Professional Documents
Culture Documents
Meet Patel 8th Sem Report
Meet Patel 8th Sem Report
Meet Patel 8th Sem Report
Submitted By
Name Enrollment No.
PATEL 210120106515
MEET
[May, 2024]
I
Gujrat Technological University GIT
Gandhinagar Institute of Technology
Moti Bhoyan Road, Gandhinagar, Gujarat
(Affiliated with GTU)
CERTIFICATE
2023-2024 and his/her work is satisfactory. This student has successfully completed all
II
Gujrat Technological University GIT
III
Gujrat Technological University GIT
COMPLETION CERTIFICATE
IV
Gujrat Technological University GIT
Gandhinagar Institute of Technology
Moti Bhoyan Road, Gandhinagar ,Gujarat
(Affiliated with GTU)
DECLARATION
We hereby declare that the Internship report submitted along with the
Internship entitled OBSERVATION STUDY OF RESIDENTIAL
BUILDING submitted in partial fulfillment for the degree of Bachelor of
Engineering in Civil Engineering to Gujarat Technological University,
Ahmedabad, is a bonafide record of the original project work carried out by
me at HAPPY DESIGN under the supervision of Mr. Ronak Kadiya and that
no part of this report has been directly copied from any students’ reports or
taken from any other source, without providing due reference.
PATEL MEET.
V
Gujrat Technological University GIT
Acknowledgement
I have taken efforts in this Internship. However, it would not have been possible
without the kind support and help of many individuals and organizations. I would like to
extend my sincere thanks to all of them.
I am highly indebted to Prof. Paresh Umredkar for their guidance and constant
supervision as well as for providing necessary information regarding the Internship. I take
this opportunity to thank all my friends and colleagues who started me out on the topic
and provided extremely useful review feedback and for their all-time support and help in
each and every aspect of the course of my project preparation. I am grateful to my college
Gandhinagar Institute of Technology, for providing me with all the required resources
and a good working environment.
I would like to express my gratitude towards the Head of the Department, Prof. Neel
Shah, and Director, Dr H N Shah for their kind co-operation and encouragement which
help me in this Internship.
Thank You
Patel Meet.
VI
Gujrat Technological University GIT
Content
Title Page I
Certificate II
Certificate III
Completion Certificate IV
Declaration V
Acknowledgement VI
Content VII
List of Figures IX
1.1 History 1
3.2 Purpose 5
3.3 Objective 6
3.4 Scope 6
VII
Gujrat Technological University GIT
3.6.3 Roles and Responsibilities 10
4.1.1 Column 12
4.1.2 Staircase 19
4.1.3 Beam 22
4.1.4 Slab 27
Masonry Work
4.1.5 31
Finishing Work
4.1.6 36
System Design
Chapter 5 39
System Design and Methodology
5.1 39
Structural Design
5.2 40
Implementation
Chapter 6 47
6.1 47
Implementation Platform
6.2 48
Result Analysis
Chapter 7 49
Testing
7.1 49
Cube Test
7.2 50
Result
Chapter 8 51
Problems and Solutions
Chapter 9 55
Conclusion
Chapter 10 56
References
VII
Gujrat Technological University I GIT
LIST OF FIGURES
Fig 1.1 Location Map
1
Fig 1.3 Organization Chart 2
Fig 2.2 Schematic Layout Which Shows The Sequence of Operation for 4
Manufacturing of End Product
Fig 3.1 Column Coupler 8
IX
Gujrat Technological University GIT
Fig 4.16 Make guidepost 32
X
Gujrat Technological University GIT
XI
Gujrat Technological University GIT
LIST OF TABLES
XII
Gujrat Technological University GIT
Project id 452432
CHAPTER – 1
1.1 HISTORY
Established in the year 1998, Happy Design is considered to be Gujarat’s most
trusted real estate developer! Their portfolio consists of many landmark projects
in the residential, commercial, and institutional sector.
They Having served in the field of real estate development for over 5 decades,
they have consistently proven to give out classy designs and adhere to quality
parameters. With many projects to show for, Happy Design has indeed carved a
niche when it comes to constructing inspirational infrastructure. The future of
Happy Design will see more aggressive planning on future projects that add value
to the lives of people as well as to the development of the nation.
Over the years the Vasani family has worked together and stood through many
challenges to successfully deliver redefining projects which have been designed,
planned and executed on time, considering the profitability and full customer
satisfaction.
