading sensors hydro-meteorological station, as well as
snapshot of the current situation if the archival project does not exist, the setting wire security fence around the hydro-meteorological stations:
object or part of the facility which is absorbed by the work, - technical description and list of publications,
- construction of ecological oil pit at substations, - see the situation on the layout view,
- technical description and list of publications, - typical sections, schedules, details and calculations.
- typical sections, schemes and detailed budgets
23) For the part of the medium-voltage network, which includes the
ANNEX 14. (P031M1): Mechanical Engineering, thermo technique, Thermal
Engineering - MP 06-01;
Design which is developed IDEJNOGPROJEKTA AS PART OF
- Projects of technological processes (P031T1): Technology and
OBJECTS UNDER ARTICLE 133 of OPLANIRANJU and
Metallurgical Engineering, Technology and Process Technology - TP 09-01;
construction, which are subject STRUČNOJKONTROLI (AUDIT)
3.2) facilities for the production of biofuels and bioliquids in facilities
only a capacity of over 100 t per year:
- Projects HVAC, thermal energy, processing and gas installations
1) For high dams and reservoirs filled with water, waste and ashes for
(P034M1): Mechanical Engineering, thermo technique, Thermal
which is prescribed technical surveillance:
Engineering - MP 06-01;
- Projects the building structure (P010G1) building regula- jump
- Projects of technological processes (P034T1): Technology and
engineering, construction structures - GP 04-01;
Metallurgical Engineering, Technology and Process Technology - TP 09-01;
- Hydro projects (P010G3): Construction Engineer leadership,
3.3) pipelines and pipelines, gas pipelines nominal working
Hidrotehnika - GP 04 -02; overpressure of over 16 bar, if passes through two or more municipalities, oil
2) For nuclear facilities and other facilities used for the pro- duction storage facilities, liquid petroleum underpants and including derivatives
of nuclear fuel, radioisotopes, irradiation can align wick of radioactive naphth capacity of over 500 t that is built up out of eksploata- CIONI fields
materials and waste materials for scientific purposes -istraživačke: defined by the law governing the mining and geological survey:
(1) Nuclear Facilities: - Projects HVAC, thermal energy, processing and gas installations
- Projects the building structure (P020G1) building regula- jump (P032M1): Mechanical Engineering, thermo technique, Thermal
engineering, construction structures - GP 04-01; Engineering - MP 06-01;
- hydroelectric projects (P020G3): Construction Engineer leadership, - Projects of technological processes (P032T1): Technology and
Hidrotehnika - GP 04 -02; Metallurgical Engineering, Technology and Process Technology - TP 09-01;
- Projects electrical installations and higher midpoint voltage 3.4) Main heating:
(P020E1): Electrical Engineering, The production of the electricity - Projects HVAC, thermal energy, processing and gas installations
transmission - EP 05-02; (P033M1): Mechanical Engineering, thermo technique, Thermal
- Projects Control of Electric Drives - auto- Mathematics, Engineering - MP 06-01;
measurement and control (P020E4): Electrical engineering, electrical - Projects of technological processes (P033T1): Technology and
installations and electrical actuator - or EP 05-01 Electrical engineering, Metallurgical Engineering, Technology and Process Technology - TP 09-01;
electronics and difficult lekomunikacije EP 05-03; 4) For objects of basic and processing chemical industry, ferrous and
- Projects HVAC, thermal energy, processing and gas installations nonferrous metallurgy, facilities for processing leather and fur, facilities for
(P020M1): Mechanical Engineering, thermo technique Thermal Engineering rubber processing, facilities for the production of pulp and paper, and
- MP 06-01; facilities for processing of non-metallic mineral resources that are being built
- Projects of technological processes (P020T1): Technology and outside the mining fields defined by the law governing mining and geological
Metallurgical Engineering, Technology and Process Technology - TP 09-01; exploration, with the exception of facilities for their primary processing of
2.2) facilities which are used for the production of nuclear fuel, ra- decorative and precious stones:
dioizotopa, irradiation, radio-active waste materials and raw materials for - Projects building construction (P040G1) building regula- jump
scientific and research purposes: engineering, Building construction - GP 04-01 or constructed đevinsko
- Projects the building structure (P020G1 or P021G1): Construction engineering, organization and construction technology and project
