REF: KEP / 759 / 2024 Date: 30/04/2024

CLIENT : M/s Al Bonian FM


SITE : The Meydan Hotel,
LOCATION : Dubai
REVISION : 0

Kind Attn : Mr. Mohammed Aslam


Mail ID : aslam.b@albonian.fm

Project:

Civil works @ Novo Cinema IBN Megaplex, Dubai, U.A.E

Subject:

Quotation for Civil works @ Novo Cinema IBN Megaplex, Dubai, U.A.E.

Greetings from Kepler Technical Service Est.

Thank you for giving us the opportunity,


We are pleased to submit the best competitive price for your kind evaluation and consideration.

Hope this quotation meets your requirements; awaiting a positive and prompt response from your end to
proceed with the work by assuring the best quality on time.

For any further clarifications and concerns please feel free to contact us. We can assure you the best
service at a reasonable value in the set time frame.

Please find the below system-based price for your reference.

Total Amount for Civil works @Novo Cinema IBN Megaplex, Dubai, U.A.E. AED 1,362,195.00

VAT@5% AED 68,109.75

Final Total AED 1,430,304.75

AED One million four hundred thirty thousand three hundred four and seventy-five fills Only

Kindly find the following BOQ for your reference,

+971 54 2799224 keplerdubai@outlook.com Page 1


SCOPE OF WORK:
PHOTOS OF EXISTING/
SLNO DESCRIPTION QTY UNIT RATE TOTAL
NEW
PRELIMINARIES

1 site mobilization, de-mobilization works. 1 Lsm 6500 6500

Supply scaffolding for high-level tasks


2 1 Lsm 4500 4500
according to the site's specifications.

SEATS REPLACEMENTWORKS

Cinema 16 requires removal of seating


1 and complete rectification & 159 No's 330 52470
replacement of cloth & Dunlop

Cinema 19 requires removal of seating


2 and complete rectification & 200 No's 330 66000
replacement of cloth & Dunlop

SUM TOTAL1 129470

PHOTOS OF EXISTING/
SLNO DESCRIPTION QTY UNIT RATE TOTAL
NEW
CARPETWORKS

Remove the Existing carpets from the


1 Lobby area floor and dispose of them at 2400 SQ.MT 20 48000
the Dubai Municipality yard.

Option 1:
Supply and installation of the customized
2 floor carpet as per the client's design and 2400 SQ.MT 440 1056000
measurement ( Same Like Existing
Carpet)

SUM TOTAL2 1104000

+971 54 2799224 keplerdubai@outlook.com Page 2


PHOTOS OF EXISTING/
SLNO DESCRIPTION QTY UNIT RATE TOTAL
NEW
DIMMING PANEL

1 Removal of Existing Dimming Panel 2 NO'S 350 700

Supply and Installation of Phase dimming


2 2 NO'S
module 5AX4 (Make: Lite-Puter)

Supply and Installation of Wall mount


3 2 NO'S 8000 16000
keypad

4 Programming, Testing & Commissioning 1 NO'S

SUM TOTAL3 16700

PHOTOS OF EXISTING/
SLNO DESCRIPTION QTY UNIT RATE TOTAL
NEW
WATERPROTECTION SS STAND
Supply of Movable stand with 4 legs &
plain ss sheet ( 2 mt L x 2 mt W x 1.7 mt
1 3 NO'S 980 2940
height 4 ms steel Legs) in the projection
area.

MDF CEILING RECTIFICATION WORKS


Removal of existing damaged MDF &
replace with laminated mdf chipboard
1 1 Lsm 2200 2200
with proper finishing in the screen 5( 3.62
mt L x 1.10 mt W)

+971 54 2799224 keplerdubai@outlook.com Page 3


LIGHTS REPLACEMENT WORKS
removal existing damged down light &
1 Supply & installation of 120W 230v 16 No's 390 6240
dimmable down light

Step light Aluminum full set supply &


2 50 No's 450 22500
installation cinema 16 & 19 – 50pc, 12v

DIFFUSERREPLACEMENT WORKS

60 X60 AC Diffuser with powder quoted


1 for cinema 16 & 19 –8pc, Supply and 8 No's 380 3040
installation

DAMAGED CEILING RECTIFICATION WORKS

Remove existing damaged ceiling and


provide new gypsum ceiling in the Lobby
1 95 Sq.mt 110 10450
area infront of screen 17, 18 & 19.( 8 mt
W x 9 mt L)

Supply & apply 2 coat primer & 2 coat half


2 white paint in the Lobby area infront of 95 Sq.mt 55 5225
screen 17, 18 & 19.( 8 mt W x 9 mt L)

Rectification of damaged 20mm Gypsum


3 ceiling including joint tapping works in 15 Sq.mt 120 1800
projection area of screen 17 & 18.