Office Address :
Site Address :
1
Gujrat Technological University GIT
Project id 452432
BUILDER
PROJECT MANAGER
HARSHAL BHATT
SENIOR ENGINEER
RUSHABH PRAJAPATI
JUNIOR ENGINEER
JIGNES UMARALIYA
SUPERVISOR
PANKAJ DESASI
2
Gujrat Technological University GIT
Project id 452432
CHAPTER – 2
OVERVIEW OF DIFFERENT DEPARTMENT
DEPARTMENT
2. ARCHITECHTURAL DEPARTMENT
The work carried out by the architect have to be properly organized. This demands
to keep the records of different contracts, the details of the project, the cost and the
budget details, the time limit and the day-by-day progress report. Most of the cases
the architects have to work with the civil or structural engineers for communication
and discussion relating the technical issues faced in the design and the
implementation.
3. SURVEYING DEPARTMENT
The surveyor is who is supposed to make precise measurement that will identify the
boundary. Surveyors help in providing unique contours on the surface of the earth
which will let the engineers to make maps and construction projects.
3
Gujrat Technological University GIT
Project id 452432
4. CONSTRUCTION DEPARTMENT
SITE
EXCAVATION PCC FOUNDATION
CLEARANCE
FRAME MASONRY
EARTH FILLING PCC
STRUCTURE WORK
B. U.
FINISHING READY TO
PERMISSION &
WORK POCESSION
N.O.C. LETTER
4
Gujrat Technological University GIT
Project id 452432
CHAPTER - 3
INTRODUCTION TO INTERNSHIP
3.1 INTERNSHIP SUMMARY
The main aim of internship project was to investigate to how a structure is
constructed within its desired properties. We get knowledge about the basic &
advanced techniques of building construction as well as saw the challenges which a
civil engineer have to face during construction. i.e. labour problems, cost
management, environmental challenges etc.
3.2 PURPOSE
The aim of this report is apprise you the practical experience gained by us program.
To get knowledge about the structural drawing & design specification.
Study the detailed drawing available at site & co-related it with the ongoing site
work.
Observation of safety practices followed at site.
Understand the quality material and time management at the site.
Understand the quantity calculation of concrete and steel.
5
Gujrat Technological University GIT
Project id 452432
3.3 OBJECTIVE
To understanding the importance of quantity, material safety of site, plans &
drawing and time management.
To have an exposure to field as an aspect of civil engineer.
To Co-relate theoretical knowledge to practical on construction site.
3.4 SCOPE
An Internship Provides Real Life Experience and Exposure.
An internship enables you to gain first-hand exposure of working in the real world.
It also allows students to harness the skill, knowledge, and theoretical practice they
learnt in university.
You can acquire endless amounts of education in your life, however, that knowledge
doesn't always translate to the working life.
Many different types of structures and components of structures can be built using
reinforced cement concrete slabs, walls, beams, columns, foundations, frames and
more.
6
Gujrat Technological University GIT
Project id 452432
Mixing of concrete :
In self loading concrete mixer, the function of the drum is to mix the raw
materials homogenously. A continuous supply of water makes sure that the
machine is working normally and the level of water is maintained in the
concrete. These drums are usually fitted with spiral blades. The drums are
designed to rotate at high speed. For mixing, rotation of the drum is fixed
in one direction. During mixing, the spiral blade pushes the concrete
materials deep into the drum. This high-speed rotation makes sure for
homogenous mixing of materials in concrete.
Tilting drum concrete mixer mixes the ingredients while forward rotating,
and discharges while reversing the concrete mixer drum. Tilt drum
concrete mixer is often used to blend plastic and semi dry concrete.
Transporting of Concrete :
Compacting of Concrete :
Curing of Concrete :
Water curing is the process where an uninterrupted flow of water is carried out
over the surface of the concrete. This is done so that there is no water loss from
the concrete surface. This effective curing method is executed by spraying or
sprinkling water or even curing agents over the concrete surface.
7
Gujrat Technological University GIT
Project id 452432
Couplers are used in reinforced concrete structures to replace normal rebar lap
joints.
The use of Couplers can simplify the design and construction of reinforced
concrete and reduce the amount of reinforcement required.
The ends of steel bars to be joined are provided with threads, and a coupler is used
to join rebars end-to-end, which transfers the loads on the rebar across the
connection. They are more efficient than lap splices because they do not depend
on the concrete for load transfer.