Engineering, Construction structures - GP 04-01; management in construction - GP 04-04;
- Hydro projects (or P020G3 P021G3) building regula- jump - Projects Control of Electric Drives - auto- Mathematics,
engineering, hydraulic - GP 04-02; measurement and control (P040E4): Electrical engineering, electrical
- Projects electrical installations and higher midpoint voltage installations and electrical actuator - or EP 05-01 Electrical engineering,
(P020E1 or P021E1): Electrical Engineer leadership, production and electronics and difficult lekomunikacije - EP 05-03;
transmission of electricity - EP 05-02; - Projects the means of transport, storage and mechanical
- Projects Control of Electric Drives - auto- Mathematics, construction and Technology (P040M3): Mechanical Engineering, transport
measurement and control (or P020E4 P021E4): Electrical engineering, agents, store and machine technology - MP 06-03;
electrical installations and electrical power-driven - EP 05-01 or Electrical 4.1) Facilities basic and processing chemical industry:
- Projects of technological processes (P041T1): Technology and
Engineering, Electronics and Telecommunications EP 05-03;
Metallurgical Engineering, Technology and Process Technology - TP 09-01;
- Projects HVAC, thermal energy, and the process ga- snih installs
4.2) objects of ferrous and nonferrous metallurgy:
(or P020M1 P021M1): Mechanical Engineering, thermodynamics, thermal
- Projects of technological processes (P042T1): Technology and
and process engineering - MP 06-01;
Metallurgical Engineering, Technology and Process Technology - TP 09-01;
- Projects technological processes (P020T1 or P021T1) tech- nology
4.3) facilities for processing leather and fur:
and Metallurgical Engineering, Technology and Process Technology TP 09-
- Projects of technological processes (P043T1): Technology and
01;
Metallurgical Engineering, Technology and Process Technology - TP 09-01;
3) For the objects for processing of oil and gas that is built up out of
4.4) objects for rubber processing:
ex- sploatacionih fields upon the consent of a ministry responsible for
- Projects of technological processes (P044T1): Technology and
exploitation of minerals, production of biofuels and bioliquids in plants with
Metallurgical Engineering, Technology and Process Technology - TP 09-01;
a capacity exceeding 100 tons per year, and oil pipelines, gas pipelines
4.5) facilities for the production of pulp and paper:
Name- legs working overpressure if more than 16 bar passes over the bases
- Projects of technological processes (P045T1): Technology and
there are two or more municipalities, oil storage of liquefied petroleum gas,
Metallurgical Engineering, Technology and Process Technology - TP 09-01;
and petroleum capacity more than 500 t, that is built up outside the mining
4.6) facilities for processing of non-metallic mineral resources that
field defined by the law governing the r - the economy itself and geological
are being built outside the mining fields defined by law they co-governing
research and the main district heating:
mining and geological research, in addition to facilities for primary
- Projects building construction (P030G1) building regula- jump
processing of decorative and precious stones:
engineering, Building construction - GP 04-01 or constructed đevinsko
- Projects of technological processes (P046T1): Technology and
engineering, organization and construction technology and project
Metallurgical Engineering, Technology and Process Technology - TP 09-01;
management in the construction GP 04-04;
5) For stadiums for 20,000 or more viewers, objects construc- tive
- Management projects electric drives - this automatic teak,
span over 50 m, the objects over 50 m in height, the capacity of the silos over
measurement and control (P030E4): Electrical engineering, electrical
20,000 m ^, Penitentiary of sanctions, facilities for official purposes
installations and electrical actuators 05-01 or EP Electrical engineering,
diplomatic consular pre stavništava foreign countries or offices of
electronics and of telecommunication - EP 05-03;
international organizations in the Republic of Serbia, if it is prescribed by
3.1) facilities for processing oil and gas that are built outside of
bilateral agreements, as well as residential complexes of multifamily housing
explosive atacionih fields prior approval unit of the Ministry responsible for
when the investor is the Republic of Serbia
the exploitation of mineral resources:
5.1) Stadiums for 20,000 spectators and more:
- Projects HVAC, thermal energy, processing and gas installations
- Projects the building structure (P201G1) building regula- jump
