Professional Documents
Culture Documents
TG Crusher - Shinile
TG Crusher - Shinile
1. Background .................................................................................... 4
2. Project Rationale........................................................................... 5
0. Executive Summary
This Proposal is prepared with the objective of establishing a stone crushing
and screening plant project for the production of different types of crushed
stones on a total of area of 20 hectare (quarry site and crushing plant)
located at Shinile Wereda of Sity Zone, Somali Region.
At full capacity operation, the plant will be capable of producing 120 Tons of
Crushed Stones per day. Products include: Crushed stone (02); Crushed
stone (01) and Crushed stone (00).
Our market study and prior experience in the industry show that there is a
huge unsatisfied demand for our project’s products in our target market
segments of Shinile Wereda and neighboring Weredas of Somali Region.
In addition to its financial viability and economic benefits, the project will
generate revenue to the government in the form of taxes over the life of the
project. Further, the project shall provide about 24 permanent workers with
different job title and up to 20 temporary workers.
1. Background
Ethiopia is considered as one of the fastest growing economies in Africa this
is apparent by fast growing and booming construction industry all over the
country. This lead to the increasing requirement of building and construction
materials in various ways with the development of the housing industry, and
the demand will also increase in proportion to the diversified dwelling.
Currently the demand is met through import and one local factory.
Investment, both public and private, being the driving force for
development, has been given utmost importance by the Government of
Ethiopia. Investment offices at federal and regional level have been
established to encourage, promote and coordinate investment activities. The
federal investment proclamation No. 15/1992 has been amended every time
to widen the scope of participation of private investment and to make the
system of administration transparent and efficient. Both at federal and
regional levels, many incentives have been permitted to encourage both
domestic and foreign investors.
The construction industry has been helped by the fact that some of its
chemical elements already exist in Ethiopia, for instance the availability of
locally manufactured cement and availability of sweet sands have helped to
reduce the demand imported ones. To reduce the dependence on foreign
resources, an industry to supply the plastering and finishing goods have to
be established. This will not only support the local market but also to
generate foreign currency through export.
2. Project Rationale
Construction Materials Manufacturing is an important industrial sector in the
country. Over the last 10 years, the Construction sector has been registering
strong growth rates in the country.
In addition, the project will realize the derived benefits that include creation
of employment and contribute to the government treasury in the form of
taxations
4. Market Analysis
The target market for our products are Hollow Blocks manufacturers,
Concrete manufacturers and other building and road contractors in Shinile
Wereda and neighboring Weredas of Somali Region.
The quantity of production of the products during the period 2015 - 2022 is
shown in the following Table. During the period under reference, the supply
of crushed stones which constitutes only domestic production, averaged at
3.05 million tons, with an average increment rate of 9.01%/year.
2015 2,208,441
2016 2,427,125
2017 2,637,557
2018 2,894,718
2019 3,148,585
2020 3,400,157
2021 3,687,130
2022 4,041,095
Average 3,055,601
Growth rate 9.01%
Source: CSA, Statistical Abstract, various years
In estimating the current effective local demand (for the year 2024) for our
products, it is assumed that the above mentioned target market areas will
constitute at least 15% of the total national demand.
2025 593,727
2026 647,222
2027 705,537
2028 769,106
2029 838,402
2030 913,942
Average 716,084
Our study results showed that the currently operating local producers are
not only little in number but also are operating at a relatively smaller
capacities. As such, we have estimated the local supply to reach 360,000
tons per year assuming there are 10 stone crushing plants in our target
market areas, each of which are assumed to operate at a capacity of 120
tons per day.
Hence, it can well be concluded that the proposed project is feasible and can
well serve in fulfilling the existing demand gap at least to some extent.
The following figure shows major departments in the Company. Overall the
plant requires 24 work forces.
6. Plant Capacity
Based on demand projection indicated in the market study, the suggested
plant capacity for shall be 120 tons per day.
The project will start operation by using its 70% capacity in the first year
then attaining 85% and 100% capacities by the second and third year of
operation respectively.
7. Project Financials
7.5. Utilities
The total annual expenditure on utilities is, thus, about Birr 1.37 million.
Annual requirement and cost of utilities is indicated in Table below.
Total approximate manpower required for the business operations along with
the respective salaries are given in the table below:
Table: Depreciation
Depreciation Original value Annual Dep.