2. Soil Testing
Soil testing is one of the most critical steps in the construction site development
process. It involves the assessment of the composition and the condition of the
8
Gujrat Technological University GIT
Project id 452432
soil
9
Gujrat Technological University GIT
Project id 452432
on site. The test is done to evaluate the soil’s structural integrity and determine
whether it can hold the weight of the proposed building, its water drainage
capability, and how well it can withstand harsh climatic conditions in the future.
Soil testing is a legal and inescapable step in site development.
Unfortunately, if the soil is marked as unsuitable, there’s no other choice but to
look for a different site
3. Site Clearing
Before construction begins, the ground needs to be clear and completely leveled.
This means clearing any trees that may be on it and any underground utilities that
may hinder the construction process. Sometimes, the site may even have buildings
in good condition. These need to be demolished and cleared from the site.
4. Site Investigation
Site investigation is similar to soil testing only that this time, the geotechnical
investigators do it to evaluate rock composition and groundwater conditions on
the site to determine how the foundation of the proposed project should be built.
10
Gujrat Technological University GIT
Project id 452432
INTERNSHIP EFFORT -
4. Be resourceful
11
Gujrat Technological University GIT
Project id 452432
12
Gujrat Technological University GIT
Project id 452432
CHAPTER – 4
SYSTEM ANALYSIS
4.1.1 COLUMN :
An RCC Column is a vertical member that transfers the load from the beam and
slabs onto the foundation.
Steps involving Construction of RCC columns:
In this stage, the situation of columns is determined realistically in the field. It’s
done by birthing rope in keeping with grids shown within the column-making
drawing below.
In the drawing, column locations are shown associated with grid-line with
dimensions. Realistically, in-field, ropes are our grid-lines. Thus, we tend to place
columns associated with rope-line by calculating dimensions shown within the
drawing.
Starter marking :
Starter is generally a casting of concrete material with equivalent width and length
of column section and comparatively smaller height of around 10 cm. It is cast in
such a manner that equal cover is left encircling the reinforcement bars of column
and then shuttering of column is provided. The main purpose of starter is to fine-
tune the form work of a column vertically to maintain sufficient gap among
column reinforcement and shuttering.
13
Gujrat Technological University GIT
Project id 452432
To retain the exact position of the columns in the below slab as well as retain the
column lines in number of floors easily, starter is marked.
1. Check for the diameter and also ensure the numbers of vertical bars
2. Spacing between vertical bars
3. Check Development length that depends on the diameter of the bar
4. Lapping in alternate bars ought to return at the same height.
5. Lapping mustn’t return within beam or block.
6. Lapping ought to be at l/3 or 2l/3 of the column as per structural notes
7. Spacing between the stirrups should be considered as per the drawing
8. The hook ought to be bent properly at right angles.
9. Check the stirrups corner. The vertical bar ought to return at the right-angle
fringe of stirrup properly certain with binding wire.
14
Gujrat Technological University GIT
Project id 452432
3. Column formwork :
There are two types of formworks are used :
1. Plywood Formwork :
15
Gujrat Technological University GIT
Project id 452432
2. Steel Formwork :
This consists of panels fabricated out of thin steel plates stiffened along the
edges by small steel angles. The panel units can be held together through
the use of suitable clamps or bolts and nuts.
The panels can be fabricated in large numbers in any desired modular
shape or size. Steel forms are largely used in large projects or in a situation
where large number reuses of the shuttering are possible. This type of
shutter is considered most suitable for circular or curved structures.
16
Gujrat Technological University GIT
Project id 452432
17
Gujrat Technological University GIT
Project id 452432
4. Pouring of Concrete :.
At this site, they are used manually concreting method and for
18
Gujrat Technological University GIT
Project id 452432
19
Gujrat Technological University GIT
Project id 452432
4.1.2 STAIRCASE
RCC staircase is the one of the important components of structure which provide
access between two floors.
According to work arrangement laying of RCC staircase can be done in three stages
:
1. Formwork
2. Reinforcement work
3. Pouring of concrete
1. Formwork
The most important step when building concrete stairs is to use a proper
formwork. The angle of flight, dimensions of thread and riser are to be properly
checked. Usually while constructing a stair attached to wall, the line of flight ,
thread and risers are marked on the wall for proper fixing of shuttering or
formwork.