engineering, construction structures - GP 04-01; control (P052E4): the Electrical engineering graduates, electrical
5.2) objects construction range of more than 50 m: installations and electrical drive
- Projects the building structure (P202G1) building regula- jump - EP 05-01 or of the Electrical Engineering, Electronics and difficult
engineering, construction structures - GP 04-01; lekomunikacije - EP 05-03;
5.3) buildings over 50 m height: - Projects mechanical installations supply facilities and industrial
- Projects the building structure (P203G1) building regula- jump water, hydraulic and hydro energy (P052M2): Mechanical Engineering,
engineering, construction structures - GP 04-01; Hidrotehnika - MP 06-02;
5.4) silo capacity of over 20,000 m ^: 6.4) power plant - heating plant electric power 10 ^ M and more:
- Projects the building structure (P204G1) building regula- jump - Projects the building structure (P053G1) building regula- jump
engineering, construction structures - GP 04-01; engineering, construction structures - GP 04-01;
- Projects HVAC, thermal energy, processing and gas installations - Projects electrical installations and higher midpoint voltage
(P204M1): Mechanical Engineering, thermo technique, Thermal (P053E1): the Electrical Engineering, Production and transmission of
Engineering - MP 06-01; electricity - EP 05-02;
- Control of Electrical Drives projects this automatic teak, - Projects for electrical drives - auto- Mathematics, measurement and
measurement and control (P204E4): Electrical engineering, electrical control (P053E4): Electrical engineering graduates, electrical installations
installations and electrical actuators - or EP 05-01 Electrical engineering, and electrical drive
electronics and difficult lekomunikacije - EP 05-03; - EP 05-01 or Electrical engineering, electronics and difficult
- Projects the means of transport, storage and mechanical lekomunikacije - EP 05-03;
construction and Technology (P204M3): Mechanical Engineering, transport - Projects mechanical installations supply facilities and industrial
agents, store and machine technology - MP 06-03; water, hydraulic and hydro energy (P053M2): Mechanical Engineering,
- Projects of technological processes (P204T1): Technology and Hidrotehnika - MP 06-02;
Metallurgical Engineering, Technology and Process Technology - TP 09-01; 6.5) electric power lines of 110 and more ^ V:
5.5) Institutes for execution of criminal sanctions: - Projects electrical installations and higher midpoint voltage
- Architectural projects (P205A1): Architecture - AP 02; (P061E1): Electrical Engineering, The production of the electricity
5.6) facilities for official purposes of diplomatic and consular transmission - EP 05-02;
missions of foreign states or offices inter- organization in the Republic of 6.6) transformer stations of 110 and more x:
Serbia, if propisa- no bilateral agreement: - Projects electrical installations and higher midpoint voltage
- Architectural projects (P092A2): Architecture - AP 02; (P062E1): Electrical Engineering, The production of the electricity
5.7) multifamily residential complexes housing when the investor is transmission - EP 05-02;
the Republic of Serbia: 7) For inter-regional and regional water supply facilities and sewage
- Architectural projects (P093A2): Architecture - AP 02; plant for treating water for drinking capacity of more than 200 l / s and a
- Projects building construction (P093G1) building regula- jump plant for waste water with a capacity exceeding 200 l / s
engineering, Building construction - GP 04-01. 7.1) interregional and regional water supply facilities and sewage:
6) For thermal power plants 10 M ^ and more, thermal power plants - Hydro projects (P071G3): Construction Engineer leadership,
- power plants electric power of 10 mW or more and other facilities for Hidrotehnika - GP 04-02;
production of electricity generation capacity of 10 Mw and more, as well as - Projects mechanical installations (P071M2): Mechanical
elektroe- tricity lines substations of 110 and more Engineering, Hydraulic Engineering - MP 06-02 or Civil Engineering,
6.1) hydroelectric dam with the corresponding capacity of 10 M ^ and Hydraulic Engineering - GP 04-02
up: 7.2) plants for treatment of drinking water for over 200 l / s at least:
- Projects the building structure (P050G1) building regula- jump - Hydro projects (P072G3): Construction Engineer leadership,
engineering, construction structures - GP 04-01; Hidrotehnika - GP 04-02;
- Hydro projects (P050G3): Construction Engineer leadership, - Projects mechanical installations (P072M2): Mechanical
Hidrotehnika - GP 04-02; Engineering, Hydraulic Engineering - MP 06-02;
- Projects electrical installations and higher midpoint voltage - Projects of technological processes (P072T1): Technology and