Supply & apply 2 coat primer & 2 coat


4 grey paint in projection area of screen 17 80 Sq.mt 55 4400
& 18.

+971 54 2799224 keplerdubai@outlook.com Page 4


DAMAGED CEILING RECTIFICATION WORKS

Rectification of damaged 60x60 ceiling


and supply & installation of 20mm
5 10 Sq.mt 140 1400
thickness half white 60x60 Rockfon in
projection area of screen 5 (3 mt x 2 mt)

Supply & Apply 2 coat primer & 2 coat


6 white paint in projection area of screen 5 18 Sq.mt 45 810
(7.5mt x 2 mt)

Supply & Apply 2 coat primer & 2 coat


7 Grey paint in projection area of screen 5 18 Sq.mt 55 990
(7.5mt x 2 mt)

Supply & fixing of Rockfon celling Grey


Colour “1” need to complete
8 replacement in Cinema 16 (only 470 No's 35 16450
changing of 60 x 60 Acoustic Rockwool
Panels
Supply & fixing of Rockfon celling Blue
Colour “1” need to complete
9 replacement in Cinema 19 (only 610 No's 35 21350
changing of 60 x 60 Acoustic Rockwool
Panels )

Cinema 18 total 240 pc Rockfon celling


10 Red Colour “1” need to complete 240 No's 35 8400
replacement.

Cinema 17 total 20 pc Rockfon celling


11 Grey Colour “1” need to complete 20 No's 35 700
replacement.

+971 54 2799224 keplerdubai@outlook.com Page 5


DAMAGED CEILING RECTIFICATION WORKS

Cinema 17 total 9 pc Rockfon celling


12 Black Colour “1” need to complete 9 No's 35 315
replacement.

Cinema 18 exit corridor false stain mark


13 Rockfon celling white Colour 9pc “1” 9 No's 35 315
need to complete replacement.

Cinema 19 stain mark on wall Equisetic


14 panel need to be replace Supply & 1 No's 2500 2500
Installation.

SUM TOTAL4 112025

TOTAL AED 1,362,195.00

VAT@5% AED 68,109.75

Final Total AED 1,430,304.75

AED One million four hundred thirty thousand three hundred four and seventy-five Only

Payment Terms:

 70% of advance against the contract value.

 20% of progress payment,

 10% of Payment after the work completion

 Quotation Validity is 15 Days only,

 Payment should be CDC.

 If the payments terms are not made as agreed, we reserve the right to stop the work on site.

Notes & Exclusions:

+971 54 2799224 keplerdubai@outlook.com Page 6


 Any Local Authority Approval/Charge Excluded.
(RCD/FEWA / TRAKEES/DU/ETISALAT/DCD/RTA/MUNICIPALITY etc.)

 If any other additional works other than the above scope shall be treated with additional
cost.

 Entry Site Access/Passes, permit from authority, any approvals, Permission to enter the site
will be by Client.

 Any power, Fire Protection, IT, DATA, Emergency Lighting and Music System related work
excluded.

 Annual Maintenance Contract was Excluded,

 Quantity is determined based on the client. Any disparities between the specified quantity
and the actual on-site conditions will result in adjustments to the quotation.

 Any Civil/Core Cutting Work Excluded.

 We only consider one DB and one SMDB for modification; any new supply of DB and
SMDB is excluded from consideration.

 supply & installation of Steel Floor Grating was Excluded.

 All measurements and quantities are subject to verification.

 Client should allot separate location for material storage,

 Option 1 carpet same as an existing carpet and It’s customized one so it’s Little bit
Expensive,

 option 2 carpet is like the existing carpet 50% of matching.

 Dimming Panel Existing is not available so we suggested new Dimming panel.

 Acoustic self-adhesive 60x60 Rockhole replacing only we considered.

Thanks & Regards

Authorized Signatory,

+971 54 2799224 keplerdubai@outlook.com Page 7