The boards must be at least 2” thick, as to support the weight of the concrete. The
wooden boards are used to create the steps and are fastened with several screws to
the lateral structure of the formwork.
20
Gujrat Technological University GIT
Project id 452432
The concrete steps are to be reinforced with steel bars so as it carries the loads
coming upon the stairs and transfer them to the ground. The number of steel bars
and size of the bars is to be calculated by a structural engineer depending upon the
loads coming on the stairs.
These steel reinforcement bars are placed in the formwork with minimum of 25
mm spacing and is tied together.
3. Pouring of concrete
Pouring of concrete into the formworks is started from the below part to above.
The concrete mix plays an important role in strength and durability of stairs. It is
recommended to use a concrete vibrator while pouring the concrete to completely
fill the gaps of the stairs and to avoid the honeycomb formation.
This work is to be carried out with great care and patience , as any sudden
movements can disturb the alignment of the formworks or even collapse the
formwork.
21
Gujrat Technological University GIT
Project id 452432
Landing = l × b × h
22
Gujrat Technological University GIT
Project id 452432
4.1.3 BEAM
• According to work arrangement laying of RCC beam can be done in four stages :
2. Formwork
3. Reinforcement
The slab is continuous over a number of beams. The slab is supported by 2.5 cm
sheathing that runs parallel to the majority of the beams.
Normally, the sheathing is supported by wooden battens spaced appropriately
between the beams.
The battens could also be propped up against the joists in the middle of the span to
reduce deflection. 3 cm thick sheathing is employed in the side forms of the beam.
23
Gujrat Technological University GIT
Project id 452432
2. Beam formwork :
Beam formwork is generally formed with either timber or metal panels. In this
type of formwork, the process is to produce a box surrounded with frames at the
perfect size of the beam and fasten it firmly on the kicker left from base or at the
last phase of beam concreting.
3. Beam reinforcement :
Necessary reinforcement detailing such as size and number of longitudinal
reinforcements and its required length, number and spacing of stirrups are
provided in structural drawings.
24
Gujrat Technological University GIT
Project id 452432
25
Gujrat Technological University GIT
Project id 452432
4.1.4 SLAB
Concrete slab is horizontal structural member which provides flat and useful
surfaces.
According to work arrangement laying of RCC slab can be done in three stages :
1. Formwork
2. Reinforcement work
3. Pouring of Concrete
1. Slab formwork :
Slab Formwork essentially consists of a horizontal load-bearing structure which
supports the form lining and transfers the forces into the shoring.
2. Slab reinforcement :
After preparation is completed, steel bars are placed into their positions with the
provision of specified spacings and concrete cover.
26
Gujrat Technological University GIT
Project id 452432
27
Gujrat Technological University GIT
Project id 452432
5. autoclaving
6. packing line
One of the most important parts of aaac wall is the foundation. This is the support
for your wall, and the trench size will depend on the width and height of your
masonry wall. For reference, you will need a half a meter deep trench for a aac
wall up to one meter in height. Make sure you check the measurements before
digging as a solid trench is essential to prevent your wall from collapsing.
Once you have your foundation, you need to set up gauging rods to ensure your
brickwork is consistently level. Set up a string line from one gauging rod to the
other. This will be for your second row of bricks, as the first string will be sitting
in the trench. Make sure the line is straight and level with no sag.
28
Gujrat Technological University GIT
Project id 452432
The mortar should slip easily from your shovel, although the mixture should be
firm enough to hold its shape. Only mix what you need and don't let the mortar sit
for more than an hour or two. Soak the bricks in water and let them drip dry. This
will ensure that they bond correctly with the mortar. Although, make sure that
there is no water running off the bricks as it can make the mortar too wet.
29
Gujrat Technological University GIT
Project id 452432
Grab the next brick and add mortar to the short edge before placing it down hard up
against the first brick. Repeat the process for the first course.
4. Second course
Start the row by placing the cut brick down on a bed of mortar. Make sure your
string line is in the right place, and the brick meets the string. Place the next brick,
check that it is flush and continue. Repeat the process until you have completed
the second course.
30
Gujrat Technological University GIT
Project id 452432
1. Internal Plastering :
The maximum thickness for internal plaster should be between 12-15mm for
internal & 20-25mm for external walls.
The first coat (chatt) should be of 5-6mm thick. Hit the first coat gently with a
trowel (thappi) for better binding between plaster and wall.
Cement mortar mix for plaster must be consumed within 30-45 minutes because
the setting time of mortar starts after 1hr.