(P050E1): Electrical Engineering, The production of the electricity Metallurgical Engineering, Technology and Process Technology - TP 09-01;
transmission - EP 05-02; 7.3) plant for waste water treatment capacity of more than 200 l / s:
- Projects for electrical drives - auto- Mathematics, measurement and
- Hydro projects (P073G3): Construction Engineer leadership,
control (P050E4): Electrical engineering graduates, electrical installations
Hidrotehnika - GP 04-02;
and electrical drive
- Projects mechanical installations (P073M2): Mechanical
- EP 05-01 or Electrical engineering, electronics and difficult
Engineering, Hydraulic Engineering - MP 06-02;
lekomunikacije - EP 05-03;
- Projects of technological processes (P073T1): Technology and
- Projects mechanical installations supply facilities and industrial
water, hydraulic and hydro energy (P050M2): Mechanical Engineering, Metallurgical Engineering, Technology and Process Technology - TP 09-01;
Hidrotehnika MP 06-02; 8) For regulation works for flood protection of town-tion and rural
6.2) hydropower plant of 10 M ^ and up: areas larger than 300 ha
- Projects the building structure (P051G1) building regula- jump - Hydro projects (P080G3): Construction Engineer leadership,
engineering, construction structures - GP 04-01; Hidrotehnika - GP 04-02;
- Projects electrical installations and higher midpoint voltage 9) For objects within the limits of immovable cultural property of
(P051E1): Electrical Engineering, The production of the electricity exceptional importance and cultural assets registered in the UNESCO list of
transmission - EP 05-02; World Cultural and Natural Heritage, the objects in the protected
- Projects for electrical drives - auto- Mathematics, measurement and surroundings of cultural property of great importance to certain borders of
control (P051E4): Electrical engineering graduates, electrical installations land plots and buildings in the protected surroundings of cultural assets
and electrical drive registered in the list of cultural and natural heritage structures in protected
- EP 05-01 or Electrical engineering, electronics and difficult areas in accordance with the act on the protection of cultural property (except
lekomunikacije - EP 05-03; the transformation of common premises into an apartment or office space in
- Projects mechanical installations supply facilities and industrial the protected environment of cultural h property of exceptional importance
water, hydraulic and hydro energy (P051M2): Mechanical Engineering, and cultural assets registered in the World Heritage List), as well as facilities
Hidrotehnika - MP 06-02; within the boundaries of the national park and legs facilities within the
6.3) a thermal power plant 10 M ^ and up: boundaries of a protected natural asset of great importance (except for family
- Projects the building structure (P052G1) building regula- jump houses,
engineering, construction structures - GP 04-01; 9.1) Facilities within the limits of immovable cultural property of
- Projects electrical installations and higher midpoint voltage exceptional importance and cultural assets registered in the list of world
(P052E1): the Electrical Engineering, Production and transmission of cultural and natural heritage and facilities in protected surroundings of
electricity - EP 05-02; cultural property of great importance to certain borders of land plots and
- Projects for electrical drives - auto- Mathematics, measurement and buildings in the protected surroundings of cultural assets registered in the
UNESCO list of World Cultural and Natural Heritage : 13.1) passenger port and airport:
- Architectural projects (P090A1): Architecture - AP 02; - Projects the building structure (P120G1) building regula- jump
9.2) facilities within national parks and facilities within boundaries engineering, construction structures - GP 04-01;
of a protected natural asset of outstanding Na tea (except for family houses, - Projects roads (P120G2): Civil Engineering, Traffic (roads and
agricultural and economic facilities and their infrastructure facilities that are railways) and other infrastructure facilities - GP 04-03 or Civil Engineering,
being built in the villages), in accordance with the law: organization and construction technology and project management in
- For buildings, architectural projects, and other projects of construction - GP 04-04;
importance to the protected natural area, depending on the type of object that - Hydro projects (P120G3): Construction Engineer leadership,
is being built, for which requires a license for the development of technical Hidrotehnika - GP 04-02;