Description
rate (Birr) (Birr)
Office Furniture &
0.10 1,000,000.00 100,000.00
Fixture
Machineries &
0.10 30,389,870.56 3,038,987.06
Equipment
Total Fixed
31,389,870.56 3,138,987.06
Investment
Operating expenses
3 months 2,858,340.17
Total required working
capital
3,280,440.17
Description Total
0 30,389,871
1 6,077,974 3,798,734 24,311,896
2 6,077,974 3,038,987 18,233,922
Total Cash in
34,670,311 19,986,493 25,170,433 30,354,374 35,000,853 40,082,867
flow
Cash out flow
Replacement 0 0 0 0 0
loan repayment 6,077,974 6,077,974 6,077,974 6,077,974 6,077,974
Capital
31,389,871 - - - - -
Expenditure
Working capital 3,280,440 - - - - -
Pre-operating
expenses and
interest
Total Cash out
34,670,311 6,077,974 6,077,974 6,077,974 6,077,974 6,077,974
flow
Net Cash Flow 0 13,908,518 19,092,459 24,276,400 28,922,878 34,004,893
Cash balance 17,188,959 36,281,418 60,557,818 89,480,697 123,485,590
ASSETS 0 1 2 3 4 5
Current Assets
Cash 3,280,440 17,188,959 36,281,418 60,557,818 89,480,697 123,485,590
Other Current
0 0 0 0 0
Assets
Total Current
3,280,440 17,188,959 36,281,418 60,557,818 89,480,697 123,485,590
Assets
Fixed Asset
Office Furniture
1,000,000.00 900,000 800,000 700,000 600,000 500,000
and Fixture
Machineries &
30,389,870.56 27,350,884 24,311,896 21,272,909 18,233,922 15,194,935
Equipment
Vehicles 0.00 0 0 0 0 0
Total Fixed
31,389,871 28,250,884 25,111,896 21,972,909 18,833,922 15,694,935
Asset
Total Asset 34,670,311 45,439,842 61,393,314 82,530,728 108,314,619 139,180,525
LIABILITIES
Short term
- - - - - -
liability
Long term
liability (Bank 30,389,871 24,311,896 18,233,922 12,155,948 6,077,974 0
Loan)
Sub Total 30,389,871 24,311,896 18,233,922 12,155,948 6,077,974 0
CAPITAL
Owner's Equity 4,280,440 4,280,440 4,280,440 4,280,440 4,280,440 4,280,440
Retained
0 16,847,506 38,878,952 66,094,339 97,956,205 134,900,085
Earnings
Earnings 16,847,506 22,031,446 27,215,387 31,861,865 36,943,880
Sub Total 4,280,440 21,127,946 43,159,392 70,374,779 102,236,645 139,180,525
Total Liability &
34,670,311 45,439,842 61,393,314 82,530,728 108,314,619 139,180,525
Capital
Net Worth 4,280,440 21,127,946 43,159,392 70,374,779 102,236,645 139,180,525
8. Environmental Impacts
This section discusses major environmental issues and constraints that can
arise from the project implementation. Positive, negative, Direct, indirect
and cumulative impacts are addressed.
8.1. Scoping
The scoping process intends to ensure that the EIA focuses on pertinent
issues. In pursuit of deciding upon the boundaries and sensitivity of the
study area for the project and drawing the list of activities and impacts to be
studied during the assessment, the consultant has carried out an initial
environmental examination and scoping.
Since the project site is located within the industrial zone of the city,
specifically demarcated for similar and related processing categories, there
are no human settlements at the nearer distance of the project. Therefore,
the consultant has focused on biological and physical components found
Based on the scoping process particular attentions have been given to the
following environmental issues:
Generation of dusts
Dry waste and
Employee’s health hazard and safety
The major positive impacts of the proposed project are mainly the economic
and social benefits that can be acquired at the national, regional and local
level. Although reversible and localized, the adverse impacts of the proposed
project arise from generation of dusts and employee’s heath impact.
Thus, the project will be an opportunity for the town by lightening the brunt
of unemployment in the town to some extent. Moreover, the building
renovations phase of the project will have a short term employment
opportunity particularly for the local laborers.
As there will be high demand for daily laborers during construction phase of
the project, it will be twofold advantages to hire laborers from local people.
First, the project promoter will reduce time of searching for laborers and
save his money that is needed for transportation of laborers to project site.
Second, fairly distributing the benefits of the project will enhance project
social acceptability in general.
There are both environmental pollution sources and human health hazards
that can be caused by the production process of the Crushed Stones. These
production process environmental aspects can be summarized as:
Solid wastes
generation of dust and nuisance noises from operation of machineries
generation of dusts and
Employee health hazard
In this context, the operation of the stone crushing and screening plant
facility will actually contribute significantly to the overall air quality.
Activities inside the repairs and mechanical workshop of the factories may
cause oil contamination risks to the land. In addition, there may be risks to
the workers, including exposure to fumes, injury with sharps etc.
General occupational health risks exist throughout the enterprise from noise,
dusts, or machineries operation.
leaving offices is the other managerial proposed option for minimizing the
problem.
The company top management and affiliated units of the Somali Region
Environmental Protection Authority, such as technical divisions of
Environmental Pollution Research, control and impact assessment core
process will make occasional and random monitoring, respectively. The
monitoring will involve both quantitative and qualitative data, as appropriate
to the nature of the information which will involve during the production
stage of the project.
generation of income for the local community, and it also paves the way for
rural development in the area.
On the other hand, the proposed project has some associated environmental
aspects that might cause adverse impacts. However most of these
environmental effects can be reduced to acceptable levels with
implementation of pollution prevention and control techniques. Therefore, it
can be concluded that there will be no severe or irreversible adverse impacts
that will prevent the implementation of the proposed pa[er products
processing project.