31
Gujrat Technological University GIT
Project id 452432
32
Gujrat Technological University GIT
Project id 452432
CHAPTER – 5
SYSTEM DESIGN
5.1 STRUCTURAL DESIGN AND METHODOLOGY :
33
Gujrat Technological University GIT
Project id 452432
1. Architectural drawings
2. Structural Drawings
5. Miscellaneous Drawings
1. Architect Drawings :
3. Location Drawings
4. Location Plan
34
Gujrat Technological University GIT
Project id 452432
35
Gujrat Technological University GIT
Project ID : 289525
CHAPTER – 6
IMPLEMENTATION
Tasks :
Finalize pre-construction activities including project agreement
financial, contractual, and interconnection.
Realize interconnection
Implementation Activities:-
Pre-construction
Project kick-off
Contractexecution
Change control
Interconnection
36
Gujrat Technological University GIT
Project ID : 289525
Project Construction
Chang control
Commissioning
6 .2 RESULT ANALYSIS
Specifications are used for the following objectives :
3. Expressing the type of material such as timber type and bricks type etc.
37
Gujrat Technological University GIT
Project ID : 289525
CHAPTER – 7
TESTING
Cube Test of Concrete is one of the most important tests done on concrete. It is also
known as a test to determine the Compressive Strength of Concrete. This single test is
enough to do a quality check on the type of concreting that is being done at site.
The factors that determine the Compressive Strength of Concrete are Water Cement ratio,
Cement Strength, Quality of concrete material and the quality control that is being done
during production of concrete.
38
Gujrat Technological University GIT
Project ID : 289525
7.2 RESULT :
Weig
Dimension of Tested Avg.
ht of
Sr Sample Grad Comp Comp Comp
CC
No e of Date of Date of load St. St.
Cube
L B H Conc Casting Testing (kN) (N/m (N/m
(g)
(mm) (mm) (mm) rete m2 ) m2 )
1. 150.53 150.98 151.24 8480 588.20 25.88
150.67 151.08 151.37 M25 05/03/23 19/03/23 8540 610.65 26.82 25.81
149.60 150.24 150.68 8442 558.10 24.73
2. 150.37 151.29 150.68 8565 580.96 25.71
148.67 151.27 150.83 M25 05/03/23 19/03/23 8750 618.67 27.50 26.63
150.58 150.47 150.38 8557 604.70 26.68
3. 149.80 150.91 151.24 8588 579.88 25.65
M25 05/03/23 19/03/23 27.49
39
Gujrat Technological University GIT
Project ID : 289525
CHAPTER – 8
PROBLEMS &
SOLUTIONS
Problem - 1
• Slurry of cement in concrete separates while casting of starter
due to excessive water in mix of concrete.
Solution :
• Managing of w/c ratio while making of concrete or for level try
to do packing so that slurry doesn’t separates or comes out from
the gap.
40
Gujrat Technological University GIT
Project ID : 289525
Problem - 2
• Steel bars are not same as drawing design for C9 column due
to lack of workmanship.
Solution :
• There have rearrange the steel bars as per drawing.
41
Gujrat Technological University GIT
Project ID : 289525
42
Gujrat Technological University GIT
Project ID : 289525
43
Gujrat Technological University GIT
Project ID : 289525
CHAPTER – 9
As a civil engineering student, I took internship at Happy Design with active participation
in superstructure work and learned the construction process, estimation of various
components of structure, team work and developed multiple skills like communication
with higher authorities, engineers, contractors, workers and also labors.
s_ The working period at “ASPIRA” was very informative. It helps me to connect with the
field and exposed us to new opportunities. Training of 12 weeks exposed me to various
construction activities. I participated and observed various activities. The training period
helped me to relate our academic knowledge with field practice. It helped to understand the
challenges and opportunities in
44
Gujrat Technological University GIT
Project ID : 289525
CHAPTER – 10
REFRENCES
IS 800-2007
IS 875-1984
IS 1893-2002
https://www.THE HAPPY DESIGN.co.in/
https://housing.com/buy-aspira-by-shreeji-devlopers-in-tragad-ahmedabad-pid-
270240 https://theconstructor.org/building/12-basic-components-building-
structure/34024/ https://happho.com/basic-components-building-structure/
https://www.maramani.com/blogs/home-design-ideas/building-construction-process
45
Gujrat Technological University GIT