documentation for facilities for which building permits issued by the ministry - Projects the means of transport, storage and mechanical
in charge of construction, ie competent authority of autonomous province, in construction and tehnologaje (P120M3): Mechanical Engineering, transport
accordance with sub-legal regulation (P091A1): 300 (chief designer architect means, storage, and machine technology - MP 06-03;
tectonic projects, Planning of free space and internal plumbing and sewage 13.2) harbor
system), or other appropriate licenses, depending on the type of facility being - Projects the building structure (P121G1) building regula- jump
built; engineering, construction structures - GP 04-01;
- For engineering structures, projects, depending on the types of 13.3) marine
facilities that are being built, for which requires a license for the development - Projects the building structure (P122G1) building regula- jump
engineering, construction structures - GP 04-01;
of technical documentation for the objects for which the building permit is
14) For state roads first and second class, traveling facilities and
issued by the ministry responsible for građevinar-, leadership and the
traffic connections to these roads and border crossings
competent authority of the autonomous province, in accordance with sub-
14.1) state roads of first and second order and the connections of the
regulation ;
traffic on these roads and border crossings:
9.3) facilities in protected areas in accordance with the Act on the
- Projects roads (P131G2): Civil Engineering, Traffic (roads and
Protection of Cultural Property (except the transformation of common
railways) and other infrastructure facilities - GP 04-03 or Civil Engineering,
voluntary rija to the apartment or office space in the protected surroundings
organization and construction technology and project management in
of cultural property of outstanding significance and cultural assets registered
construction - GP 04-04;
in the World Heritage List)
- Projects of traffic and traffic signals (P131S1): Traffic Engineering,
- Architectural projects (P090A2): Architecture - AP 02.
Road Transport (integral and the indoor traffic) - SP 07-01;
10) For a plant for the treatment of hazardous waste, incineration or
14.2) road structures (bridges) for state roads of first and second
chemical treatment capacity of more than 70 tons per day
order, road facilities and road connections to these roads and border
- Projects HVAC, thermal energy, processing and gas installations
crossings:
(P102M1): Mechanical Engineering, thermo technique, Thermal
- Projects building construction (P132G1) building regula- jump
Engineering - MP 06-01;
engineering, Building construction - GP 04-01 or constructed đevinsko
- Projects of technological processes (P102T1): Technology and
engineering, organization and construction technology and project
Metallurgical Engineering, Technology and Process Technology - TP 09-01;
management in construction - GP 04-04;
11) For the facilities for treating hazardous waste by incineration,
14.3) road infrastructure (tunnels) for state roads of first and second
thermal and / or physical, physico - chemical, the procedures of chemical, as
order, road facilities and road connections to these roads and border
well as the central store and / or landfill for hazardous waste disposal
crossings:
- Projects HVAC, thermal energy, processing and gas installations
- Projects building construction (P133G1) building regula- jump
(P100M1): Mechanical Engineering, thermo technique, Thermal
engineering, Building construction - GP 04-01 or constructed đevinsko
Engineering - MP 06-01;
engineering, organization and construction technology and project
- Projects of technological processes (P100T1): Technology and
management in construction - GP 04-04;
Metallurgical Engineering, Technology and Process Technology - TP 09-01;
15) For the public railway infrastructure with connections and
12) For airports for public air transport
subways
12.1) building construction on the airport complex (put- Nick
15.1) public railway infrastructure with connections
terminals, freight terminals, air force bases - hangars, infrastructure facilities
- Projects roads (P141G2): Civil Engineering, Traffic (roads and
and facilities for radio - navigation equipment):
railways) and other infrastructure facilities - GP 04-03 or Civil Engineering,
- Architectural projects (P111A1): Architecture - AP 02;
organization and construction technology and project management in
- Projects building construction (P111G1) building regula- jump
construction - GP 04-04;
engineering, Building construction - GP 04-01 or constructed đevinsko
- Projects of traffic and traffic signals (P141S1): Traffic Engineering,
engineering, organization and construction technology and project
Road Transport (integral and the indoor traffic) - SP 07-01;
management in construction - GP 04-04;
- Projects electrical installations and higher midpoint voltage
- Projects electrical installations of low and midpoint voltage
(P141E1): Electrical Engineering, The production of the electricity
(P111E2): Electrical Engineering, N ENERGY Elektroe- installation and
transmission - EP 05-02;
electric motor drive - EP 05-01;
- Projects Control of Electric Drives - auto- Mathematics,
- Projects telecommunication networks and systems (P111E3):
measurement and control (P141E4): Electrical engineering, electrical
Electrical Engineering, Electronics and Telecommunications
installations and electrical actuator - or EP 05-01 Electrical engineering,
- EP 05-03;
electronics and difficult lekomunikacije - EP 05-03;
- Projects for electrical drives - auto- Mathematics, measurement and
- Projects machine parts switches, railway equipment and accessories
control (P111E4): Electrical engineering graduates, electrical installations
(P141M4): Mechanical Engineering, Transport medium stva, warehouses
and electrical drive
and machine technology - MP 06-03;
- EP 05-01 or Electrical engineering, electronics and difficult
15.2) facilities in public railway infrastructure with connections
lekomunikacije - EP 05-03;
(bridges):
12.2) civil engineering works at the airport complex (auxiliary
- Projects building construction (P142G1) building regula- jump
annually - runways, taxiways, apron, Han- garske platforms):
engineering, Building construction - GP 04-01 or constructed đevinsko
- Projects roads (P112G2): Civil Engineering, Traffic (roads and
engineering, organization and construction technology and project
railways) and other infrastructure facilities - GP 04-03 or Civil Engineering,
management in construction - GP 04-04;
organization and construction technology and project management in
15.3) facilities in public railway infrastructure with connections
construction - GP 04-04;
(tunnels):
- Projects electrical installations in the lighting system Airport
- Projects building construction (P143G1) building regula- jump
(P112E5): Electrical Engineering, Electrical installation and electrical drive
engineering, Building construction - GP 04-01 or constructed đevinsko
- EP 05-01;
engineering, organization and construction technology and project
- Projects of traffic and traffic signals (P112S1): Traffic Engineering,
management in construction - GP 04-04;
Road Transport (integral and the indoor traffic) - SP 07-01;
15.4) Metro:
13) For passenger pier, port, dock and marina
- Projects building construction (P144G1) building regula- jump
engineering, Building construction - GP 04-01 or constructed đevinsko
engineering, organization and construction technology and project
management in construction - GP 04-04;
- Projects roads (P144G2): Civil Engineering, Traffic (roads and
railways) and other infrastructure facilities - GP 04-03 or Civil Engineering,
organization and construction technology and project management in
construction - GP 04-04;
- Projects of traffic and traffic signals (P144S1): Traffic Engineering,
Road Transport (integral and the indoor traffic) - SP 07-01;
- Hydro projects (P144G3): Construction Engineer leadership,
Hidrotehnika - GP 04-02;
- Projects electrical installations and higher midpoint voltage
(P144E1): Electrical Engineering, The production of the electricity
transmission - EP 05-02;
- Projects for electrical drives - auto- Mathematics, measurement and
control (P144E4): Electrical engineering graduates, electrical installations
and electrical drive
- EP 05-01 or Electrical engineering, electronics and difficult
lekomunikacije - EP 05-03;
- Projects HVAC, thermal energy, processing and gas installations
(P144M1): Mechanical Engineering, thermo technique, Thermal
Engineering - MP 06-01;
16) For electronic communications facilities or networks, systems or
resources that are of international or trunk Na tea and those that are built on
the territory of two or more units of the local government:
16.1) objects of electronic communications, and network, or systems
they co-agents that are of international or regional importance:
- Design of the facilities of electronic communications, and network,
or system resources (P150E3): Electrical engineering graduates, in electronic
equipment - EP 05-03;
16.2) electronic communications facilities or networks, systems or
equipment that is built on the territory of two or more local self-government:
- Projects of electronic communications facilities or networks,
systems or equipment (P151E3): Electrical engineering graduates,
Electronics and Telecommunications - EP 05-03.
17) For hydro facilities on waterways
- Hydro projects (P160G3): Construction Engineer leadership,
Hidrotehnika - GP 04-02;
18) For navigable canals and locks that are not in consistence vu
hydropower system
- Projects the building structure (P170G1) building regula- jump
engineering, construction structures - GP 04-01 or Gradual đevinsko
engineering, hydraulic - GP 04-02;
- Hydro projects (P170G3): Construction Engineer leadership,
Hidrotehnika - GP 04-02.
19) For regional landfill or landfills for non-hazardous waste to the
area populated with over 200,000 inhabitants
- Projects the building structure (P180G1): Construction
Engineering, Construction structures - GP 04-01 or Civil Engineering,
Hidrotehnika - GP 04-02 or Civil Engineering, Traffic (roads and railways),
and other infrastructure facilities - GP 04-03 or Building Engineer leadership,
organization and construction technology and management to projects in
construction - GP 04-04;
- Hydro projects (P180G3): Construction Engineer leadership,
Hidrotehnika - GP 04-02;
- Projects of technological processes (P180T1): Technology and
Metallurgical Engineering, Technology and Process Technology - TP 09-01.
20) for facilities for the production of energy from renewable sources
with power of 10 M ^ and up
20.1) power plants, the obnovlji- from renewable sources with power
of 10 ^ M, and more
- Projects the building structure (P191G1) building regula- jump
engineering, construction structures - GP 04-01;
- Projects HVAC, thermal energy, processing and gas installations
(P191M1): Mechanical Engineering, thermo technique, Thermal
Engineering - MP 06-01;
- Projects of technological processes (P191T1): Technology and
Metallurgical Engineering, Technology and Process Technology - TP 09-01;
- Projects electrical installations and higher midpoint voltage
(P191E1;
- Projects for electrical drives - auto- Mathematics, measurement and
control (P191E4): Electrical engineering graduates, electrical installations
and electrical drive
- EP 05-01 or Electrical engineering, electronics and difficult
lekomunikacije - EP 05-03;
20.2) other facilities for the production of energy from renewable
sources of energy capacity of 10 MW or more
- Projects the building structure (P190G1) building regula- jump
engineering, construction structures - GP 04-01;
- Projects HVAC, thermal energy, processing and gas installations
(P190M1): Mechanical Engineering, thermo technique, Thermal
Engineering - MP 06-01;
- Projects of technological processes (P190T1): Technology and
Metallurgical Engineering, Technology and Process Technology - TP 09-01;
- Projects electrical installations and higher midpoint voltage
(P190E1): Electrical Engineering, The production of the electricity
transmission - EP 05-02;
- Projects Control of Electric Drives - auto- Mathematics,
measurement and control (P190E4): Electrical engineering, electrical
installations and electrical actuator - or EP 05-01 Electrical engineering,
electronics and difficult lekomunikacije - EP 05-03;
21) For objects that are intended for the production of weapons and
military equipment to the law governing the production of arms and military
equipment, as well as facilities for the production and stockpiles wick
explosives
- Architectural projects (P206A1): Architecture - AP 02;
- Projects building construction (P206G1) building regula- jump
engineering, Building construction - GP 04-01 or constructed đevinsko
engineering, organization and construction technology and project
management in the construction GP 04-04
- Projects electrical installations for high-voltage and the midpoint
(P206E1): Electrical Engineering, N ENERGY Elektroe- installation and
electric motor drive - EP 05-01;
- Projects electrical installations of low and midpoint voltage
(P206E2): Electrical Engineering, N ENERGY Elektroe- installation and
electric motor drive - EP 05-01;
- Projects HVAC, thermal energy, processing and gas installations
(P206M1): Mechanical Engineering, thermo technique, Thermal
Engineering - MP 06-01;
22) For health care facilities over the accommodation capacity of 500
beds
- Architectural projects (P207A1): Architecture - AP 02;
23) For buildings constructed in the territory of two or more local
governments offered the only nica
- Projects depending on the types of facilities that are being built, for
which requires a license for preparation of technical documentation of the
structure for which the building permit issued by the ministry in charge of
construction, or the competent authority of an autonomous province, in
accordance with the bylaw.